CC Resolution No. 9993RESOLUTION NO. 9993
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CUPERTINO
APPROVING CONTRACT CHANGE ORDER NO. 1 FOR MEDIAN
MODIFICATION, STEVENS CREEK BOULEVARD AT STELLING
ROAD, PROJECT NO. 97-105
RESOLVED by the City Council of the City of Cupertino, California, that Change Order
No. 1 for changes to work which has been approved by the Director of Public Works and this day
presented to this Council, be, and it hereby approved in conjunction with the project known as
MEDIAN MODIFICATION, STEVENS CREEK BOULEVARD
AT STELLING ROAD, PROJECT NO. 97-105
BE IT FURTHER RESOLVED that funds are available and no further appropriation is
necessary.
PASSED AND ADOPTED at a regular meeting of the City Council of the City of
Cupertino this 3rd day of November, 1997, by the following vote:
Vote
Members of the City Council
AYES: Burnett,
NOES: None
ABSENT: None
ABSTAIN: None
Chang, Dean,
Sorensen,
Bautista
ATTEST:
APPROVED:
Mayor, i2~ty of Cupertino
Cupertino
10300 Torre Avenue
Cupertino, CA 95014-3202
(408) 777-3354
FAX (408) 777-3333
PUBLIC WORKS DEPARTMENT
MEDIAN MODIFICATION
STEVENS CREEK BOULEVARD AT STELLING ROAD
PROJECT NO. 97-105
CONTRACT CHANGE ORDER NO. 1
Contractor
Collishaw Construction
P. O. Box 611718
San Jose CA 95161-1718
The following changes are hereby approved:
IA.
lB.
Provide surveying
Repair broken electrical conduit
Total Change Order No. 1
$ 1,050.00
.2,335.00
$ 3,385.00
Total Project:
Original Contract
Change Order No. 1
Revised Contract
$ 41,135.00
3,385.0O
$ 44,520.00
CONTRACTOR
Title ,~ ,~ ~
Date /I
~.ert J. Visl
Director ot Public Works
City Council: Nov. 3, 1997
Resolution No. 9993