Loading...
14. Mary Ave Bridge contract award PUBLIC WORKS DEPARTMENT CUPERTINO AGENDA ITEM ~ Summary AGENDA DATE November 20.2007 SUBJECT AND ISSUE Appropriation of $ 716,000 from the Gas Tax Reserve and from accumulated operating savings from the FY 2006-2007 Budget to the Mary Avenue Bicycle Footbridge Project in the 2007-2008 Capital Improvement Program. Acceptance of a budget Augmentation from the Valley Transportation Authority for the Mary Avenue Bicycle Footbridge Project in the amount of $3,350,000. Restore the Project Budget Augmentation allocated to the Mary Bicycle Footbridge project to support the bid process to the Stevens Creek Corridor project budget in the amount of$ 5.701 Million in FY 2007-2008 and in the amount of $1.000 Million in FY 2008-2009. Award of a Contract to for the Phasell construction of the Mary Avenue Bicycle Footbridge in the amount of $7,469,735 to Golden State Bridge Inc. and the allocation of a construction contingency in the amount of $ 1,000,000. Authorize the City Manager to negotiate and execute a contract with Aidala Studios for the fabrication of the project sculptures as approved by the Council in an amount not to exceed $145,000. Authorize the City Manager to negotiate and execute Amendment No.1 to the Design Services Contract with HNTB, Inc for Architectural and Engin~ring services during cons:truction in an amount not to exceed $425,000 for a total contract amount not to exceed $1,200,000. BACKGROUND On December 5, 2006 the Council accepted a progress report on the Mary Avenue Bicycle Footbridge Project. The project is a single span cable stayed bridge over Interstate Route 280 connecting an established bicycle trail system on Mary Avenue in Cupertino on the south side of 1-280 to Mary Avenue in Sunnyvale on the north. The design concept, developed by city staff and the design consultant, Biggs-Cardosa Associates, had been approved by the Council on February 1,2005. The project was advertised for competitive bidding on March 28, 2007 and bids were received and opened on May 3, 2007 resulting in two bids, both of which were in excess of $12 Million which represented a variation of 100% over the Engineer's estimate, On Staff's recpmmendation, the Council acted on May 10, 2007 to reject both bids. . 14 - 1 1 On August 21 ~ 2007, the Council approved a design alternative for the bridge to be constructed of structural steel in lieu of the previously approved pre-stressed concrete design and approved design services contracts with HNTB~ Inc. in the amount of $775,000 and LERA Associates in the amount of $150,000. Staff was requested by the Council to report back in late September with a new Engineer's estimate based on the steel design and with appropriate recommendations for budget augmentations to proceed with the bidding of the project On September 18, the Council received a Report of the Cost Estimates and Bid Package for the steel bridge design of the Mary Avenue Bicycle Footbridge. The final estimate of probable cost for the bridge construction was determined to be $10~205,OOO. The final estimate of the project budget was detennined to be $17, 435,000. In consideration of that report, the Council approved a project budget augmentation to support the bid process in the amount of$ 5,701,000 in FY 2007-2008 and in the amount of $1,000,000 in FY 2008-2009 for the Mary Avenue Bicycle Footbridge Project. This budget augmentation was approved with the understanding that the staff would seek additional funding from the Valley Transportation Authority (VTA), the primary sponsor of the project In addition, the Council authorized the Director of Public Works to advertise the project for competitive construction bids. VTA Funding Augmentation As part of the Council request to seek other funding, Staff has initiated discussions with the VT A to determine what, if any, funding might be available with the VTP 2030 Bicycle Fund. Staffhad requested that the VTA consider the status and certainty of other projects in the County, and, to the greatest extent possible, advance additional funding from the VT A Bicycle Expenditure Plan. The VTA staff recommended that funding be increased for the Mary Avenue Bicycle Footbridge in an amount of $3~350,000 for a total VTA funding commitment of $10,350,000. with the understanding the City would provide an equal match in additional funding as follows: VTP 2030 Project Bll $ 10,000,000 Additional VT A Funding (11-01-07) $ 3.350.000 Tota~ Proposed VTA Funding $ 10,350,000 On November 1~ 2007, following approvals by the VTA Bicycle Pedestrian Advisory Commission and substantial consensus from the Technical Advisory Committee (T AC) and Congestion Management Planning and Program Committee (CMPP) the VTA Board considered the VT A staff recommendations. The Board voted unanimously to approve the funding allocation recommended by staff in the amount of $3,350,000 for a total VTA commitment to the project of $1O,350~000. ' This amount, combined with the prior funding allocations, including an additional amount of General Funds from the City as noted below will fully fund the estimated cost of the project.. The steel bridge project was advertised for competitive biding on September19~ 2007 and bids were received and opened on November 13, 2007. 14 - 2 2 REPORT ON CONSTRUCTION BIDS Construction bids were received and opened on November 13, 2007 with the following results: Bidder Bid Amount % Difference ENGINEER'S ESTIMATE $10,205,000.00 FCI Constructors Inc. $ 8,437,655.00 (17 %) California Engr. Contractors, Inc. $ 7,748,184.00 (24%) Anderson Pacific Engr. Construction $ 7,729,469.00 (24% ) Proven Management, Inc $ 7,431,205.00 (27%) Golden State Bridge, Ine. $ 7,329,903.00 (280/0) s noted above the apparent low bidder, Golden State Bridge, Inc. is $2,875,097 below the engineer's estimate of $10,205,000, a variance of -28% which is an exceptional price for this project. In addition, there were several bid alternates included which were estimated to be a total of $178,000. This was not included in the project budget. However, now that we the City has received such a good price, staff is recommending that the alternates be included in the award of the contract. The low bid from Golden State Bridge, Inc. , inclu~ed a price of $139,832 which is well below the estimate. A list ofthe alternates is shown on Attachment B. The combination of the low bid and the add alternates brings the contract award to a total of $7,469,735. That bid price, if accepted will bring the final project cbst (rounded to $1,OOO's) to a total of $14,800,000. A revised project budget which reflects the low bid and the additional VTA Funding, is shown on Attachment A. CIP Budget Addition Required to fInish proiect: , FY2007-2008 Final Project Cost with Low Bid $ 14~800,000 Funding Resources: Current Funding VTA Add'l Funding Total Funds Approved $ 10,734,000 3.350.000 ($ 14.084.000) Additional City GF to Award Contract $ 716,000 Total GF $ 2,691,000 18% Other Funds $ 12,109,000 82% Leverage = 5.5 to 1 14.3 3 SCHEDULE With the successful award of the contract, the current schedule as reported to the Council on December 5, 2006, is expected to prevail as follows: , Bid and Award Construction Contract Stmcture Completion / Open Bridge Final Completion November 20 December March 2007 2008 2009 PROJECf ART City policy requires that 1/4% of the constructed cost of a project be allocated for the installation of public art. Because of the visibility and importance of this bridge project a 1.4 % art allocation ($145,000) was included in this project budget. '. The concept approved by the Council, and on which the Fine Arts Commission concurred, was developed by Tom Aidala, a noted artist and architect, and will place sculptures of a family of California native quail elevated on a cluster of granite boulders, and a red-tailed hawk elevated on a pedestal near the approach path on the Cupertino side of the bridge. An additional item on this agenda is the authorization for the City Manager to negotiate and execute a final design and sculpture fabrication contract in an amount not to exceed $145,000. ANNUAL FACILITY MAINTENANCE COSTS The City's agreement with Caltrans requires that the City, assume responsibility for the care and maintenance of the bridge superstructure (towers, cables, bridge deck and lighting, etc.) and the pathways on either side while Caltrans will be responsible for maintenance in their right of way along the freeway. This arrangement was established because it is important that the City have