Vallco - Development Schedule (COA 59) 3.4.25March 4, 2025
The Rise (Vallco) – Work Schedule Compliant with COA 59
The developer has provided staff the following preliminary schedule for March through August
2025 for grading/erosion control work and right-of-way construction activity on the site:
January 3, 2025 – commencement of site work to prepare for installation of
utilities and infrastructure (estimated duration 2 months)
March 10, 2025 – anticipated commencement of grading activities on-site
(estimated duration 4 months)
June 1, 2025 – anticipated commencement of utility installation, some of which is
in the right of way (estimated duration 2 months)
Note: SWPPP and erosion control has been ongoing since demolition and will be continuous
through construction.