Vallco - Development Schedule (COA 59) 3.4.25March 4, 2025 The Rise (Vallco) – Work Schedule Compliant with COA 59 The developer has provided staff the following preliminary schedule for March through August 2025 for grading/erosion control work and right-of-way construction activity on the site:  January 3, 2025 – commencement of site work to prepare for installation of utilities and infrastructure (estimated duration 2 months)  March 10, 2025 – anticipated commencement of grading activities on-site (estimated duration 4 months)  June 1, 2025 – anticipated commencement of utility installation, some of which is in the right of way (estimated duration 2 months) Note: SWPPP and erosion control has been ongoing since demolition and will be continuous through construction.