22-026 Change Order dated 2-3-23 Granite Rock CCO 7 Memorial Park PondsMEMORIAL PARK POND REPURPOSING PROJECT
PROJECT NO. 2022-03
CONTRACT CHANGE ORDER
DATE:2/3/2023 CCO# 7
Contractor:
P.O.# 2022‐540
Acct. # 280‐99‐254 900‐905
Granite Rock Company
5225 Hellyer Avenue, Ste 220
Sna Jose, CA 95138
Change
No.Cost
7
$4,677.34
The following changes are hereby approved, notwithstanding language in any attachment to the contrary, Contractor agrees
that the amount paid pursuant hereto is full and complete compensation for the work described herein for each and every
entity involved in the project who is being compensated hereunder and that each and every claim for any cost for schedule
impact such as a delay, impact, inefficiency, acceleration, extended overhead, increased supervision, compression and all
other factors affecting cost arising from the subject of this Change Order is hereby released and waived by all such
Subcontractors and suppliers at all tiers.
Description
Install 4'x4' 5" Concrete Pad
City Authorization
Type and No.
Email dated
December 14, 2022
Page 1 CCO 7 Memorial Park Ponds 02‐03‐2023
MEMORIAL PARK POND REPURPOSING PROJECT
PROJECT NO. 2022-03
CONTRACT CHANGE ORDER
Cost
Total Project:
Original Contract $1,324,207.00
CCO 1 $4,716.62
CCO 2 $224,382.36
CCO 3 $5,509.80
CCO 4 $4,414.22
CCO 5 $5,200.48
CCO 6 $8,000.00
CCO 7 $4,677.34
==============
Revised Contract Total Change Orders $256,900.82
Schedule Impact:
This CCO 14
All CCO 28
Completion Date:
Orig
Revised
REVIEWED BY: APPROVED BY:
City of Cupertino City of Cupertino
Ayano Hattori Chad Mosley
City Project Manager Interim Director of Public Works
ayanoh@cupertino.org chadm@cupertino.org
Date:Date:
CSG Consultants Granite Construction Company
Nourdin Khayata Kevin Jones
Construction Manager Area Manager
nourdin@csgengr.com kjones@graniterock.com
Date:Date:
11/5/2022
10/8/2022
$1,581,107.82
Removal and disposal of second concrete slab under north and south
ponds.
Removal of approximately 200 L.F of abandoned asbestos pipe
Calendar Days
Install new conduits and wiring and connect to existing pull boxes to
restore lighting at Memorial Park
Modify and adjust irrigation components per Instructional Bulletin #1
dated 8/30/22
Relocate, maintain and remove Temp Fencing
Remove Rocks from Soil area
Install 4'x4', 5" Concrete Pad
Change Order No.7
Page 2 CCO 7 Memorial Park Ponds 02‐03‐2023
Kevin Jones
Feb 6, 2023
Feb 6, 2023
nourdin khayata
Feb 6, 2023
Feb 6, 2023
February 3rd, 2022
Ayano Hattori
Project Manager
Public Works
City of Cupertino
10300 Torre Avenue
Cupertino, CA 95014
RE: Memorial Park Ponds Repurposing Project
Change Order Request
Statue Pad
Dear Ms. Hattori,
Attached is the price to install a 4 foot square pad 5” thick onsite.
Total price is: $4,677.34
If you have any questions, feel free to give me a call at (831) 332-8714
Sincerely,
Graniterock Company
Kevin McDermott
(831) 332-8714
DATE: 2/3/2023
1
JOB NAME: Cupertino Memorial Park Ponds Repurposing
PROPOSAL SUMMARY
(Last Update: 11/5/20)
Graniterock Proposal No:
Markup Labor 15%
Markup Equipment 15%
Markup Materials 15%
Markup Subs 10%
OPERATION AMOUNT
Operation #001: Dig, compact, form and
pour 4'x4'x5" concrete pad $ 4,608.22
Operation #002:$-
Operation #003:$-
Operation #004:$-
Bond @ 1.5%$ 69.12
TOTAL $ 4,677.34
OP 1-20 Subtotals
Labor Subtotal $ 2,376.62
Equipment Subtotal $ 671.60
Materials Subtotal $ 460.00
Subs Subtotal $ 1,100.00
Grand Total $ 4,608.22
Granite Rock CCO 7 Memorial Park Ponds
Final Audit Report 2023-02-06
Created:2023-02-03
By:Julia Kinst (juliak@cupertino.org)
Status:Signed
Transaction ID:CBJCHBCAABAAMOgdJghcg2MOV6dfy-mxDDsv9v-lF1cI
"Granite Rock CCO 7 Memorial Park Ponds" History
Document created by Julia Kinst (juliak@cupertino.org)
2023-02-03 - 9:33:48 PM GMT- IP address: 216.198.111.214
Document emailed to kjones@graniterock.com for signature
2023-02-03 - 9:35:00 PM GMT
Email viewed by kjones@graniterock.com
2023-02-03 - 9:52:48 PM GMT- IP address: 172.226.212.16
Signer kjones@graniterock.com entered name at signing as Kevin Jones
2023-02-06 - 6:54:07 PM GMT- IP address: 68.113.60.178
Document e-signed by Kevin Jones (kjones@graniterock.com)
Signature Date: 2023-02-06 - 6:54:09 PM GMT - Time Source: server- IP address: 68.113.60.178
Document emailed to Ayano Hattori (ayanoh@cupertino.org) for signature
2023-02-06 - 6:54:11 PM GMT
Email viewed by Ayano Hattori (ayanoh@cupertino.org)
2023-02-06 - 6:54:31 PM GMT- IP address: 104.47.74.126
Document e-signed by Ayano Hattori (ayanoh@cupertino.org)
Signature Date: 2023-02-06 - 6:54:52 PM GMT - Time Source: server- IP address: 73.162.56.125
Document emailed to nourdin@csgengr.com for signature
2023-02-06 - 6:54:54 PM GMT
Email viewed by nourdin@csgengr.com
2023-02-06 - 7:15:48 PM GMT- IP address: 98.248.42.52
Signer nourdin@csgengr.com entered name at signing as nourdin khayata
2023-02-06 - 7:16:18 PM GMT- IP address: 98.248.42.52
Document e-signed by nourdin khayata (nourdin@csgengr.com)
Signature Date: 2023-02-06 - 7:16:20 PM GMT - Time Source: server- IP address: 98.248.42.52
Document emailed to Chad Mosley (chadm@cupertino.org) for signature
2023-02-06 - 7:16:21 PM GMT
Julia Kinst (juliak@cupertino.org) added alternate signer Jimmy Tan, P.E. (jimmyt@cupertino.org). The original
signer Chad Mosley (chadm@cupertino.org) can still sign.
2023-02-06 - 9:39:36 PM GMT- IP address: 216.198.111.214
Document emailed to Jimmy Tan, P.E. (jimmyt@cupertino.org) for signature
2023-02-06 - 9:39:37 PM GMT
Email viewed by Jimmy Tan, P.E. (jimmyt@cupertino.org)
2023-02-06 - 9:40:19 PM GMT- IP address: 104.47.73.254
Document e-signed by Jimmy Tan, P.E. (jimmyt@cupertino.org)
Signature Date: 2023-02-06 - 9:41:19 PM GMT - Time Source: server- IP address: 64.165.34.3
Agreement completed.
2023-02-06 - 9:41:19 PM GMT