20-137 Service Order No. 21 dated 7-10-23 CSG Pumpkin Fiesta Storm Drain CM & Inspection CITY OF CUPERTINO
MASTER AGREEMENT CONSULTANT SERVICES
SERVICE ORDER NO.
MASTER AGREEMENT #:MA Date:
Maximum Compensation:
Consultant:Firm Name:
Address:
Contact: Ph:
Email Address:
Project Name:
Description: (simple project description if appropriate)
Attachment A: Includes Description of Project, Scope of Service, Schedule of Performance
and Compensation
City Project Management
Managing Department: Public Works Project Manager:
Fiscal/Budget :
SO Acc't #:PO #:
Project #:Date:
Approvals:
Date:
Date:
Appropriation Certification: I hereby certify that an unexpended appropriation is available in the above
fund for the above contract as estimated and that fund are available as of this date of signature
City Finance:Date:
Consultant:
Manager:
Management Analyst
Master Agreement Maximum Compensation:
Master Agreement Unencumbered Balance:
Total Previously Encumbered to Date:
MA End Date:
Encumbrance this Service Order:
City of Cupertino Master Agreement Service Order
2021-011 10/22/2020
$938,045.00 12/30/2023
CSG Consultants
550 Pilgrim Dr, Foster City, CA 94404
Nourdin Khayata 650.522.2524
Pumpkin Fiesta Storm Drain Construction Management & Inspection
Suyesh Shrestha
$938,045.00
$805,892.50
$ 89,850.00
$ 42,302.50
210-99-256 900-905
SC 005.03.02
tbd
7/7/2023
21
nourdin@csgengr.com
4
4
Jul 8, 2023
Jul 10, 2023
Jul 10, 2023
550 Pilgrim Drive
Foster City, CA 94404
phone 650.522.2500
fax 650.522.2599
www.csgengr.com
FOSTER CITY | PLEASANTON | SAN JOSE | SACRAMENTO | NEWMAN | FRESNO | PASO ROBLES | ORANGE
May 10, 2023
John Raaymakers, PE
Senior Project Manager
10300 Torre Avenue
Cupertino, CA 95014
Re: Inspection and Construction Management Services for the Pumpkin Fiesta Storm Drain Project
CSG Consultants, Inc. (CSG) would like to thank the City of Cupertino (City) for the opportunity to present its
proposal to provide inspection and construction management services for the Pumpkin Fiesta Storm Drain
Project (Project).
S COPE OF WORK
We understand the project scope involves Replacement of various existing storm drain structures. This includes 36”
Reinforced Concrete Pipe, Box culverts with sizes of 4’x2’, 7’x3’, and 7’x4’, a pre-cast box culvert, and approximately
850’ of various cast-in-place structures. The Project duration is 90 working days, and the work is primarily in
residential areas.
The Project will be Awarded May 16, 2023 with an anticipated start date in mid-June. Due to the limited budget City
requested part-time inspection and construction management services.
PROPOSED STAFF
For this project, CSG proposes Nourdin Khayata as the main point of contact. His contact info is as follows:
Nourdin Khayata, PE | VP, Construction Management
(650) 522-2524 Office | nourdin@csgengr.com E-Mail
Jim Mazzone will be assigned as the main inspector on this project. However, due to the timing and the part
time inspection requested by the City, CSG will assign other inspectors to help cover the work when Mr.
Mazzone is assigned to other projects. Mr. Khayata will be the CM through the project duration. Material
Testing is not part of this proposal.
COST
CSG stands ready to provide the requested services for this project. Provided below is the proposed fee.
We look forward to working with the City of Cupertino on this project. If you have any questions regarding our
proposal, please contact Mr. Khayata at (650) 522-2524.
Sincerely,
Nourdin Khayata, PE
Vice President, Construction Management
Employee Hourly
Rate
Working
Days
Hours per
Day Total Hours Cost
Jim Mazzone
Inspector $170 90 4 360 $61,200
Nourdin Khayata
CM $190 90 1.5 135 $25,650
Contingency $3,000
TOTAL COST $89,850
Service Order 21 CSG Pumpkin Fiesta Storm
Drain CM & Inspection
Final Audit Report 2023-07-10
Created:2023-07-07
By:Julia Kinst (juliak@cupertino.org)
Status:Signed
Transaction ID:CBJCHBCAABAATzBAHIVKd89Ytrk-5NG834DpHoZRpEia
"Service Order 21 CSG Pumpkin Fiesta Storm Drain CM & Inspe
ction" History
Document created by Julia Kinst (juliak@cupertino.org)
2023-07-07 - 9:03:29 PM GMT- IP address: 98.97.58.57
Document emailed to nourdin@csgengr.com for signature
2023-07-07 - 9:04:19 PM GMT
Email viewed by nourdin@csgengr.com
2023-07-08 - 10:32:26 AM GMT- IP address: 172.224.248.63
Signer nourdin@csgengr.com entered name at signing as Nourdin Khayata
2023-07-08 - 10:33:17 AM GMT- IP address: 176.88.127.210
Document e-signed by Nourdin Khayata (nourdin@csgengr.com)
Signature Date: 2023-07-08 - 10:33:19 AM GMT - Time Source: server- IP address: 176.88.127.210
Document emailed to Chad Mosley (chadm@cupertino.org) for signature
2023-07-08 - 10:33:21 AM GMT
Email viewed by Chad Mosley (chadm@cupertino.org)
2023-07-10 - 4:15:12 PM GMT- IP address: 64.165.34.3
Document e-signed by Chad Mosley (chadm@cupertino.org)
Signature Date: 2023-07-10 - 4:15:39 PM GMT - Time Source: server- IP address: 64.165.34.3
Document emailed to Julia Kinst (juliak@cupertino.org) for signature
2023-07-10 - 4:15:42 PM GMT
Document e-signed by Julia Kinst (juliak@cupertino.org)
Signature Date: 2023-07-10 - 4:58:46 PM GMT - Time Source: server- IP address: 98.97.58.57
Agreement completed.