Loading...
CC Exhibit 09-02-14 Item #13 Construction Update PowerPoint • xr �� p t. x c \ s a ki IX 1. A. McClellan Ranch Environmental Education Center & _ Blacksmith Shop Relocation Project CUPERTINO Project Schedule • Construction start - .June 2014 • Construction completion - March 2015 F Prior Month Activities 'Fe All Completed first concrete pour for the foundation for Education Center building and Blacksmiths Z Shop £ • Started utility work » if i View looking southeast September 1 , 2014 Construction Update Report 2 .{ V McClellan Ranch Environmental Education Center & Blacksmith- Shop Relocation Pro ect 4 Week Lool<-Ahead • Complete utility work into site • Start rough framing for EEC • Start work on concrete slab foundations for both buildings � y Prepare Blacksmith shop for relocation • �� G« . Utilities in building prior to slab 5 pour ��,� �� a 3S °'Raz Preparing to pour foundation for September 1 , 2014 Blacksmith shop 3 n , McClellan Ranch Environmental Education Center & Blacksmith Shop Relocation Pro ect CUPERTINO Parking area is reduce on site due to construction '''='� "°9k zone, additional parking is .v s; at McClellan Ranch West ffiffi •�'�``- ':��4 _-x ����l�r�f' Ili �:. •�:.,x✓,ss��.��.rs%�1%r{ �a/�.!//�ii�%�r//f��',yik""..�7� ��.�i �' �_ - tl � !k�.R>"`� •�^<v £uX�k �-:Nt� S. � ...: q Entrance to Construction Site r� r`h Milk Barn Restrooms are open for park users W Concrete poured for new building foundation September 1 , 2014 Construction Update Report 4 Apple C 2 CUPERTINO Project Schedule • Anticipated Completion of Utility Relocation and Wolfe Road Widening work in December 2014 • Majority of Utility Relocation work is anticipated to be s x complete by the beginning of u October. Aim Wolfe Road Widening work is anticipated to be complete in .p In December. September 1 , 2014 Construction Update Report 5 � Y Apple C 2 CUP ERTINO Sanitary Sewer, Storm Drainage, Water and joint - N Trench facilities being ` ` L'a �/ k�L 'i a'•! d��'' h;0 . .,�M!'vjO7aF SJt,/714 46 � Y installed concurrently along W ��y Wolfe Rd and Pruneridge Ave _t � E. i F3 . e s.' All landscaping work : 4 st tt g along Wolfe Road is s_ cheduled for .s completion in January 2015 s • sy h n.•a September 1 , 2014 Construction Update Report 6 -2013 Pavement Maintenance Project GUPIERTINQ Phase 11 Project Scope & Schedule • Scope: Rubber cape seal, chip seal and slurry • Work substantially complete: duly .2014 • Present to Council for Acceptance: October 2014 tr Streets Included (partial list) ' Homestead Road (Foothill to Hwy -85) %.SAY F G C 0?s R tT Ny6 ' Blaney (Rodrigues to Bollinger) a Regnart Road (upper portion) K' September 1 , 2014 Construction Update Report 7 2013 Pavement Maintenance Project Phase II - Blaney Ave Rubber Cape ".a, '�' ��..'< '"♦ i Y ti� : -3 t a ^i ..r. �x e ¢ & ,< s � s , < ..' y,N Ls/5. � u.,?yM<�`•wY--. ':.r ...: �` . �r•U"a'r'^4. t' � ,, �a� 3�'i .'' t''•a H y/-.IY",xsi'/ rg-: ::..... _"'.�°" ,.,_, ..,-,. : .<.,wn. ..,..,. .:: � >:.. -'.�,.�` ;(�A�ik� ,�/��''_y O /-y!,uj�/ss�f/W�j'»�" s. � r �Y ,:� ¢x,::E//iii;;" ;:H; �'♦sue.s r�t�,�y ~~ .. .' �,�.�:�;: < � �� �:.'>" ,�,,. �3 ��,,.. ,� >r-,<, �/�,j/i�r"�.r,� ,�iii f ? /H XI-. ,.,/,a,�S l/- srrlr ,rt-�. �,„// fi --:::r/ ,... «�«w�w+.,`.