BLD-2021-0780 Inspection RecordINSPECTION RECORD
CITY HALL
10300 Torre Avenue • Cupertino, CA 95014-3255
PHONE 408-777-3228
WWW.CUPERTINO.ORG
BUILDING ADDRESS: 10511 GLENCOE DR Cupertino APN: 326 30 103 PERMIT NO: BLD-2021-0780
OWNER'S NAME: PAPADOPOULOS JOHN TRUSTEE OWNER'S PHONE: Not Provided
CONTRACTOR: J BUILDING INC, 31375 SANTA FE WAY UNION CITY CONTRACTOR PHONE:
DATE ISSUED 11/1/2023 8:55:58 AM ISSUED BY:VALUATION: $150000
JOB DESCRIPTION
TO CLEAR CODE CASE - CONVERT (E) ATTACHED GARAGE INTO ADU (495 SF); REMODEL KITCHEN (278 SF); REMODEL BATHROOM (213 SF); REMODEL OTHER (1168 SF); (2) NEW SUB-
PANEL (100 AMP); (2) TANKLESS WATER HEATERS REV #1 - BATHROOM DIMENSIONS CHANGED FOR BATHROOMS #1, #2, AND ADU-APPROVED 3/3/2022 REV#2-REVISE RISE DROP
BEAM OF CEILING; NEW CEILING JOISTS ABOVE ADU AND MASTER SUITES (S1,S2,SD0,SD1) - APPROVED 05/18/2022 REV#3 - REMOVE BRICK VANEER AND REPAIR THE DAMAGED
STUCCO AT FRONT AND SIDE (1000 SF); RE-DESIGN ENTRY COVERED PORCH ; RELOCATE THE ELECTRICAL SUB-PANEL (100 AMP) FROM ADU TO HALLWAY OF MAIN HOUSE-
APPROVED 3/31/2023 REV#4 - UPDATE LOCATION OF EXISTING SEWER LATERAL A-1.3 - APPROVED 04/24/2023 REV#5 - RELOCATE AC UNIT; REMOVE ARCHES AT ENTRY; OPENING AT
ENTRANCE CHANGED TO 5FT 8IN; REMOVE WALL HEATER IN ADU-APPROVED 9/1/2023 REV#6 - APPROVAL FOR PLACEMENT OF A SHED (100 SF); THE CONSTRUCTION OF THE SHED IS
EXEMPT FROM BUILDING PERMIT PER CRC R105 -APPROVED 10/24/2023
INSPECTION TYPE DATE STATUS INSPECTOR
FOUNDATION 2022-02-22 Failed Rodney Weathers
ROUGH PLUMBING 2022-02-22 Passed Rodney Weathers
FOUNDATION 2022-03-09 Rescheduled
FOUNDATION 2022-03-11 Failed Rodney Weathers
FOUNDATION 2022-03-10 Rescheduled
FOUNDATION 2022-03-24 Passed Rodney Weathers
Initial Investigation 2022-08-22 In Violation Rodney Weathers
ROUGH ELECTRICAL 2022-08-30 Failed Rodney Weathers
ROUGH FRAME 2022-08-30 Failed Rodney Weathers
ROUGH PLUMBING 2022-08-30 Failed Rodney Weathers
ROUGH ELECTRICAL 2022-09-01 Failed Rodney Weathers
ROUGH ELECTRICAL 2022-09-07 Passed Rodney Weathers
ROUGH ELECTRICAL 2022-09-09 Failed Rodney Weathers
ROUGH FRAME 2022-09-26 Failed Bob Sabich
ROUGH FRAME 2022-09-29 Cancelled Rodney Weathers
ROUGH ELECTRICAL 2022-09-29 Failed Rodney Weathers
ROUGH PLUMBING 2022-09-29 Failed Rodney Weathers
SERVICE UPGRADE 2022-10-18 Passed Bob Sabich
ROUGH FRAME 2022-10-26 Failed Rodney Weathers
EXTERIOR SHEAR Pending Pending
INTERIOR SHEAR Pending Pending
ROUGH FRAME 2022-11-04 Passed Bob Sabich
FIRE DEPT - SPRINKLERS - ROUGH 2022-11-21 Passed Santa Clara County Fire
ROUGH ELECTRICAL 2022-11-28 Failed Rodney Weathers
ROUGH PLUMBING 2022-11-28 Passed Rodney Weathers
INSULATION 2022-12-05 Passed Antonio Torrez
SHEETROCK 2022-12-16 Passed Rodney Weathers
SHOWER PAN 2023-01-24 Failed Rodney Weathers
SHOWER PAN 2023-01-27 Passed Rodney Weathers
UNDERGROUND WATER SERVICE 2023-01-27 Failed Rodney Weathers
INTERIOR LATH 2023-02-03 Passed Bob Sabich
UNDERGROUND WATER SERVICE 2023-02-03 Passed Bob Sabich
EXTERIOR LATH 2023-03-14 Conditional Rodney Weathers
EXTERIOR LATH 2023-04-28 Passed Bob Sabich
FOUNDATION 2023-04-28 Failed Bob Sabich
FOUNDATION 2023-05-01 Cancelled Rodney Weathers
PIERS 2023-05-01 Failed Rodney Weathers
PIERS 2023-05-01 Cancelled Rodney Weathers
PIERS 2023-05-05 Failed Rodney Weathers
SCRATCH COAT 2023-05-05 Failed Rodney Weathers
FINAL MECHANICAL 2023-05-05 Failed Rodney Weathers
PIERS 2023-09-12 Passed Rodney Weathers
AIR CONDITIONER 2023-09-26 Failed Rodney Weathers
PIERS 2023-09-26 Cancelled Rodney Weathers
EXTERIOR LATH 2023-10-02 Passed Rodney Weathers
ROUGH FRAME 2023-09-26 Passed Rodney Weathers
SCRATCH COAT 2023-10-11 Passed Rodney Weathers
FINAL BUILDING 2023-10-20 Failed Rodney Weathers
ROUGH ELECTRICAL 2023-10-20 Passed Rodney Weathers
FINAL BUILDING 2023-10-27 Rescheduled Rodney Weathers
FINAL BUILDING 2023-11-06 Cancelled
FINAL BUILDING 2023-10-30 Failed Rodney Weathers
FIRE DEPT - SPRINKLERS - FINAL 2023-10-31 Passed Santa Clara County Fire
FINAL BUILDING 2023-11-01 Passed Rodney Weathers
EVERY PERMIT ISSUED SHALL BECOME INVALID UNLESS THE WORK ON THE SITE AUTHORIZED BY SUCH PERMIT IS COMMENCED WITHIN 12 MONTHS AFTER ITS ISSUANCE, OR IF THE WORK
AUTHORIZED ON THE SITE BY SUCH PERMIT IS SUSPENDED OR ABANDONED FOR A PERIOD OF 12 MONTHS AFTER THE TIME THE WORK IS COMMENCED.