05-013, Pavement Engineering, Inc.
AGREEMENT
NotJ1flJS-43? tJ
CUPEI\IINO
CITY OF CUPERTINO
10300 Torre Avenue
Cupertino, CA 95014
(408) 777-3200
BY THIS AGREEMENT, made and entered into on the 8th day of February , 20 ~,
by and between the CITY OF CUPERTINO (Hereinafter referred to as CITY) and
Name (1) Pavement Engineering rnc. (2)
Address 1301 Rand Street. Ste. D City Petal UIDa, C,A Zip Q4Q')4 Phone (07) 769-5330
(Hereinafter referred as CONTRACTOR), in consideration of their mutual covenants, the parties hereto agree as follows:
CONTRACTOR shall provide or furnish the following specified services and/or materials: Design, contract documents, cost
estimate, bid support, const. inspection & suoport for 2005 Annual Overlay project
EXHIBITS: The following att8:cl1ed exhibits hereby are'l11ade part 01 this Agreement: "
See Exhibit A" Proposal
TERMS: The services and/or materials furnished under this Agreement shall commence on February R, 700')
and shall be completed before December 1. 2005
COMPENSATION: For the full performance of this Agreement, CITY shall pay CONTRACTOR: $89,850 with Director
approval on an additional $5,000 for additional work
California Labor Code, Section 1771 requires the payment of prevailing wages to all workers employed on a Public Works contract in
excess of $1,000.00.
GENERAL TERMS AND CONDITIONS
Hold Harmless: Contractor agrees to save and hold harmless the City, its officers, agents and employees from any and all damage and
liabilit~ includi~ all costs of defending any claim, caused by or arising out of the performance of this Agreement. City shall not
be lia e for acts of Contractor in performing services described herein.
due to negligence, errors and omissions
Insurance: Should the City require evidence of insurability, Contractor shall file with City a Certificate of Insurance before commencing
any services under this Agreement. Said Certificate shall be subject to the approval of City's Director of Administrative Services.
Non-Discrimination: No discrimination shall be made in the employment of persons under this Agreement because of the race, color,
national origin, ancestry, religion or sex of such person.
Interest of Contractor: It is understood and agreed that this Agreement is not a contract of employment in the sense that the
relationship of master and servant exists between City and undersigned. At all times, Contractor shall be deemed to be an independent
contractor and Contractor is not authorized to bind the City to any contracts or other obligations in executing this agreement. Contractor
certifies that no one who has or will have any financial interest under this Agreement is an officer or employee of City.
Changes: This Agreement shall not be assigned or transferred without the written consent of the City. No changes or variations of any
kind are authorized without the written consent of the City.
CONTRACT CO-ORDINATOR and representative for CITY shall be:
NAME
Carmen Lynaugh
DEPARTMENT
Public Works
This Agreement shall become effective upon its execution by CITY, in witness thereof, the parties have executed this
Agreement the day and year first written above.
CONTRACTOR:-J
, ./ ,
/ ,/:{ ///' /,
By / J /~,t /c, . ,/tr
Title' P~.s~1
Soc. Sec. #
By
Title
Yellow: Contractor
Gold: Department
fi1
Pavement Engineering Inc.
Civil Engineers . Materials Testing
Specializing in Pavement Rehabilitation
EXHIBIT A
PUBUC WORKS
FEB 11 200~,
February 1, 2005
MP05-034a
Ms. Carmen M. Lynaugh
Public Works Projects Manager
City of Cupertino
10300 Torre Avenue
Cupertino, CA 95014-3255
Subject: 2005 Annual Overlay Project
~~Dgineering, Inspection and Testing Services
Dear Carmen:
It was a pleasure to hear from you last week and discuss the scope
of work for the subject project. Pavement Engineering is pleased
to provide a proposal for the preparation of contract documents, as
well as the contract administration phase of the work. As you are
aware, PEl has performed numerous projects in the past for the city
of Cupertino. This proposal is based on our past experience
working with the city on similar projects.
It is our understanding that the target budget of the project is
approximately $800,000 to perform the work, including design,
testing and inspection fees. The street list includes several
roadway segments in the El Rancho neighborhood. Past experience in
this area shows that local R-value's range between less than 5 up
to 10. Pavement thicknesses generally vary between 2 to 3 inches
on most roadway segments, with a base thickness ranging between 0
to 4 inches. Typical rehabilitation treatments in this area have
included milling and filling, or placing a leveling course, fabric
and overlay. Significant digouts have also been performed in the
past in this neighborhood. We anticipate similar rehabilitation
methods for the 2005 Overlay project.
From our preliminary review of the streets it is apparent that
there is significant concrete repair work to be done in the El
Rancho neighborhood. From our phone discussion we understand that
a prior contract will address as much of the concrete work as
possible, but there may be some work added to our project if it is
not completed in the concrete contract.
