101-2011-2012 Work Program.pdf2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 1 of 36 1. Major Developments (for a full list of development activity go to www.cupertino.org/developmentactivity) A. Apple Apple has submitted plans for the development of an R&D campus in the N- E part of the City. The project area generally encompasses the properties between I-280, N. Tantau Ave, Homestead Road and N. Wolfe Road. The project also includes properties on the east side of N. Tantau Ave between Pruneridge Avenue and I-280 and three parcels to the north- east of the intersection of Pruneridge Avenue and N. Tantau Avenue. Environmental Review of the proposed project is currently underway. The Environmental Impact Report (EIR) is anticipated to be released in Summer 2012. Staff is reviewing the project concurrent with the environmental review. It is anticipated that public hearings for the project will occur at the end of 2012. The proposed project includes: • Demolition of approximately 2.65 million square feet of existing office, research and development buildings on 175 acres; • Construction of: o An office, research and development building comprising approximately 2.8 million square feet; o 120,000 s.f. corporate auditorium; o 100,000 s.f. corporate health/fitness center; o 45,000 s.f. central plant; o Research facilities comprising approximately 300,000 square feet located on the east side of Tantau Avenue; and o Associated Parking including: o A 4,600 space parking garage o 750 space surface parking lot for auditorium and o 100 space visitor parking lot. • Development Allocation of up to 300,000 square feet of office space for subsequent development located within the project area. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 2 of 36 B. Vallco Mall (Cupertino Square) 1. Periodic updates to City Council from property owners. 2. Periodic reports regarding development approvals. 3. Adherence, if possible, to artist renderings presented to Council. 4. Analyze the impacts of the development agreement's expiration. Owners of Vallco Mall are pursuing the private revitalization of the center as follows: Construction Underway: 1. Bay Club – approximately 67,000 square feet adjacent to the Sears space. Approved but construction hasn’t started 1. Retail adjacent to JcPenney’s – 43,000+ square feet of multi-tenant retail space facing Wolfe Road and Vallco Parkway, adjacent to the new garage. The developer has put the plans for the JcPenney’s retail frontage on hold until the economy improves. Sears (who owns their building) has sub-leased approximately 67,000 square feet on three levels to Bay Club – an upscale fitness center including a spa, drop-in child care, and gym/fitness rooms. The new athletic club will face Stevens Creek Boulevard, and will have a café at the Wolfe corner. On February 1, 2012, Redevelopment Agencies were dissolved. The Vallco area is no longer a Redevelopment Area. In August 2011, the Vallco Farmer’s Market moved from the Sears parking lot to the northern J.C. Penney’s parking lot. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 3 of 36 C. Sand Hill Properties Site (Main Street Project) City Council approved the original Master Use Permit, Architectural & Site Approval, Tentative Map, Tree Removal Permit, and EIR on January 20, 2009. Sandhill has applied for a modification to their permits to make changes to the project. The Planning Commission hearing is scheduled for March 27, 2012 and a City Council hearing is tentatively scheduled in April. The project, located on a 17-acre site, was originally approved for 150,000 sf of retail shops; a 145,000 sf athletic club or alternate option of an additional 36,000 sf of retail; up to a 250 room hotel (w/a 400-person banquet facility if over 160 rooms); 160 senior housing units; 100,000 sf of office; .75 acre park; and a town square;. The Master Use Permit, Architectural & Site Approval and Tree Removal Permits expire on January 20, 2014. The modified project proposed by Sandhill consists of 292,000 square feet of office space, 78,700 square feet of retail space, 60,000 square feet of athletic club and/or additional retail space, a 180-room hotel, 143 senior age-restricted condominium units, vacating Finch Avenue, a town square, 0.75-acre park and an alternate option to include a 105-unit market-rate apartment complex. D. The Oaks City Council approved a Use Permit, Architectural & Site and Tentative Map applications to construct a retail/hotel project on September 2, 2008. City Council approved the Use Permit Modification for a limited number of late evening commercial entertainment establishments and live entertainment activities on November 16, 2010. Council has approved a four story 122-room hotel, and a 3-story, 56,200 square foot mixed use building with retail, office, and banquet uses. The Use Permit and Architectural and Site approvals expire on September 2, 2012. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 4 of 36 A Farmer’s Market along the highway 85 sound wall was approved by the Planning Commission on April 26, 2011 to open on Sundays from 9am to 1 pm. The market began operations on October 1, 2011. E. Rose Bowl and Out-parcels • KCR/Evershine, the new owner of the Rose Bowl, has developed slightly modified plans with 204 residential units and 60,000 sq. ft. of retail. • KCR has applied for a building permit for the superstructure. The permit is expected to be issued in March/April 2012. • The two out-parcels adjacent to Highway 280 have been on hold. