BLD-2022-2471InspectionRecordINSPECTION RECORD
CITY HALL
10300 Torre Avenue • Cupertino, CA 95014-3255
PHONE 408-777-3228
WWW.CUPERTINO.ORG
BUILDING ADDRESS: 10755 MINETTE DR Cupertino APN: 375 32 049 PERMIT NO: BLD-2022-2471
OWNER'S NAME: SF21G LLC OWNER'S PHONE: Not Provided
CONTRACTOR: T J C HOME BUILDERS LLC, 26880 ALISO VIEJO PKWY STE 200 ALISO VIEJO CONTRACTOR PHONE: 6502723276
DATE ISSUED 6/6/2024 4:49:16 PM ISSUED BY:VALUATION: $764700
JOB DESCRIPTION
CONSTRUCT NEW 2-STORY SINGL FAMILY DWELLING - (2118 SF); WITH (4) BEDROOMS, (3) BATHROOMS AND AN ATTACHED GARAGE - (432 SF) , NEW PORCH - (46 SF), NEW
COVERED PATIO - (172 SF); ATTACHED ADU WITH (1) BEDROOM AND (1) BATHROOM - (511 SF) REV # 1 - FOUNDATION REVISION - APPROVED 05/25/2023 REV # 2 - REVISE REV # 1;
FOUNDATION REVISION TO MATCH ARCH SLAB PLAN PAD AND EFE TO THE PAD AND EFE NUMBERS ON THE GRADING PLAN SUBMITTED IN REV # 1 - APPROVED 07/06/2023 REV # 3 -
REVISE HEADER #3 FROM DROP TO FLUSH - APPROVED 1/11/2024
INSPECTION TYPE DATE STATUS INSPECTOR
UNDERGROUND WATER SERVICE 2023-10-26 Failed James Lee
UNDERFLOOR PLUMBING 2023-10-30 Passed James Lee
UNDERGROUND SEWER 2023-10-30 Passed James Lee
FOUNDATION 2023-11-09 Conditional Rodney Weathers
UNDERFLOOR FRAMING 2023-12-06 Cancelled
UNDERFLOOR FRAMING 2023-12-08 Cancelled
UNDERFLOOR FRAMING 2023-12-11 Cancelled
UNDERFLOOR FRAMING 2023-12-13 Rescheduled
ROOF NAIL 2023-12-18 Rescheduled
ROOF NAIL 2023-12-20 Rescheduled
EXTERIOR SHEAR 2023-12-19 Rescheduled
EXTERIOR SHEAR 2023-12-20 Rescheduled
UNDERFLOOR FRAMING 2023-12-21 Rescheduled
ROOF NAIL 2024-01-03 Rescheduled
ROOF NAIL 2024-01-04 Rescheduled
EXTERIOR SHEAR 2024-01-03 Rescheduled
EXTERIOR SHEAR 2024-01-04 Rescheduled
ROOF NAIL 2024-01-05 Rescheduled
UNDERFLOOR FRAMING 2024-01-05 Cancelled
ROOF NAIL 2024-01-09 Rescheduled
EXTERIOR SHEAR 2024-01-09 Rescheduled
ROOF NAIL 2024-01-10 Rescheduled
EXTERIOR SHEAR 2024-01-10 Rescheduled
ROOF NAIL 2024-01-11 Rescheduled
EXTERIOR SHEAR 2024-01-11 Rescheduled
EXTERIOR SHEAR 2024-01-12 Rescheduled
ROOF NAIL 2024-01-12 Rescheduled
EXTERIOR SHEAR 2024-01-16 Cancelled James Lee
ROOF NAIL 2024-01-16 Cancelled James Lee
EXTERIOR SHEAR 2024-01-17 Passed James Lee
ROOF NAIL 2024-01-17 Passed James Lee
EXTERIOR SHEAR 2024-01-18 Cancelled
ROOF NAIL 2024-01-18 Cancelled
ROOF NAIL 2024-01-19 Cancelled
EXTERIOR SHEAR 2024-01-19 Cancelled
ROUGH FRAME 2024-02-08 Rescheduled
ROUGH FRAME 2024-02-07 Rescheduled
INSULATION 2024-02-12 Rescheduled
INSULATION 2024-02-13 Rescheduled
ROUGH FRAME 2024-02-12 Conditional James Lee
INSULATION 2024-02-14 Passed James Lee
FIRE DEPT - SPRINKLERS - ROUGH 2024-02-06 Passed Santa Clara County Fire
ROUGH FRAME 2024-02-13 Cancelled
INSULATION 2024-02-15 Cancelled
EXTERIOR LATH 2024-02-14 Passed James Lee
SHEETROCK 2024-02-20 Rescheduled
SHEETROCK 2024-02-21 Rescheduled
SHOWER PAN 2024-02-20 Rescheduled
SHOWER PAN 2024-02-21 Rescheduled
SHEETROCK 2024-02-22 Failed Rodney Weathers
SHOWER PAN 2024-02-22 Passed Rodney Weathers
SHEETROCK 2024-02-26 Conditional James Lee
SHOWER PAN 2024-02-26 Cancelled
EXTERIOR LATH 2024-02-26 Cancelled
INTERIOR LATH 2024-02-26 Conditional James Lee
ELECTRIC METER RELEASE 2024-04-08 Cancelled James Lee
ELECTRIC METER RELEASE 2024-04-09 Rescheduled
ELECTRIC METER RELEASE 2024-04-17 Rescheduled
ELECTRIC METER RELEASE 2024-04-18 Rescheduled
ELECTRIC METER RELEASE 2024-04-12 Passed James Lee
UNDERGROUND WATER SERVICE 2024-04-12 Passed James Lee
ELECTRIC METER RELEASE 2024-04-15 Cancelled
UNDERGROUND WATER SERVICE 2024-04-15 Cancelled
FIRE DEPT - SPRINKLERS - FINAL 2024-05-13 Passed Santa Clara County Fire
PW – DEV SERVICES FINAL 2024-05-29 Passed Kevin Rieden
FINAL ELECTRICAL 2024-06-03 Conditional Antonio Torrez
FINAL MECHANICAL 2024-06-03 Conditional Antonio Torrez
FINAL PLUMBING 2024-06-03 Conditional Antonio Torrez
FINAL PLUMBING 2024-06-04 Passed James Lee
FINAL ELECTRICAL 2024-06-04 Passed James Lee
FINAL MECHANICAL 2024-06-04 Passed James Lee
FINAL BUILDING 2024-06-06 Passed James Lee
FINAL PLANNING 2024-06-06 Passed Danielle Condit
EVERY PERMIT ISSUED SHALL BECOME INVALID UNLESS THE WORK ON THE SITE AUTHORIZED BY SUCH PERMIT IS COMMENCED WITHIN 12 MONTHS AFTER ITS ISSUANCE, OR IF THE WORK
AUTHORIZED ON THE SITE BY SUCH PERMIT IS SUSPENDED OR ABANDONED FOR A PERIOD OF 12 MONTHS AFTER THE TIME THE WORK IS COMMENCED.