control over the bridge and its appearance. In addition it will ensure that no freeway signage or other fixtures are arbitrarily placed on it. Very little in the way of maintenance costs is expected on the new bridge for some years, and everything planted will be on a warranty for up to six months. There will be an annual cost for some minor maintenance, but it is estimated that the cost will not exceed $10,000 annually after the first year. FISCAL IMPACT An additional amount of funding for the project of $ 716,000 is required. The following approach is recommended for funding of the project and award of the Construction contract to the low bidder. Uncommitted General Funds - Gas Tax Funds $ 716.000 Current CIP Savings through FY 2006-2007 $ 116,000 Gas Tax Reserves $ 600~OOO Total Unallocated GF $ 716,000 14 -4 4 Smce this is not new money but is instead either fuD.ds that were achieved through savings duriI ,the course of the budget year or additional revenue not included in the budget, the additiOnal funding in the amount of $ 716,000 for this project is proposed to be advanced from these sources. Lastly, the Council, on September 18, 2007 had authorized the approval of a Project Budget Augmentation from the Stevens Creek Corridor project budget to support the bid process in the amount of $ 5.701 Million in FY 2007-2008 and in the amount of $1.000 Million in FY 2008- 2009 for the Mary Avenue Bicycle Footbridge Project. Since the amount of the low bid is now known and staff has recommended appropriate funding to award the contract, this allocation is no longer necessary and the funds for the Stevens Creek Corridor should be restored to the project. RECOMMENDATION Appropriation of $ 716,000 from the Gas Tax Reserve and from. accumulated operating savings from the FY 2006-2007 Budget to the Mary Avenue Bicycle Footbridge Project in the 2007-2008 Capital Improvement Program. Acceptance of a budget Augmentation from the Valley Transportation Authority for the Mary Avenue Bicycle Footbridge Project in the amount of $3,350,000, Restore the Project Budget Augmentation allocated to the Mary Bicycle Footbridge project to support the bid process to the Stevens Creek Corridor project budget in the amount of $ 5.701 Million in FY 2007-2008 and in the amount of $1.000 Million in FY 2008-2009. Award of a Contract to for the Phase II construction of the Mary Avenue Bicycle Footbridge in the amount of $7,469,735 to Golden State Bridge Inc. and the allocation of a construction contingency in the amount of $1,000,000. Authorize the City Manager to negotiate and execute a contract with Aidala Studios for the fabrication of the project sculptures as approved by the Council in an amount not to exceed $145,000. Authorize the City Manager to negotiate and execute Amendment No. 1 to the Design Services Contract with HNTB, Inc for Architectural and Engineering services during construction in an amount not to exceed $425,000 for a total contract amount not to exceed $1,200,000. Submitted by: ~~uaU~ DirectOr of Public Works Approved for submission: '~ David W. Knapp City Manager 14 - 5 5 ATTACHMENT lA' BUDGET - STEEL BRIDGE.. MARY AVENUE BICYCLE FOOTBRIDGE -11/20/07 (rounded to $1.000's) Item Feasibility Study $ Phase I Construction Concrete Bridge Design Admin/Permits/FeesNE Steel Design (HNTB) Peer Review(LERA) Construction A&E (HNTB) Construct. Mgnit (Swinerton) Bridge Con~truction Construction Contingency Art Total Revenue Pre-Bid Budaet 9-18-21 Budaet Post Bid Qoenina 11-20-07 210,000 , 620,000 2,310,000 695,000 775,000 150,000 425,000 900,000 10,205,000 1,000,000 145,000 ' $ 17,435,000 (10.734.000) , Additional Funding Req. $ 6,701,000 Footnotes: $ 210,000 620,000 2,310,000 795,000* 775,000 150,000 425,000 900,000 7 470 000*'- , , 1,000,000 145.000 $ 14,800,000 (14.084.000)*** . $ 716,000 "'Adds $100,000 for source inspection for the steel bridge ."'Low Bid received 11-13-07 with $140,000 add alternates ***Includes $3,350,000 in additional VTA Funding Approved 11-01-07 ... "" , m ATTACHMENT IB' ADD ALTERNATES - MARY AVENUE BICYCLE FOOTBRIDGE - 11-20-07 Item Engineers Estimate Bid Amount Concrete Path $ 114,560 $ 90,000, Landscape 26,500 20,832 Custom Shelter & Trail Furniture 36,940 29,00.0 Total $ 178,000 $ 139,832 ... .jl. , -..j