CC 10-10-2023 Item No. 9. McClellan Road Separated Bike Corridor, Phase 3 Project_Supplemental Report      CITY COUNCIL STAFF REPORT  SUPPLEMENTAL 1  Meeting: October 10, 2023    Agenda Item 9    Subject  Award a construction contract for the McClellan Road Separated Bike Corridor Phase 3  Project to Redgwick Construction Company for improvements at the intersection of De  Anza Boulevard and McClellan Road/Pacifica Drive and approve a budget modification  in the amount of $975,000.    Recommended Action  1. Award a construction contract for the McClellan Road Separated Bike Corridor,  Phase 3 Project (Project 2020‐12) in the amount of $1,569,386 to Redgwick  Construction Company;  2. Authorize the City Manager to execute the contract when all conditions have  been met;  3. Authorize the Director of Public Works to execute any necessary construction  change orders up to a construction contingency amount of $156,938.60 (10%) for  a total contract amount of $1,726,324.60; and  4. Adopt Resolution No. 23‐XXX approving budget modification #2324‐304,  approving a transfer of $948,551.46 from the Capital Improvement Fund (budget  unit 420‐99‐036 900‐905, ST 047) to the Transportation Fund (budget unit 270‐99‐ 269 900‐905) and approving a transfer of $975,000 within the Transportation  Fund from Senate Bill (SB) 1 Capital Outlay (budget unit 270‐85‐821 900‐971) to  the project (budget unit 270‐99‐269 900‐905), for a total authorized project  expenditure of $2,299,410.    Background:    Staff’s responses to questions received from councilmember are shown in  italics.          Q1: Can you point me to details of how the Bike Corridor will look?  I am  having a hard time visualizing separated bike lanes at the very wide and very  busy intersection of McClellan and D Anza. (Mohan)  Staff response: Attached is the aerial plan view of McClellan Phase 3.    Attachments Provided with Original Staff Report:  A. Draft Contract  B. Draft Resolution  Attachments Provided with Supplemental 1:   C. Plan View