22. Mary Ave Bicycle Footbridge
PUBLIC WORKS DEPARTMENT
CUPERTINO
Summary
AGENDA ITEM
J).
AGENDA DATE AU2Ust 21. 2007
SUBJECT AND ISSUE
Approval of the Cable Stayed Structural Steel Alternative Design Concept for the Mary
Avenue Bicycle Footbridge in lieu of the Prestressed Concrete Design previously
Approved by the Council.
Authorize the City Manager to negotiate and execute a contract with HNTB, Inc. (NE
Division) for the alternative structural steel design of the project at a cost not to exceed
$ 725,000 and $50,000 in additional services, which may be approved by the Director of
Public Works.
Authorize the City Manager to negotiate and execute a contract with Leslie E. Robertson
Associates (LERA) for the peer review and plan check and other necessary structural
engineering services of the steel design alternate in an amount not to exceed $120,000
with $30,000 for additional services, which may be approved by the Director of Public
Works.
BACKGROUND
On December 5, 2006 the Council accepted a progress report on the Mary Avenue
Bicycle Footbridge Project. The project is a single span cable stayed bridge over Interstate
Route 280 connecting an established bicycle trail system on Mary Avenue in Cupertino
on the south side of 1-280 to Mary Avenue in Sunnyvale on the north. The design
concept, developed by city staff and the design consultant team of Biggs-Cardosa
Associates and HNTB, Inc had been approved by the Council on February 1,2005.
The project was advertised for competitive bidding on March 2,8, 2007 and bids were
received and opened on May 3, 2007 resulting in two bids, both of which were in excess
of $12 Million which represented a variation of 100% over the Engineer's estimate. On
Staff s recommendation, the Council acted on May 10, 2007 to reject both bids and
authorize the Director of Public Works to evaluate the plans and specifications, review
the estimate and report back to Council with recommendations regarding the re-
advertising of the project.
1
ANALYSIS
The staff has followed two separate but parallel tracks of action in analyzing the bids and
reconsidering the design components of the project.
The first track (A) involved the original design team (Biggs-Cardosa Associates and
HNTB, Inc) and the construction manager (Swinerton CM) working with staff to both
determine the accuracy and/or insuffi~iency of the original engineer's estimate of $ 6.3
Million as well as to consider changes in the documents and some additional value
engineering to attempt to further reduce the cost. This work was performed by the design
team at no additional cost to the City.
The second track (B) involved an outside consultant team of structural and civil engineers
to also consider these issues independently of the first track and, in addition, to suggest
alternative designs that could substantially reduce the cost of the current concrete
alternative. This team included the Northeast Division of HNTB and the structural
engineering firm ofLes Robertson and Associates (LERA). Both of these two consultants
are located in New York City and are working independently of the local team.
FINDINGS
After a great deal of analysis and review of the estimates, quantities, bidding climate and
other considerations, the local design and CM team, along with the New York City team,
the activities and conclusions from both Track A and Track B Teams have discovered a
number of factors that contributed to what now is clearly a significantly insufficient
estimate of $ 6.2 Million for construction of the bridge.
These factors fall into three specific categories. These categories are (1) factors that the
design team should have known or had been reasonably able to determine before the
project was advertised and, as a result, incorporated into the estimate, (2) factors which
may have come into being as the project was being bid in March-May time frame, and (3)
factors which no-one could have predicted or even imagined would be present in such
measure as to radically affect the bids received. A detailed discussion of these categories
is contained in Attachment 'A' of this report. However, a summary of these categories
and their probable impact on the Cost Estimate is as follows:
Original Bid - Engineer's Estimate (May 2007)
$ 6,200,000
Category 1 Impacts
Category 2 Impacts
Category 3 Impacts
(Costs, timing, constructablity)
(Bidding Climate/Market)
(Unknowns during bidding)
4,500,000
1,500,000
500,000
Total with Probable Impacts on the Bid:
$12,500,000*
*The.actuallow bid was $ 12,446,732
2
Given the resources available to the original designers, it is unclear why all this
information and the resulting cost factors and impacts in both Category 1 and 2 above
were not addressed in the bid. The reviewers from outside firms and the contractors
themselves have all pointed this out in the course of the evaluation of the project post-bid
openmg.
Estimates of the effect these factors, if acknowledged in the Engineer's Estimate would
have added up to $ 4-5 Million to the estimate back in May 2007, which would have
resulted in an Engineer's Estimate of at least $11 Million.