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 5 of 36 F. Aloft Cupertino Hotel A 138-room, five-story hotel was approved in January 2009. In 2010, the project was given approval for a modification to reduce the size to 123 rooms and four stories, and an extension to the use permit until January 2012. The developer has changed hotel operators from Hyatt Place to the Aloft chain, part of the Starwood Hotel and Resort Group. Applicant applied for a modification to the plans to reduce the scope of the hotel to make the project financially feasible. Item approved by DRC on 03/31/2011. Developer broke ground in the fall of 2011. Superstructure building permit was issued in December 2011. G. Embarcadero Park/Results Way On 7/21/09, the City Council approved the applicant’s request to extend the expiration date by five years to allow phasing of construction, clarify conditions approval, and modify the traffic and signal improvement condition. Former Measurex site. Three new office buildings totaling 155,500 sq. ft. Demolish five buildings totaling 139,632 sq. ft. Approved Sept. 2008, the extended expiration date is July 21, 2014. Arcsight, one of the existing tenants, was acquired by HP in September 2010 and was moved to Sunnyvale in 2012. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 6 of 36 Apple, Inc. has leased the vacant space at the Results Way office park and will also take over Arcsight’s tenant space for a term of seven years. Redevelopment of the site by the owner has been put on hold. H. Cupertino Crossroads Façade and site improvements for a new TJMaxx Homegoods and Party City store to replace the Mervyn’s space were approved by the Planning Commission in April 2011. The City Council approved two new retail/restaurant building pads at the Crossroads Shopping Center in November 2011. Construction is expected to begin in March 2012. Islands restaurant, has applied for use permits for a bar and late night use. The project will be reviewed by the Planning Commission on March 13, 2012. The project consists of the demolition of the Marie Calendar’s building (4,930 sq. ft.) and the construction of a 5,086 sq. ft. building for Island’s Restaurant, as well as an 8,011 sq. ft. building for three future retail/eating establishment tenants. I. Prometheus/Biltmore Adjacency Prometheus has submitted plans for a new multi-family residential project with a commercial frontage. The project is expected to be heard at the Planning Commission in the April/May timeframe and a subsequent hearing will be scheduled at the Council. Approximately 20,000 square feet of commercial space will be demolished with 7,000 of new retail proposed. About 89 residential units are expected on the site fronting Stevens Creek Blvd and 12 within the adjacent Biltmore complex. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 7 of 36 J. Apple Cafeteria Apple has submitted plans for a new cafeteria to serve employees at the Tomokazu Restaurant site located on the northeast corner of Bandley and Alves Drives. The project is expected to be heard at the Planning Commission in April 2012. About 4,000 square feet of existing restaurant space will be demolished to accommodate an approximately 19,000 square foot cafeteria with underground parking. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 8 of 36 2. Capital Improvements and Plans A. Parks 1. Stevens Creek Corridor Park Phase 2 – (Completion of trail to Stevens Creek Blvd. including restoration of the creek along the golf course) The City Council reviewed design elements, funding and authorized grant applications for Stevens Creek Corridor Park and Restoration Phase 2 in January, March, April and May 2011. In June 2011, as part of the 2011-12 Capital Improvement Program, the City Council approved a project budget of $1,400,000 for the design phase. The balance of the overall project budget and construction funding is planned for inclusion in the 2012-13 capital program. Design completion anticipated January, 2013, construction to begin in April 2013, and creek construction to be complete by the end of October 2013. The Phase 2 Project generally consists of extending the trail from its current temporary end point at the northern end of the Blackberry Farm parking lot, along the east side of the creek adjacent to the eighth green of the golf course to a new bridge, then to the west side of Stevens Creek through the Stocklmeir Orchard, past the Stocklmeir house and ending at the Blue Pheasant parking lot. It also includes restoring the creek channel along the east bank, encroaching moderately onto the golf course and relocating the existing sanitary line under the ninth fairway for approximately 700 feet. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 9 of 36 2. Lawrence – Mitty Park a. Work with County to come up with a plan to move the County Roads and Airports activity off the site and develop a park Santa Clara County Department of Roads and Airports owns a parcel west of Lawrence Expressway currently used as a materials storage site. County Parks has received Board of Supervisors approval for the San Tomas Aquino trail master plan, which identifies this site as greenbelt. Independent appraisal is $1.880 million. At this point, the timing is uncertain for acquisition and partial funding is tentatively identified for FY 2012-2013. County Board of Supervisors have voted to set aside some County parks money for urban parks. Staff has approached the San Jose Water Company about the potential for acquiring land immediately adjacent to the Roads & Airports corporation yard at Doyle, east Lawrence Expressway. The approximate one acre San Jose Water Company parcel if available, could be purchased for a Roads & Airport yard expansion, freeing up the creekside parcel for park development and the extension of the Tomas Aquino trail. County park acquisition funds may support this effort. The appraised value for the west site is $1,880,000. The appraised value for the east site is $2,010,000. Mark Linder is meeting with Rob Courtney, the new Director of County Parks on April 26 to explore County support for this project. b. Pursue Grants Staff is working to obtain grant funding for acquisition and design and construction. However the current State budget crisis has created a great deal of uncertainty around grant funding of any kind. Staff will develop a preliminary Project Budget estimate for consideration in the FY 11/12 CIP budget discussions. