BLD-2022-1632InspectionRecordINSPECTION RECORD
CITY HALL
10300 Torre Avenue • Cupertino, CA 95014-3255
PHONE 408-777-3228
WWW.CUPERTINO.ORG
BUILDING ADDRESS: 18689 CRABTREE AVE Cupertino APN: 375 25 049 PERMIT NO: BLD-2022-1632
OWNER'S NAME: MARTINEZ PHYLLIS OWNER'S PHONE: 4086587847
CONTRACTOR: TLS CONSTRUCTION INC, 2102 ELLEN AVE SAN JOSE CONTRACTOR PHONE: 408-497-3746
DATE ISSUED 4/11/2024 2:45:37 PM ISSUED BY:VALUATION: $271700
JOB DESCRIPTION
CONSTRUCTION NEW DETACHED ADU - (620 SF); REV #1 UPGRADE MAIN SERVICE PANEL (200A) - APPROVED 1/23/2024 REV #2 CLARIFYING CONFLICTING HEIGHTS OF THE
BUILDNG IN REGARDS TO FOUNDATION - APPROVED 3/21/2024 REV # 3 REVISE THE SEWER LINE CONNECTION AS BUILT - APPROVED 4/11/2024
INSPECTION TYPE DATE STATUS INSPECTOR
FOUNDATION 2024-01-04 Failed James Lee
ELECTRIC METER RELEASE 2024-02-02 Passed James Lee
ROUGH FRAME 2024-02-20 Failed Antonio Torrez
UNDERFLOOR PLUMBING 2024-02-20 Failed Antonio Torrez
UNDERGROUND ELECTRICAL 2024-02-20 Failed Antonio Torrez
UNDERGROUND ELECTRICAL 2024-02-22 Failed Rodney Weathers
UNDERFLOOR PLUMBING 2024-02-22 Cancelled Rodney Weathers
UNDERGROUND SEWER 2024-02-22 Failed Rodney Weathers
UNDERGROUND WATER SERVICE 2024-02-22 Failed Rodney Weathers
UNDERGROUND SEWER 2024-02-28 Failed Rodney Weathers
UNDERGROUND WATER SERVICE 2024-02-28 Passed Rodney Weathers
ROUGH FRAME 2024-02-28 Failed Rodney Weathers
FOUNDATION 2024-03-25 Cancelled James Lee
ROUGH FRAME 2024-03-25 Passed James Lee
UNDERFLOOR PLUMBING 2024-03-25 Passed James Lee
UNDERGROUND ELECTRICAL 2024-03-25 Failed James Lee
UNDERGROUND SEWER 2024-03-25 Failed James Lee
PW – DEV SERVICES FINAL 2024-04-10 Passed Kevin Rieden
FINAL BUILDING 2024-04-11 Passed James Lee
UNDERGROUND ELECTRICAL 2024-04-11 Passed James Lee
UNDERGROUND SEWER 2024-04-11 Passed James Lee
EVERY PERMIT ISSUED SHALL BECOME INVALID UNLESS THE WORK ON THE SITE AUTHORIZED BY SUCH PERMIT IS COMMENCED WITHIN 12 MONTHS AFTER ITS ISSUANCE, OR IF THE WORK
AUTHORIZED ON THE SITE BY SUCH PERMIT IS SUSPENDED OR ABANDONED FOR A PERIOD OF 12 MONTHS AFTER THE TIME THE WORK IS COMMENCED.