CONCLUSION
As a reminder, it should be noted first and foremost that this Cupertino project is the only
cable stayed pedestrian bridge over an Interstate Highway in California. Unfortunately,
that fact notwithstanding, the inescapable conclusion is that others appeared to have had a
better picture of the cost of the construction of this project than our consultants had when
the proj ect was bid.
It would have served the City's decision making process better at the time had the City
known of this potential. Staff instead relied on the special expertise and experience of our
design team, particularly the structural engineers, Biggs Cardosa Associates. However,
the consultants failed to accurately define the expected price in bidding the project, and,
as a result, City finds itself in its current awkward position after the bidding process.
All the factors discovered since the bid opening have contributed to the conclusion that
the current engineer's estimate for the bridge, corrected for escalation, is more accurately
expressed as $13,000,000, almost $ 7 Million greater than the original estimate and more
closely aligned with the bids received over three months ago on May 3,2007.
Other factors, a longer period of construction management and oversight, a larger
contingency, as well as the cost of the value engineering efforts will all combine for a
total cost for the entire project of at least $19.6 million. With the current revenue of $10.7
Million, to proceed with rebidding even a revised concrete design, the project would
require that the City invest almost $ 9 Million in additional General Fund resources to
advertise the repackaged project for competitive bids.
However, for all the reasons noted above, the fact remains that if we re-bid the
current concrete design, there is no guarantee that the bids we might receive will be
less than those received previously. In fact, they might be even higher now that the
project has been advertised in the current volatile bidding climate.
In conclusion, for all these reasons staff does not recommend proceeding with the
project as currently designed.
3
STEEL BRIDGE DESIGN ALTERNATIVE
The New York VE (Value Engineering) team of HNTB NE Division and Leslie
Robertson and Associates (LERA) in addition to evaluating the current concrete design
and its erroneous estimate along with the City's construction manager, Swinerton CM,
have all concluded that a much more efficient and cost effective design would be to
construct the bridge out of structural steel instead of concrete.
A preliminary design was authorized by staff to evaluate the cost and schedule impacts of
redesigning the project with the same architectural concept (two A-frame towers with a
cable stayed deck spanning the entire reach of Interstate 280) but constructed largely from
structural steel. The architectural appearance and striking nature of the design would be
maintained and, as such, there would be very little difference in appearance from the
original concrete design. However, what we have learned in this evaluation process is that
for a cable-stayed structure, steel is easier to fabricate and erect and, when all things are
considered it is potentially less costly than the high strength concrete bridge as currently
designed.
We did not initially consider a steel bridge alternative because there was no indication
from any comer of the industry at that time, especially from our consultants, that the
concrete bridge would be so much more complicated to build and, as a result, more
expenSIve.
Steel Bridge Advantages
The advantages of moving to a steel bridge alternative are largely derived from two
factors. The steel bridge is not as heavy as the concrete bridge and it is much easier to
construct. The result of these two factors provide a number of advantages as follows:
Towers: The steel towers can be fabricated in a steel shop and transported to the site.
They can be fabricated in half sections to facilitate transportation and erection in place.
Because there is no need to use concrete forms and a complex array of reinforcing steel
nor for the curing and heat control of high-strength concrete, the construction schedule is
shorter and the tower construction is considerably simplified as are the cable connections.
Also, the use of a modem paint system reduces maintenance demands.
Superstructure: The steel framing eliminates the need for heavy falsework (the
temporary supports under the bridge and over the freeway) and using erection towers
instead provides for the fabricated girders for the deck sections to be placed with less
impacts to traffic (fewer lane closures) and it can be done more expeditiously. The precast
concrete deck material placed on the girders is also done more expeditiously and the
quality control is improved. (Council may recall that our choice to use prefabricated
columns and girders .on the portico in the Civic Center resulted in very high quality
materials and finishes.) Also, the reduced mass and cross-sections have been shown to be
extremely stable for wind effects and while reducing the seismic forces as well.
4
Stay Cables: Reduced superstructure weight of the steel bridge allows for more compact
stay cables, which are less expensive to fabricate and erect, and behaves very well during
a seismic event. Also the connections on the tower and on the deck are much easier to
install and tension before removal of the temporary erection towers.