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 10 of 36 3. Review plans for Simms and Stocklmeir and consider including in the CIP. Complete McClellan Ranch Master Plan. The 2011-2012 CIP budget included $50,000 to update the McClellan Ranch Park Master Plan. If approved by council, this will incorporate the Simms property as “McClellan Ranch West Preserve” McClellan Ranch Master Plan was approved as part of 2011-12 CIP budget to validate or amend previouis master plan and to gain concurrence in prioritizing and phasing Capital Improvements. The future use of the Stocklmeir property will be revisited once the Stevens Creek Corridor Park Phase 2 is complete. McClellan Ranch Master Plan to go to Council for approval in April, 2012. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 11 of 36 4. Support the four city task force investigating possible Stevens Creek Trail alignment. Councilmember Mahoney and Parks and Recreation Director Mark Linder represent Cupertino on this task force. Each member city, Cupertino, Sunnyvale, Los Altos, and Mountain View have one elected official and one staff member on the task force. The focus of the task force is to develop a route for the Stevens Creek Trail between Cupertino and Mountain View. The four cities are hiring a consultant to work with community to develop trail alignment alternatives. The current effort of the task force is to secure grant money to hire a consultant to develop alternative routes for the trail between Cupertino and Mountain View. Task Force met on February 17, 2011 and made a presentation on Stevens Creek Corridor Trail and creek restoration. The next Task Force meeting is May 19. The meeting will be at Blackberry Farm and will include a tour of the trail. The four cities hope that with consultants help we will have options for the Stevens Creek Trail to connect between Cupertino and Mountain View. Sunnyvale providing most of the funding, but all cities are contributing. The consultant will begin in late March and end by December 2012. B. Provide report on Pavement Management annually in May. 2012 Annual Report to go to Council in May. Annual report to include multi-year preventative maintenance strategy that balances available funds with prioritized needs. C. Investigate additional parking opportunities around Civic Center. Council assigned Vice Mayor Orrin Mahoney and Councilmember Gilbert Wong to work with Public Works. Council approved a $50,000 CIP budget for 2011-12 to conduct a Civic Center Master Plan, to include a parking analysis. This work is underway and will be presented to the committee in Spring, 2012. Additional 11 parking spaces being proposed on Rodrigues including two spaces with electric vehicle charging stations. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 12 of 36 D. Develop Trash Plan as part of City’s Municipal Regional Storm Water Permit Bring draft plan to Council for approval for achieving 40% city-wide trash reduction. Item will go to Council in March, 2012. Council may amend plan in September 2012 or September 2013. Implementation to occur by July 1, 2014. Decision on whether to include Single-use bag ban will be key element of plan. E. Annual Forestry Workplan A new ordinance requirement to develop annual public tree workplan that focuses on asset inventory, conditions, and set standards for their care. Establishes goals and objectives to promote healthy trees through City. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 13 of 36 3. Organizational Improvements A. E-Services Bring City Hall to the customer and improve efficiency of service delivery. 1. E-Services Applications in process: • Working towards the ability to accept and edit plan sets in a digital format. • Inspector Portal created to increase efficiency of inspectors in the field allowing for improved customer service. • GIS Urban Forest Management inventory. • GIS updated streetlight inventory. • Paperless Agenda • Permit Tracking System • Paperless timesheets The City Clerk’s office provided training and distributed iPads to the City Council, Planning Commission, and Department Heads, Building Inspectors, and other key staff. All paper copies of City Council and Planning Commission packets have been replaced with digital copies. In the six months from June 2011 through Feb 7, 2012, the project saved $9,670 in printing costs for the City Council packet alone. Applications completed: • Comply with new credit card security rulings. • Pavement Management on web. • Code Enforcement tracking system. • On-line building permits for minor projects. • Building permit searches from our database for 1997 forward. • Upgraded Records Management System. • Permit application, payment and inspection scheduling. • Upgraded Park & Recreation registration system. • Phase I of on-line permit system is complete • Parking permits The City provides abundant public access to many meetings and city records using state-of-the-art software programs available through the City’s website. Through a digital records management program and an integrated document and video-streaming program, all users have access to all public document and video records. We can also provide council reports and bid documents on disk. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 14 of 36 Building Inspectors use the iPads to access email, photograph sites, and do data entry while in the field. The Code Enforcement Office began testing iPads in February 2012. Permit Tracking System - On February 21, 2012, the Council authorized the City Manager to execute a contract with CSI Magnet and Avolve Software Corporation for an amount of $484,410 with a contingency of $16,590. Calendar year 2012 will be spent implementing the new permit tracking system. The launch of the new system is expected in March 2013. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 15 of 36 2. Review of the development application process. Matrix Consulting Group completed the study on November 5, 2009. Staff report submitted to Council on December 3, 2009. The Council considered the item in May 2010 and directed staff to organize community focus group meetings. City Council reviewed the item on February 15, 2011and directed staff to initiate Ordinance amendments to simplify approval authority and improve readability and consistency in accordance with the recommendations. The City Council also directed staff to begin a separate project to include a limited review of the R1 ordinance related to notification, story poles and design review. The Planning Commission reviewed proposed Municipal Code Amendments and the Public Engagement Policy at its March 22, 2011 and April 5, 2011 meetings and recommended minor amendments. The Council adopted the Municipal Code Amendments and the Public Engagement Policy in November 2011. Internal improvements to date: • Open counter (Building, Planning, Public Works) at lunchtime • Reviewing handout material for revisions to simplify and improve readability • Flowchart Staff is also working on implementation of the on- line permitting system detailed later in this report. The system is expected to be rolled out in March 2013. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 16 of 36 B. Fiscal Strategic Plan The Plan: • defines the financial problem • analyzes the structure of the organization • identifies opportunities for decreasing expenses and areas of risk exposure • identifies opportunities for stabilizing our revenue resources • adopted each year in conjunction with the annual budget • Committee will meet during February/March/April to recommend revenue, expenditure and reserve policy opportunities for the 2012/13 budget. Recommendations this year include: • Consider a 2012 mail-in ballot to increase storm water/clean creek fees. Fees have not been updated since 1992. Consultant is complete. • Pursue TEA/ERAF Phase 2 with State legislation. • Revisit BMR unit requirements. • Refinance the City’s $44Million debt. • Adopt a PARS plan in lieu of Social Security for all part-time employees. • Amend and renew the Insight Agreement. • Amend and renew the Apple Agreement. • Revisit Library JPA formula C. Analyze and pursue opportunities to expand the City’s fiber network Since its approval by the City Council as part of the fiscal year 2009-2010 budget staff has been negotiating with Comcast to establish a new fiber connection to the Comcast facility at Imperial Avenue. As part of the current project, a consultant has been retained and is currently producing the design documents. This fiber backbone down Stevens Creek passes most major city facilities. Staff is exploring connection opportunities with and among these facilities as part of a future project. The City Channel switched from its original analog transmission network to a new, fiber-based digital carrier. Staff spliced into unused strands within the City’s fiber optic traffic network. This fiber pathway now links City Hall with the Comcast hub on Imperial Avenue. The signal is then routed to Comcast’s master head end in Santa Clara where it is inserted into the cable system as Cupertino Channel 26. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 17 of 36 4. Public Safety A. Neighborhood Watch Continue emphasis on Neighborhood Watch • As of April 2011, currently have 210 active Neighborhood Watch Leaders supporting groups. • Partnering with Target Store for National Night Out event in August. • Participated in City orientation of CERT graduates to connect them with Outreach programs in City. • Participated in Block Leader trainings, fall festival, Earth Day, National Night Out 2011 and City-wide Disaster drill. • Publish weekly crime report (Ecap) in a yahoo group. From July 2010 – April 2011: • Conducted 16 Neighborhood Watch presentations. Presentations at: o Boy Scouts working on “Citizenship in the Community” badge in area of neighborhood burglaries o Personal Safety for Retired Nurses Association o Back to School personal safety at a block party 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 18 of 36 B. Emergency Preparedness 1. Continue emphasis on Emergency Response (ER) and Preparedness CARES, CERT, MRC training and projects. • Provide ongoing training in various areas of disaster preparedness. • City received CREST award and CESA gold award for our disaster drill in October, 2009. • Citywide Disaster drill conducted in October 2011Transitioning services with the Fire Department and Marsha Hovey’s replacement. From July 2010 – April 2011: CERT - 11 residents trained CPR – 17residents trained First Aid – 0 residents trained Employees CPR –120 trained First Aid – 76 trained (mandatory training every two years) Kaleidoscope -- 30 PEP - 82 2. Managing registered and spontaneous volunteers Identify leadership to manage spontaneous volunteers. Currently coordinating all divisions responsible for volunteers to standardize administrative procedures regarding registration, skill sets and insurance coverage. • Volunteer application complete. • Volunteer manual being revised. • Volunteered Squared software program implemented City-wide. 3. Work with schools and staff for Active Shooter preparedness SROs conduct Code Red Training and Drills at 14 schools in Cupertino. 