>♦"""4 ., �i _<.,-z, ?' � �`"..'� rLl- �%/� ,�: ,,,,r,4,,` a '>.,:` ,r,;.,n;/,yr, ;rs...�rri/�'%„ i/ ,ri. :>"'� a r/y s <.,- ::, u• - r. _,- °'� /i r/�%Y!/'/i//:��/y� <�� ;,, 6/.- �,,:/-,3:;,,»--� ,;,',r '�rr.Y-. / -,>,.e,r,: :r.,--�%r, ,. ,'•. r,/rte/:.../.�,,. F ..:: •..(,..,r.r,-%-. -r/,y. „bi ,r,r.-./.�i:r..., „ lii/'.. 'o :. -,sar F'r,,,a.<s>.»,.�n�- s...:. ",a-. .�<^'-a£.. :✓ �;/' ' ,.<?<•:<<:., -,:> ,r�I// ....-,r,.r/io/r3�/ s,r,�„y;.-s, .;,��„,:.a.»a,.,.-;««., �a,:� �,�;�':^:� -', _ i.�<,:r..s�ii/f _.<.,. .: .�iyi.:,�:>r-:.! s:.-:; ri/,-;'y/��°,/rs:„�-<,„r r '�:s;�„ ro:�ak.E,. oz<- �•' •>a-• ' �� :, /Ii t`. .- '.,:s:: ... "..>.. / /i-r,./.•Y/.,/'r/':��,�i -,�✓-r r/�,,.;s£r'�k�,y s.<_:s )�,�,�:� � ��rkt k`..- ,,. _.__. _.:..,... //., ../r/H ,/,rr-: r�,r,�,ry ��l r �.`, a<�,arr„ -_a ♦'i s t <..:::,: ,>..,” ,r.�;,�yi%r„., i- :y -S,�,t u:A„cs .,,.r..,,r: �.r ,._. F.,. :; » '�• z. �;r ..,.._._. '.....,. ., �,•r ✓Il�.r�i�:r,rr,: �, <Y<v�S,/, ��-.- r's;.�rF:�., N .�_"`., Z< 1 � ,f s>.��k':....,. w./:f�v,✓r.,�i.�r li./�i»/�, .r��-�//�'rr,r,!�%a, -r- � F:� , _.,.. a..:,::- '/,.,s /✓r. w.-r»,1.r�3syr,/,/..r.'„'�sl`,a,.,,sr/'�,r r.sxL_ ;ylF/r t,s� .. ..,• t :,. q,,,:'✓r��q ,�'.� r/ry .�� F raj I/� �! N � >.� `�s, �"r y� .' s k.. :i,-. ,i' /,.�.-,.�,Yi�u,//.4�/,(fot. I / -l i,G-..:.. �,x;,, � ::d����?yarr�r•� ,�F'°� ..-:1.. --,>„ <.,.: <,.. /,4:: / .�-,..:.,. ! /'- / :T .r,--�. /.s s.,s ., /.X-;s.,YS:�'a .,�”?. aF 5 3• > /:/li: -, ,.,q„/.r r.. r',»�Y// lr �sy: ,�k<w/�. � -�i�r.�r,.<1F� r rr.-, :,-..,. ..o♦; .. '"� 'l 1 - Y:H 7.+sc t. .....,: , -,,,- ✓�='-p,,,.-„r,GY,,,..r,!/T�?:�, -i.:. ,,.>Lr--»,),., /: .�;..- >� , ��,�^� > -. ..z:<t.- A a'', �r-7 :..%� ',3.'.:,ir i�'�' -,<,<-,,.wr., <<.:/ 1' /' !. :.a: s„ /, r.:- ,,,F�'i ,. :, s rj'.,4',/,.. ,:F...ra ,✓x 3 r r�'-d rk,/ 3 il'.... ::/ //f 1��� ,r//r �. /I :�,'."a � •k 'k� y �',}yj 3;.r /;,/� ./ �✓�i �</:';, /:: /,-;-s✓/,,,: 'r/r-f-:,�.:yl-:s�..�-r'iJrr�,>x!F,>,.„�,,.�z T.,>�T .. :'",.. .�fi' r;.7; ��.,, ,/,,rr-�/„ ,Y <r✓i ,l ,6�`6 � /,.,�.�,3,{:,/,s„ 1 k �S <s-�/�sl,,,;,1 . i�•ss!'s� _s�:r.,,.a�,�s%��'rI'/�/r/....:_ ,.r-�r :_:�: -a. y C''�- ,3/ .,� ,�,y� �,� .. :. -/ ..,. '> -_:,. :.<x..<..,, -.r•., /� s' r,. 3 � :rla'W � .' � - � Yc';�. s --t <. � G'.� ,� , �ur,-;r-.,s-,./„�;c.>,�s:;.::,�:w:,, .-.,.,v,:,' ,.:»...,:,,,<:.,m..,.,.�:- .>..::>..,-,�,.,,..a",s: -':r,:.wr.�,ax.,.,su:,.>..,..,;.H.,-.�,.�;.,c s:.,r.r:>-.r-ur.,.z; -'a,,;.n.1:u...�u�:,>,;::u.1 .. -• ... s`.�sb-;ors..,.a.., a..:,ru,„.,o.>..,>-,.,.,,/u,_-,..,..,,46.si.✓�/!>?�yii..y,,,,.,.,..:.-IS- , ,:,;r:r,>wri Y y.. ).. / ^��'a<sg� 'r2•�-`,s / t Y' J?;:�b�rz/��,.v ,>•,,”'r �"�,;s"t';?« .♦w„-..<«<.'��'' `�r'r,""�'° s"Wxv S. ,,r�'- I. .ro%N / ,.rr'✓r f,, T"�I ,?') fs �i .hvs,s ✓'s` ,s �- l'ri.,. „r.-,/,-, -r �. 'r,.::.HH,.o,.".,.....,,..,..,,,,<.,/, --:.-. i�,:/,r.//,,:i- .-�:r ,//r ,.,,: ,G„ ,.r,..,,r r.::,i/,�.,,,:.,. ii ur:;r�,�,,,...Is'�'Y',�,. ,'//n ✓i <t- r. ... ,:r- ,,.r.,,..:./<...:.,, ,.r..-,-_-r,.- .__- ✓/,..f,:Sr r/ls'. � ,./, r� y:, f ..S r / :Y,-_. -is,,�,a<i,/,.¢,..::,..,,,,,,,,,,,:,r././,i,I/r...,. ,i.<,.,-,-,-,..,.,..,,"„n, ,;/r�,r / , ,�/„l��„ �- i/.c. ,,,/ ,�, ✓�� �M/ r. ,:'�r 'rte .