1301 Rand Street, Suite D, Petaluma, CA 94954-1196 . Tel. (707) 769-5330 . Fax (707) 769-5333
20260 Skypark Drive, Redding, CA 96002-9221 . Tel. (530) 224-4535 . Fax (530) 224-4539
1248 Laurel Lane, Suite B, San Luis Obispo, CA 93401-5860 . Tel. (805) 781-2265 . Fax (805) 781-2267
Ms. Carmen M. Lynaugh
February 1, 2005
MP05-034
Page 2
Scope of Work
The following describes our scope of work and fees for this
project:
Preparation of Contract Document and Cost Estimate
PEl will prepare the documents based on our approach in past
years. All field quantities of physical elements to be
incorporated in the rehabilitation work of each street will be
measured and recorded. This information will include location
of existing striping, pavement markers and paint markings;
location of underground utility covers; limits of paving
transitions, digouts, and other pavement repairs; and total
area of pavement to be resurfaced. If any concrete repairs or
tree root damage is identified during our field reviews,
including corners requiring access ramps, this work will be
noted and brought to the City's attention to determine if the
repairs should be added to the contract. The existing striping
is to remain unchanged except as indicated by the City.
Our design approach will also include any pavement evaluation
testing such as deflection testing, coring and R-value
determination as required. The extent of this testing will be
determined by the project design engineer during initial field
visits. These tests are included in our fees.
All field quantities will be compiled into individual
engineer's estimates by street segment. A summary spreadsheet
of the entire proj ect will be provided. Technical
specifications will be drafted and details for typical
sections, transitions, keycuts, digouts, and additional
pavement work will be prepared. Any portions of the work which
require further clarification will be submitted in the form of
drafted plan views, details, elevations, or cross sections, as
is necessary. All such details are anticipated to be 8-1/2 x
11 inch size and will be bound into the specification package.
This information will be submitted to the City as part of the
90% design submittal.
R:\Business\Text\Marketing\Proposals\Proposals2005\MPO5-034a_pr.wpd
fa
Ms. Carmen M. Lynaugh
February 1, 2005
MP05-034
Page 3
After review of the 90% submittal, we will meet with the City
staff to resolve any outstanding issues and will adjust the
contract documents accordingly.
Biddinq Process Support Services
After the final submittal, we will be available to answer any
specific questions from the City concerning the design and the
technical issues of the contract documents. Should the need
arise, we will prepare an addendum as required. In addition,
we will also be available for help with questions from the
contract administration personnel or from contractors during
the bidding process.
Construction Inspection and Support Services
PEl will provide construction inspection and support services
similar to past projects. Our services will involve on-site
inspection through the various phases of the work, including
compaction testing during paving. We will perform field
materials testing at the outset of paving and perform
laboratory testing on the material during the paving process.
A project manager will also be available during the inspection
and testing to maintain communications between the City, our
Inspector(s), and the Contractor. The project manager will
take care of submittal reviews, payment requests, and any
other coordination necessary during the work.
Fees
Attached to this proposal is a spreadsheet with an approximation of
the hours anticipated to complete the work in both phases of the
project. This spreadsheet will be updated regularly and included
with each invoice to summarize our efforts during each respective
billing period.
R:\Business\Text\Marketing\Proposals\Proposals2005\MPO5-034a_pr.wpd
fa
Ms. Carmen M. Lynaugh
February 1, 2005
MP05-034
Page 4
Preparation of Contract Document and Cost Estimate
PEl's fee for the work is based on similar services provided
to the City. Our fees for the total project include all field
work, design work and contract document development up to
completion of the project. Our fees also include answering
questions during the bid process and preparation of Addendum
if necessary.
All fees and costs associated with this project are subject to
final negotiation with the City of Cupertino. The attached
proposal conditions apply. Typically, our fees for this
service range between 5% to 6%.
Total Design Services: $39,495.00
(~5% of contract)
Construction Inspection and Support Services
Our estimated fee for construction inspection and support
services is based on the expected type of work to be performed
and the anticipated schedule of the contractor. As in past
projects, this amount may vary based on the actual schedule of
the contractor. If this should occur, we will notify the city
in advance to negotiate any changes in fees. Please bear in
mind that our fee is not a fixed sum but rather a rate based
on the actual time worked by our personnel. In the event that
the actual time is less than the estimated time, our fee will
be less than the stipulated amount.
All fees and costs associated with this project are subject to
final negotiation with the City of Cupertino. The attached
proposal conditions apply. Based on past projects performed
for the city of Cupertino, construction inspection and support
services have ranged between 7% and 9.5% of the construction
cost.