Steel Bridge Cost Offsets
While the construction cost will be less than concrete there will be some offsetting
expenses that must be incurred for this alternative. The redesign cost for the New York
team to convert the project as now designed into a steel structure would be $725,000 plus
$50,000 in potential additional services, which, among other things, includes a new wind
tunnel test for the steel version. The cost of the peer review and plan check by LERA is
$120,00 plus $30,000 in potential additional services. It is expected that the design can be
completed and a final engineer's estimate provided to the Council no later than October
2007 and, with Council approval and additional funding the project can proceed to the
bidding process with a construction start in January 2008, a delay of six months.
A summary of the project cost projections for the two options of re-bidding the concrete
bridge and proceeding with the design and construction of the structural steel alternative
is shown below.
BUDGET I COST COMPARISON - MARY A VENUE BICYCLE FOOTBRIDGE
Item Re-Bid Concrete Bid Steel
Feasibility Study (Completed 2002) $ 210,000 $ 210,000
Phase I Construction (Completed 2005) 620,000 620,000
Design of Concrete Bridge (BCA) 2,310,000 2,310,000
AdminlPermitslFeesNE 850,000 810,000
Construction Phase Services (BCA) 530,000 0
Steel Design Alternative (HNTB-LERA) 0 775,000
Peer Review/Plan Check (LERA) 0 150,000
Construction Phase Services (HNTB) 0 425,000
Construction Management (Swinerton) 925,000 900,000
Cost Estimate - Bridge Phase II 13,003,000 10,085,000
Construction Contingency 1,300,000 1,000,000
Art 145,000 145,000
V alue En~ineering Deducts (275,000) (400,000)
Total $ 19,618,000 $ 17,030,000
Revenue (10,734,000) (10,734,000)
Shortfall $ 8,884,000 $ 6,296,000
5
As shown, with additional value engineering incorporated into the steel structure design,
the current expectation is that the additional project cost for a steel structure on a January
2008 start date is expected be approximately $ 6.3 Million rather than $ 8.8 Million (or
more) as would be expected the current concrete design.
Staff is therefore recommending that the Council authorize the City manager to negotiate
and execute both an agreement with HNTB (NE) in an amount not to exceed $ 725,000
with $50,000 for additional services which may be approved by the Director of Public
Works for the redesign of the bridge to a steel structure, and with Leslie E. Robertson
Associates (LERA) for the peer review and independent plan check in an amount not to
exceed $120,000 with $30,000 for additional services which may be approved by the
Director of Public Works.
SCHEDULE
Should the Council approve the staff recommendation to proceed with the design of the
steel bridge alternative, the approximate schedule would be as follows:
Event
Date
Design and Bid
Approval of Steel Design Contracts
Approval of Estimate, Bid and Budget and
Advertise Project (8 weeks)
Open Bids and Award Contract
*(Council consideration at Council Meeting)
August 21, 2007*
September-October 2007*
November 2007*
Construction
Structure Completion - Bridge Dedication
Proj ect Completion
December 2008
March 2009
The Council should note that this is an extremely aggressive and optimistic schedule at
every point, which relies on the ability of staff and consultants to meet certain milestones
along the way, including redoing the wind tunnel test at a laboratory in Canada and a
fairly aggressive review timeline for Caltrans for the steel bridge. All players have
pledged to make every effort to meet these goals. However there still could be, as yet
unknown, pitfalls that might arise which could affect this schedule.
FISCAL IMPACT
There is no immediate fiscal impact from this action as sufficient funds are available in
the project budget for this redesign work. The funds available in Account No. 428-9449-
9300 are a combination 80% grant and 20% General Fund consistent with the revenue
allocation in the current adopted budget.
6
However, should the Council authorize staff to proceed when the final design report is
presented to Council later this year, at that point as the project goes out to bid, an
additional appropriation of approximately $6 Million would be necessary. Should that be
the case staff would recommend appropriate funding sources for this effort at that time.
STAFF RECOMMENDATION
Approval of the Cable Stayed Structural Steel Alternative Design Concept for the Mary
Avenue Bicycle Footbridge in lieu of the Prestressed Concrete Design previously
Approved by the Council.
Authorize the City Manager to negotiate and execute a contract with HNTB, Inc. (NE
Division) for the alternative structural steel design ofthe project at a cost not to exceed
$ 725,000 and $50,000 in additional services which may be approved by the Director of
Public Works.