�';/r/ /rte .,/. /.�. -.i.._ �-it/,/.. �. / ./ ,/. ./ „/,�,r � i •.,.9///..a ......... .... a Y , ../9�,..,,,.li,... :, rr/✓ .,���/`�il'�../, 1, rsL l�r/�,- �i/i,r / ..,•:. r / sir” ss:.. r„> s^?, ••.•,�sl/r'•n<°/,,,a-/.Gr,,,,l„ ,/- /. ,/. o/ .rJ-. /��;r.G,:. „%2s -/,/ rr. .., s _✓,.3.i: :t:„rrs,,, <t..,r.<,_---s:.::->.� ty...::..:....:::...........r-- <� ,:s:r,. / �- :/,a:.-r.�//' .6�'.y///r,-i�./,.rr�//. rr./ 1i4��Ill '.lT ...... //r //r r MOO- ,. a-.. L J .4 k September 1 , 2014 C I P Construction Update Report 8 a� } R'O3 ' w h a 1 \ \ ni�z as $ c ; s GUPERTINO 2013 S Overlay Project Scope & Schedule • Scope: Rubberized asphalt overlay • Work substantially complete: July 2014 • Present to Council for Acceptance: October 2014 Street Included: Stevens Creek Boulevard from Hwy 85 to De Anza Boulevard September 1 , 2014 Construction Update Report 10 2013 S Overlay Project - Stevens Creek Blvd . Asphalt k Rubber EB Stevens Creek Blvd. @ Hwy 85 EB Stevens Creek Blvd @ Hwy 85 .................. . . ..... ... ............. NIN ... W , tp �r I � 8 Mill s _. qq R' k11. cv r , Z September. 1 , 2014 C I P Construction Update Report 1 1 CUPERTIPIO 2014 Pavement Maintenance Project - Phase Project Scope & Schedule • Scope: Asphalt overlay • Work substantially complete: November 2014 • Present to Council for Acceptance: December 2014 Streets Included (partial list): Elmsford Drive Stafford Drive Belknap Drive Belknap Drive Yorkshire Drive Elmsford Drive Folkstone Drive Bubb Road Yorkshire Drive Weymouth Drive Rainbow Drive Belknap Drive Yorkshire Drive Rainbow Drive North bend Aster Lane Waterford Drive Barnhart Avenue Barnhart Avenue Moretti Drive Sterling Blvd Torre Avenue Stevens Creek Blvd Pacifica Drive Pacifica Drive Farallone Drive De Anza Blvd Willowgrove Lane Ferngrove Drive Hyde Drive Stevens Canyon Road Park Entrance South New Pavement Bollinger Road Blaney De Anza Blvd Antoinette Drive Clay St Clifden Way Christo Rey All September 1 , 2014 Construction Update Report 12 � 2014 Pavement Maintenance Project - Phase II CUPERTINO Project Scope & Schedule • Scope: Rubberized asphalt overlay • Work substantially complete: November 2014 • Present to Council for Acceptance: December 2014 Streets Included: Stevens Creek Boulevard from De Anza Boulevard to Wolfe Avenue De Anza Boulevard from Stevens Creek Boulevard to Homestead Road September 1 , 2014 Construction Update Report 13 CUPERTINO 2014 Pavement Maintenance Project Phase III Project Scope & Schedule • Scope: Rubber cape seal, chip seal and slurry • Work substantially complete: November 2014 • Present to Council for Acceptance: December 2014 Streets Included: Stevens Creek Boulevard from De Anza Boulevard to Wolfe Avenue De Anza Boulevard from Stevens Creek Boulevard to Homestead Road September 1 , 2014 Construction Update Report 14 o .0 2014 Reconstruction of Curbs /Gutters & Sidewalks CUPERTINO Project Schedule Work substantially complete: June 2015 Present to Council for Acceptance: August 2015 Streets Included: Throughout the City to resolve drainage issues, trip/fall hazards and to prepare streets for future asphalt improvements. September 1 , 2014 Construction Update Report 15