Estimated Inspection and Support Fees: $50,355.00
(~6.3% of contract)
R:\Business\Text\Marketing\Proposals\Proposals2005\MPO5-034a_pr.wpd
fa
Ms. Carmen M. Lynaugh
February 1, 2005
MP05-034
Page 5
We look forward to another successful project with the City of
Cupertino. Our crews can be available to start immediately upon
completion of an Agreement with the city. Please feel free to call
me at (707) 769-5330 if you have any questions regarding this
proposal.
Very truly yours,
PAVEMENT ENGINEERING INC.
~L
Mike Wasden
Project Manager
Attachments:
Project Street List
Proposal Conditions
Proposal Hours Breakdown
pc: C File
M File
MP Files P / S / R
R:\Business\Text\Marketing\Proposals\Proposals2005\MPO5-034a_pr.wpd
fa
PROPOSAL CONDITIONS
1. Proposal is valid for thirty days from the date of the
proposal.
2. All work shall be performed utilizing common methods and
practices of the civil engineering profession. Reports and
construction documents will be signed by a registered civil
engineer.
3. Fees for Lump Sum or Unit Price Proposals will be charged at
the quoted price. The quoted prices include all laboratory
testing costs. Fees for Engineering and Technical Services on
a Time and Materials Basis will be charged at the applicable
hourly rates of the current PEl Fee Schedule.
4. The proposal is based upon providing liability insurance with
limits up to $1,000,000.
5. One copy of an Engineering Report or Plans and Specifications
will be provided to the Owner of a project. Additional copies
are $35 each.
6. Payment: Invoices will be submitted at the completion of the
work for Engineering Reports. Inspection fees will be invoiced
on a monthly basis. All invoices are due upon receipt.
Interest of 1-1/2% per month (but not exceeding the maximum
rate allowable by law) will be payable on any amounts not paid
within 30 days, payment thereafter to be applied first to
accrued interest and then to the principal unpaid amount.
Attorneys fees or other costs incurred in collecting any
delinquent amount shall be paid by the client.
R:\Business\Text\Marketing\Proposals\Proposals2005\MPO5-034a_pr.wpd
2005 Annual Overlay Project MP05-034/MP05-035
City of Cupertino
Design Development
Description Proposal
Units Units Rate Extension
Principal Engineer hour 13 $ 175.00 $ 2,275.00
Associate Engineer / Project Manager hour 110 $ 140.00 $ 15,400.00
Engineering Technician / Drafting hour 138 $ 95.00 $ 13,110.00
Deflection Testing hour 8 $ 275.00 $ 2,200.00
Coring hour 15 $ 225.00 $ 3,375.00
Traffic Control hour $ 100.00 $
R-Value each 3 $ 195.00 $ 585.00
Per Diem each 7 $ 150.00 $ 1,050.00
Mobilization each 1 $ 1,500.00 $ 1,500.00
TOTAL DESIGN DEVELOPMENT $ 39,495.00
Contract Administration
Description Proposal
Units Units Rate Extension
Principal Engineer hour 10 $ 175.00 $ 1,750.00
Project Manager hour 85 $ 140.00 $ 11,900.00
Inspection day 30 $ 1,050.00 $ 31,500.00
Lab Testing: Test Strip each 1 $ 1,125.00 $ 1,125.00
AC Tests during Production each 5 $ 550.00 $ 2,750.00
Mobilization each 1 $ 1,330.00 $ 1,330.00
TOTAL CONTRACT ADMINISTRATION $ 50,355.00
CITY OF CUPERTINO
2005 o VERLA Y PROJECT STREETS
STREET FROM TO LENGTH WIDTH S.F.
ANNE LN TANTAU END 315 36 11,340
ARATA WY LOREE CALVERT 990 38 37,620
BARNHART AVE CULBERTSON MORETTI 566 37 20,942
BARNHART CT BARNHART END 250 33 8,250
BRET AVE LOREE SCB 1,225 38 46,550
CALVERT DR MENHART NORTH END 732 38 27,816
GASCOIGNE DR WUNDERLICH BARNHART 1,240 33 40,920
JOHANSEN DR MEIGGS PENDERGAST 1,012 37 37,444
JOHNSON AVE BOLLINGER NEWSOM 275 37 10,175
LOREE AVE CALVERT JOHSON 210 38 7,980
MEIGGS AVE TANTAU MOREN GO 734 37 27,158
MINETTE PL MINETTE END 160 33 5,280
NEWSOM AVE CARVER JOHNSON 512 33 16,896
PENDERGAST AVE CULBERTSON WUNDERLICH 1,122 37 41,514
STERN LOREE STEVENS CREEK 1,180 38 44,840
TILSON AVE CALVERT JOHNSON 270 38 10,260
TUGGLE PL WUNDERLICH E. END 168 33 5,544
TOTAL 400,529
rootlbusiness/marketing/proposals/2005/cupertino OL Project.xls