Authorize the City Manager to negotiate and execute a contract with Authorize the City
Manager to negotiate and execute a contract with Leslie E. Robertson Associates (LERA)
for the peer review and plan check and other necessary structural engineering services of
the steel design alternate in an amount not to exceed $120,000 with $30,000 for
additional services which may be approved by the Director of Public Works.
Submitted by:
Approved for submission:
:a~A~ffi7!!:Ud Lf:f
Director of Public Works
~
David W. Knapp
City Manager
7
ATTACHMENT A
CONCLUSIONS REGARDING THE ENGINEER'S ESTIMATE
Category 1 - Factors that should have been known:
Apparently the Design Consultants relied mostly on Caltrans published reports of bid unit
prices from current and past projects. None of this information reflected the complexity
of the design, the difficulty of the construction, nor the condensed time frame. An
example of the impact of the condensed time for construction is that the limited time (10
months) would have required the contractors to build both towers at the same time,
thereby doubling the cost of forms, labor and scaffolding along with additional traffic
control on the freeway.
Further, it is apparent that the specialty pricing from suppliers and vendors (particularly
concrete, steel and cables) did not the reflect actual prices being experienced on the job
when a contractor adds profit and overhead to account for a difficult fabrication process
during construction.
Given the resources available to the original designers, it is unclear why all this
information and the resulting cost factors were not addressed in the bid. The reviewers
from outside firms and the contractors themselves have all pointed this out in the course
of the evaluation of the project post-bid opening.
Estimates of the effect these factors, if acknowledged in the Engineer's Estimate would
have added up to $ 4-5 Million to the estimate back in May 2007. The analysis and
evaluation of those bids clearly indicate that these factors alone could have resulted in an
Engineer's Estimate of up to $11 Million.
Even though the bids were over that at approximately $12.5 - $13 Million, it would have
served the City's decision making process better at the time had the City known of this
potential. Staff instead relied on the special expertise and experience of our design team,
particularly the structural engineers, Biggs Cardosa Associates, and the City has invested
over $2 million in this effort. As noted above, the consultants failed to accurately define
the expected price in bidding the project which has put the City in the current awkward
position after the bidding process.
In short, the City should have been advised of this situation well ahead of advertising for
competitive bids. The unfortunate consequence of that situation is that the project, in its
current form, is "tainted" by the combination of two bids in excess of $ 12 Million that
are now on the record along with the revelation by the City's consultants that the estimate
was seriously in error.
Category 2 - Factors that may have affected the bid pricing during the bidding period:
It is clear from the outside reviews and our interviews with the contractors that the
construction bidding market is, without exception, more volatile than it has ever been
since the construction of the Interstate system in the 60's and 70's which had the
unforeseen effect of placing the contractors in an extraordinary buyer's market.
This situation was compounded by the fact that there was and is an unusually high
volume of projects (many in the $50 - 100 million category) such that contractors can
pick and choose with the effect of loading more profit and risk avoidance onto smaller
and more complicated projects like the Mary Avenue Bridge. That volatility was
apparently rapidly increasing as the Bridge project went out to bid.
Category 3: Unpredictable factors unknown at the time the project was bid.
Several contractors dropped out of the competition right before the bid deadline to
compete for the Oakland 1-580 ramp repair, which had the potential for a very big profit
in a very short period of time. If contractors are aware that there are very few bidders on
any given project (only two bidders were left on this project), they will be more
conservative (i.e., pricier) with their bids. This was completely unforeseen when the
project was advertised. It is impossible to speculate on this potential but it may have had
very little effect or up to 10 percent ($1,000,000) or more.
Summary of Probable Impacts on Engineer's Estimate
Original Bid - Engineer's Estimate (May 2007)
$ 6,200,000
Category 1 Impacts
Category 2 Impacts
Category 3 Impacts
(Costs, timing, constructablity)
(Bidding ClimatelMarket)
(Unknowns during bidding)
4,500,000
1,500,000
500.000
Total with Probable Impacts on the Bid:
$12,500,000*
*The actual low bid was $ 12,446,732
.~..- , ~-:'... ..._-
-
...:;
. .'.~.
- '-" "
.II'
~
"'.
~, ~\
I ~ 11
\' Ii'
110.'I
\1
~1 ~,
~
\~
l'
~
.,
..
\~ \~.
'~
~l
\
.'~
" '\
'V
-...- .
,