14 schools trained Expanding to Child Development Centers (on-site Day Care) 4. Bicycle Safety Presentations to students Bicycle Safety presentations made to students to help understand the rules pertaining to bicyclists. 8 elementary schools trained 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 19 of 36 5. Digital Media Safety Started awareness training to middle and high schools. Offering to parents and PTA’s at all schools. 3 middle schools 3 high schools 6. Bully and Respect Awareness Emphasis on cyber-bullying 8 schools received training 7. Stranger Danger Awareness for all elementary grades K-2nd grades 8 schools received training 8. Update the Stevens Creek Reservoir dam failure evacuation plan Draft is complete. Discussed with Disaster Council in January 2012. Next steps: • Sheriff to confirm perimeter control and evacuation areas • Public meeting (s) to discuss alert warnings and evacuation plan • Adoption 9. Disaster Recovery Plan In progress Santa Clara Emergency Wireless Network (SCEWN) has been installed in the city EOC. SCEWN is a back up network to key public service end points in the event of a disaster. Local Hazardous Material Annex Plan Complete and schedule for City Council approval 3/20/12 FUHSD Evacuation Memorandum of Understanding Complete and approve by FUHSD on 3/6/12 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 20 of 36 C. Traffic Safety 1. Walkability Implement “walkable city” concept. Ensure that the concept is present in all City development/redevelopment projects. Examples of recently approved walkable developments include: • Don Burnett Bicycle Pedestrian Footbridge • Stevens Creek Corridor • Crossroads 2. Review traffic safety issues a. Safe routes to school program Project completed summer 2011. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 21 of 36 b. Traffic Improvements around Schools The Sheriff’s Office, the City, the School District, and the residents continue to work together to improve the safety of vehicle, pedestrian, students and reduce traffic congestion on the primary roadways around the school. Four month pilot project at Monta Vista, Kennedy, and Lincoln involving deputies on over time and additional crossing guards. The program is now an ongoing partnership. Partners continue to examine other alternatives to reduce congestion. Working with schools, Sheriff’s Office, AMR, CHP and other community partners to increase awareness of the consequences of drinking and driving. SRO’s conduct Every 15 Minutes event at Homestead High School. Two-day event provides a realistic perspective to students about the dangers of drinking and driving. The results of the four month trial were positive. All parties involved agreed to continue the program through the school year when another evaluation will be conducted. A full report went to City Council in 2011. Entire senior class participates in program. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 22 of 36 c. Walk One Week (WOW) After a successful Walk One Week (WOW) in April 2010, the Teen Commission decided to have WOW in November 2010 and April 2011. The Commission seeks to include other West Valley schools. The Commission requested assistance from the Parks and Recreation Commission. The Parks and Recreation Commission wrote to other West Valley cities seeking participation. The Teen Commission will be meeting with other teen/youth commissions in February 2011. Spring 2011 WOW involved 11 schools and 2100 youth. April 2012 WOW being planned by the Teen Commission now. Walk one Week (WOW) had a successful November 2010 campaign involving nine CUSD schools. The second WOW campaign began March 30 and ended April 13, 2011. The Teen Commission met with other West Valley teen or youth commissions to ascertain interest in participating with their schools. Teen Commission reported to Council on May 3. 2011. WOW continues to grow in number of schools and number of participants each year. Cupertino Teen Commissioners presented on WOW at the region- wide youth conference on March 3, 2012 in Santa Clara. d. Track status of efforts to encourage walking/biking to school The Teen Commission and Public Safety Commission will continue to track efforts to encourage walking/biking to school. Teen commissioners are already considering opportunities to expand the WOW program for the coming year. 3. Provide pedestrian ramps at required intersections City has met all current obligations. We continue to install ramps as new development occurs and as part of our annual street paving program. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 23 of 36 D. Non-City Projects 1. Monitor the Santa Clara Valley Water District’s flood control basin project at Rancho San Antonio In process as managed by the Santa Clara Valley Water District. Project was approved by the SCVWD Board and construction drawings are under courtesy staff review. Excavated soils will be trucked to Lehigh Quarry, avoiding almost all diesel truck circulation impacts on Cupertino neighbors. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 24 of 36 2. Monitor the Lehigh reclamation/expansion project. Stevens Creek Elementary School is being monitored by the Air District per EPA directive. The County of Santa Clara continues public processes for the preparation of two applications relating to Lehigh Southwest and its constituent cement plant and quarry. Reclamation Plan Amendment for Permanente Quarry - Comprehensive (File No. 2250-13-66-10P) Reclamation Plan Amendment for Permanente Quarry East Materials Storage Area (File No. 2250-13-66-09P) Permanente Creek Water Quality Study – Provide data and review of other studies to determine if City should attempt to compel Regional Water Quality Control Board to enforce pollutant statutes against Lehigh. The Bay Area Air Quality Management District located a monitoring station at Monta Vista Park. It will monitor air quality for one year. A Revised Health Risk Assessment (HRA) from Lehigh Southwest Cement Company dated March 30, 2011, is available. This assessment is a draft, and is under review by the BAAQMD and the State Office of Environmental Health Hazard Assessment. This review is expected to be complete in June 2011. The public comment period for this Notice Of Preparation (NOP) will close on May 23, 2011. Following the NOP comment period, the County will begin work on the environmental studies and analysis for the EIR. The public Draft EIR is scheduled to be available Fall 2011. Lehigh (Hanson) applied for an amendment to the 1985 Permanente Quarry Reclamation Plan to include an approximately 89-acre area to be used for overburden storage identified as the East Materials Storage Area (EMSA). Council has held two study sessions and held many public hearings on these, and related matters. Staff continues to track this issue closely working with all necessary regulatory agencies. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 25 of 36 5. Housing A. Provide housing opportunities for Cupertino workers The General Plan update and Housing Element identified sites for additional housing units. The Santa Clara County Housing Trust Home Ownership Assistance Program is available to Cupertino teachers and other public service employees. The Cupertino Below Market Rate (BMR) program also gives priority to Cupertino teachers, public service employees and Cupertino workers. B. Cleo Avenue Affordable Housing Entitlement applications were filed in April 2011and City Council approved the use permit and tentative subdivision map in July 2011. The Final Map was approved by City Council on January 17, 2012. Building permit has been issued. Grading on the site has begun. Habitat for Humanity is currently hosting monthly meetings with potential program applicants at City Hall. In June 2011, they will hold an application meeting at the Cupertino Community Hall. C. BMR Manual Update Staff contracted with Keyser Marston to update the City’s Housing Mitigation Manual as well as recreate an administrative manual for the City’s BMR program administrator. The administrative manual used by West Valley Community Services was finalized in 2009. A draft of the Housing Mitigation manual, which details program policy was completed in early 2010. The revised manual contains changes to the BMR program required to address the The Housing Commission found the existing mitigation fees are insufficient to offset the impacts of development and recommended increasing housing fees for non-residential developments, including commercial development and residential developments that are too small (6 or fewer units) to require a BMR unit. The current fee structure was approved in 2007. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 26 of 36 outcome of the Palmer vs. the City of Los Angeles case which ruled that cities are unable to require BMR units in rental developments, incorporates the program changes adopted by Council in 2007 and includes amendments necessary to ensure the program is consistent with the recently adopted Housing Element. Staff will bring the revised manual to the City Council in conjunction with the next revision of the Housing Element in 2013. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 27 of 36 6. Economic Development / Redevelopment A. Encourage, retain and support healthy environment for retail growth There were twenty retail openings for the 2010 calendar year including Aqui, Addison Credit Union, Smoke Eaters, and V-Jones Salon. While this was fewer than the 2009, the 09-10 fiscal year openings exceeded 08-09. Over 100 “New Business Welcome Packages” were distributed in 2010 in partnership with the Chamber of Commerce. The Economic Development Committee is meeting regularly and providing input on the economic development work plan. The next meeting will take place sometime in August or September. Active outreach to landlords and brokers to facilitate re-tenanting, and the leasing of new mixed use space continues. • Assisted new business with planning/ building facilitation – including Flight Wine & Food, Kiddie Academy, and Kee Wah Bakery. • Two new retail/restaurant building pads were approved at the Crossroads Shopping Center in November 2011. • TJ Maxx/Homegoods and Party City have been announced as new Crossroads tenants, filling the entire space of the former Mervyn’s store. TJ Maxx/Homegoods is expected to open in May 2012. • Council authorized recruitment to fill the Economic Development Manager position with direction to get input from businesses on the position. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 28 of 36 Retention efforts include active outreach to business owners through direct meetings, and Chamber participation. Actively facilitated business input on the Development Permit Process and Green Programs, including the Green Building Ordinance. • The Cupertino Restaurant Association continues to bring value to our local dining establishments. In addition to the recent “Restaurant Bootcamp” event, the March meeting featured a presentation on gift card marketing. A new Dining Guide was printed featuring a more user-friendly map in 2011. • Continued outreach to the Asian business community through the Chamber’s AABC, including offering the Mandarin version of the “Should I Start My Own Business” class in partnership with SCORE and NOVA. The most recent class on April 27th was well attended and involved the Library as a new partner. An all- day “How to Start My Own Business Class” was offered in November 9, 2011. • Mayor Santoro will be hosting a Small Business Seminar on May 29th 2012 in coordination with the Chamber and Council. B. Consider retail in reviewing new development Advise on/facilitate new development projects. • Heightened office leasing activity (Apple, Seagate, Lab 126, etc.) will fuel more retail development as the daytime population continues to expand. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 29 of 36 7. Planning A. Review the Heart of the City The Council approved the Heart of the City Specific Plan on February 16, 2010. The second reading was conducted on March 16, 2010. The HOC Specific Plan became effective April 16, 2010. On November 15, 2011, the City Council approved amendments to the City’s Zoning Map, Heart of the City Specific Plan, and General Plan Land Use Map to make technical amendments. The amendments involved clarifications to language and the land use/zoning of particular sites in the Heart of the City Specific Plan. The changes became effective on February 16, 2012. B. Prepare a historic preservation policy The City Council reviewed and approved the recommended changes to the General Plan with regards to historic preservation policies on June 1, 2010. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 30 of 36 C. Update the General Plan Housing Element The Planning Commission and City Council reviewed a final draft of the Housing Element in March and April 2010 respectively. The final adopted Housing Element was then forwarded to HCD in late April 2010. The City received a letter from HCD dated June 24, 2010 stating the City of Cupertino’s Housing Element was in compliance with State law. The plan is available for distribution. D. Review of single family residential standards/requirements for: • Lots sloped 15% to 30% • Two Story Design Review • Notice Boards/Story Poles • Public noticing • General consistency and readability Ordinance amendments to the R1 ordinance were approved by the City Council in August 2011. • Ordinance amendments included: o Requiring design review only for larger second stories and those with smaller side yard setbacks o Eliminating the story pole requirement o Changing the public noticing radius from 300 feet to adjacent to the project site. o Applying select hillside standards to development on slopes greater than or equal to 20%. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 31 of 36 8. Building Community A. Continue to offer opportunities and programs to promote cultural understanding and address the needs of our diverse community Neighborhood block leader program supports 350 leaders. The Community Improvement Grant program is ongoing. “Around the Block,” an on-line quarterly newsletter for block leaders continues. The Block Party Program has expanded to include environmental options. The Block Leader Program celebrates its 10th anniversary at the Annual Recognition event on March 15. Leaders who have volunteered for 1, 5 and 10 years will be honored. Other meetings this year include updates from the Sheriff’s Office and a bus tour highlighting current and future development in Cupertino. Nine issues have been produced. Presentations in how to lower energy bills and home energy and water assessments are offered. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 32 of 36 B. Leadership 95014 Bring proposals for restarting program as part of 2009/2010 budget. Program began with a two-day retreat in September 2010. There were 13 participants. Program rebranded as Leadership 95014. Second session “The Cost of Going Green” sponsored by PG&E was held in October. Third session “Keeping Cupertino at the Head of the Class” focused on Cupertino public schools from K – Community College. The fourth session focused on community needs and services as well as making ethical decisions. The fifth session was on March 3 and focused on High Technology. Participants completed a project of community benefit. The sixth session on April 14 addressed retail development, latest demographics for Cupertino and Block Leader program. Leadership 95014 received City funding for 2011/2012. Wilfred Jarvis Institute, PG&E, and Recology are also sponsors. Second class began September 2011 and will conclude May 2012. There are 15 participants in this year’s program. Minh Le and the Cupertino based Wilfred Jarvis Institute are providing the personal leadership development training pro bono. Participants gave positive feedback about Leadership 95014 at the program’s mid-point evaluation on January 20, 2011. May 19 the participants present their projects followed by a personal leadership session with Minh Le. The Graduates were honored at the June 7, 2011 council meeting. The second year of Leadership 95014 appears to be going well. Good feedback from the participants. Two sessions remain, the Community Services/Ethical Leadership Day and Project Presentations and Graduation. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 33 of 36 9. Community Organizations A. Support the Cupertino Historical Society in its effort to create a Center for Living History Staff and the Parks and Recreation Commission met with the Historical Society to define a project that a majority of the Cupertino Historical Society Board will endorse. Cupertino Historical Society is no longer pursuing the Center for Living History or the Stocklmeir project. The City re-roofed the Stocklmeir house in 2008. The Historical Society has sent a letter to the City Manager expressing support for the trail connecting to Stevens Creek Blvd. so long as the multi-use trail is kept close to the creek with a footpath through the orchard. In June 2008, Council referred Stocklmeir project to Parks and Recreation Commission to study options. Went to Council on August 4, 2009. Council supported the vision of a legacy farm. Issue will return to Council when a more detailed plan is developed. The Council approved $450,000 in the CIP Program for this project for FY10-12. B. Pursue partnership opportunities with the three school districts: 1. Traffic and parking The Safe Routes to Schools projects have proceeded with excellent cooperation between the City and Monta Vista, Cupertino and Garden Gate. Added three crossing guards in 2008. Teen Commission sponsored a Walk One Week (WOW) for Cupertino schools in April 2010, November 2010, and April 2011. WOW for April 2012 being planned by the Teen Commission now. Construction of the Garden Gate Safe Routes to School project, which includes sidewalk, curb ramp, and traffic signal improvements, is expected to commence Summer 2011. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 34 of 36 2. Teacher housing See Section 5A (Housing) 3. School Resource Officers Funded second SRO in FY 2011/12with COPS grant from the State. CUSD & FUHSD contribute $10,000 each to this program with a COPs grant of $100,000. 4. Juvenile Intervention Program Contracting with Linda Rios for Outreach Services CUSD contributes 50% of the cost of this program. 5. Recycling De Anza/City recycling program – the City gives De Anza used computers and De Anza refurbishes them. 6. Summer School Program Worked in partnership with FUHSD to provide summer school in 2009. Program expanded in 2010. Program will be expanded and continued in 2011 and 2012. 7. Placement of Arks (emergency supplies) at school sites. Arks are currently located at Garden Gate, Lawson, Hyde and De Anza College with a cooperative agreement with the schools for mutual use & storage of supplies. Each Ark costs approximately $10,000 to purchase equipment. Staff will continue to look for additional school sites that can accommodate and support these Arks. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 35 of 36 10. Go Green A. Develop Sustainability Compliance Programs Local government “sustainability compliance” is addressed in Cupertino, and the majority of Bay Area Cities and Counties, via the following activities: • Achieve AB32 Local Targets : o Complete Municipal Greenhouse Gas (GHG) Emissions Inventory o Complete Communitywide GHG Emissions Inventory o Set a municipal & community GHG reduction goals o Develop a Climate Action Plan (see below) • Adhere to updated CEQA Guidelines: o BAAQMD set “Thresholds of Significance” for plans (i.e. General Plan Updates) to be addressed in a GHG Reduction Strategy (i.e. Climate Action Plan) • Implement state green building code and facilitate green building construction, renovation, operation, maintenance, etc (see comments) GHG Inventories - In 2009, staff completed both a Municipal & Community-wide Greenhouse Gas Emissions Inventory. Supported by Joint Venture Silicon Valley’s Public Sector Climate Task Force, staff is currently updating the inventories for 2010. Climate Action Plan - Staff is working with local jurisdictions to create a Climate Action Plan template to leverage grant resources to cover the cost of developing this report and monitoring tool. Green Building Ordinance - In January 2010, the Council authorized staff to work on a Green Building ordinance. In June and July 2010, the City held two focus group meetings to get public input. In November 2010, the Planning Commission recommended approval of the draft ordinance. The Council reviewed the draft in February and May2011 and directed staff to begin a one-year public review period of the ordinance. The ordinance is expected to be reviewed by the Council in May/June 2012. 2011/2012 City Council Work Program Project Status Comments 2011/2012 Council Work Program (March 14, 2012) Page 36 of 36 B. Look for ways to become more resource efficient. To achieve utility and financial savings, staff have designed and implemented over a dozen local, regional and statewide efforts including but not limited to: • Water Efficient Landscaping Ordinance - Completed • Energy Service Agreement • Utility Accounting • Renewable Energy Procurement Energy Service Agreement Update Siemens reports and our staff have confirmed that the street light project is 100% complete. Some minor work continues on park and parking lot lighting. Approx. 2,950 lights have been installed. Work on irrigation controllers has also been completed. With both elements of the project installed, the city will reduce its electricity bill by 813,003 kwh of electricity, reduce its water bill by 34,374,394 gallons, and save at least $235,882 each year. Utility Accounting – Through the Climate Action Plan Project (above), staff is working to utilize a tool that will enable better monitoring and tracking of municipal utility consumption. Renewable Energy Procurement Staff have requested Council direction on whether or not to engage in Phase II of the Joint Venture Silicon Valley-led Regional Renewable Energy Procurement Project (R-REP) for the Corporation Yard site. This project phase will evaluate the feasibility of including additional technologies (i.e. wind, solar, fuel cells) and accessing additional financing mechanisms (i.e. direct purchase, lease- to-own, or power purchase agreements).