BLD-2022-1647InspectionRecordINSPECTION RECORD
CITY HALL
10300 Torre Avenue • Cupertino, CA 95014-3255
PHONE 408-777-3228
WWW.CUPERTINO.ORG
BUILDING ADDRESS: 7537 PEACH BLOSSOM DR Cupertino APN: 366 11 134 PERMIT NO: BLD-2022-1647
OWNER'S NAME: RANGANATH SUNDARESHWAR P AND SUNDARESHWAR V OWNER'S PHONE: 408-218-2045
CONTRACTOR: GRAND - NEST CONSTRUCTION, 13428 CHRISTIE DRIVE SARATOGA CONTRACTOR PHONE: 650-861-2039
DATE ISSUED 3/21/2024 3:04:42 PM ISSUED BY:VALUATION: $350000
JOB DESCRIPTION
REAR ADDITION (469 SF) AND FRONT ADDITION (28 SF); REMODEL OTHER (310 SF); POWDER & BATHROOM ROOM REMODEL (73 SF); KITCHEN REMODEL (288 SF); NEW RECESS LIGHTS
(16)
INSPECTION TYPE DATE STATUS INSPECTOR
FOUNDATION 2023-03-24 Passed Rodney Weathers
UNDERFLOOR FRAMING 2023-04-04 Passed Rodney Weathers
EXTERIOR SHEAR 2023-04-28 Passed Antonio Torrez
ROOF NAIL 2023-04-28 Passed Antonio Torrez
UNDERFLOOR PLUMBING 2023-05-24 Passed Bob Sabich
ROUGH FRAME 2023-06-09 Failed Rodney Weathers
ROUGH ELECTRICAL 2023-06-09 Passed Rodney Weathers
ROUGH PLUMBING 2023-06-09 Passed Rodney Weathers
ROUGH MECHANICAL 2023-06-09 Passed Rodney Weathers
EXTERIOR LATH 2023-06-14 Passed Rodney Weathers
ROUGH FRAME 2023-06-14 Failed Rodney Weathers
INTERIOR SHEAR 2023-06-09 Conditional Rodney Weathers
INSULATION 2023-06-21 Failed Bob Sabich
ELECTRIC METER RELEASE 2023-06-21 Failed Bob Sabich
INSULATION 2023-06-26 Failed Bob Sabich
ROUGH FRAME 2023-06-26 Failed Rodney Weathers
ELECTRIC METER RELEASE 2023-06-26 Passed Rodney Weathers
SCRATCH COAT 2023-06-29 Passed Rodney Weathers
SHEETROCK 2023-06-29 Passed Rodney Weathers
SHOWER PAN 2023-07-05 Cancelled Bob Sabich
GAS TEST 2023-06-29 Passed Rodney Weathers
SHOWER PAN 2023-06-29 Passed Rodney Weathers
FINAL ELECTRICAL 2023-08-22 Failed Rodney Weathers
FINAL MECHANICAL 2023-08-22 Failed Rodney Weathers
FINAL PLUMBING 2023-08-22 Failed Rodney Weathers
ROUGH FRAME 2023-08-22 Passed Rodney Weathers
INSULATION 2023-08-22 Passed Rodney Weathers
SANITARY - VISUAL 2023-11-20 Failed cupsanitary
PW – DEV SERVICES FINAL 2023-11-20 Passed Kevin Rieden
SANITARY - VISUAL 2023-12-12 Failed cupsanitary
SANITARY - VISUAL 2024-02-13 Failed cupsanitary
SANITARY - VISUAL 2024-02-28 Scheduled cupsanitary
SANITARY - VISUAL 2024-02-28 Passed cupsanitary
SANITARY - FINAL 2024-03-06 Passed cupsanitary
FINAL BUILDING 2024-03-21 Passed Antonio Torrez
FINAL PLUMBING 2024-03-21 Passed Antonio Torrez
FINAL MECHANICAL 2024-03-21 Passed Antonio Torrez
FINAL ELECTRICAL 2024-03-21 Passed Antonio Torrez
EVERY PERMIT ISSUED SHALL BECOME INVALID UNLESS THE WORK ON THE SITE AUTHORIZED BY SUCH PERMIT IS COMMENCED WITHIN 12 MONTHS AFTER ITS ISSUANCE, OR IF THE WORK
AUTHORIZED ON THE SITE BY SUCH PERMIT IS SUSPENDED OR ABANDONED FOR A PERIOD OF 12 MONTHS AFTER THE TIME THE WORK IS COMMENCED.