CC 01-20-2015 Exhibit, Item No. 18, McClellan Ranch Environmantal Education Center Construction UpdateCity of Cupertino
Construction Update Report
January 20, 2015 Construction Update Report
McClellan Ranch Environmental Education Center
& Blacksmith Shop Relocation Project
Project Schedule
• Construction start - June 2014
• Construction completion - March
2015
Prior Month Activities
• Continued to work on utilities
• Worked on EEC and covered area
framing
• Completed structural upgrade to
Blacksmith Shop walls
• Heavy rainfall and storms
impacted flow of work
January 20, 2015 Construction Update Report
View looking southeast
1/20/2015
-*lS
1
McClellan Ranch Environmental Education Center
'•• & Blacksmith Shop Relocation Project
4 Week Look -Ahead
• Installation of building utilities
• Install EEC siding and roofing
• Install BSS siding and roofing
Framing of outdoor covered area
January 20, 2015
Inside large classroom
McClellan Ranch Environmental Education Center
& Blacksmith Shop Relocation Project
During construction,
additional parking at
McClellan Ranch West
Weatherizing for storm
January 20, 2015 Construction Update Report
Milk Barn Restrooms are open
for park users
1/20/2015
2
1
Public Building Solar Installation -
<•.�• �• Service Center
Project Schedule
• Construction start - Dec 2014
• Construction completion - Feb 2015
Prior Month Activities
• Installed solar panels
• Provided pathway for power and
data from panels to Electrical Room
4 Week Look -Ahead
• Wiring, hook up to PG&E grid
• Substantial completion
• System activation - Mar/Apr 2015
Carport style PV system - panels installed
January 20, 2015 Construction Update Report 5
211 Sports Center Tennis Court
cull , Retaining Wall Repair Project
Project Schedule
• Construction start - Oct 201
• Construction completion -
Jan 2015
Prior Month Activities
• Contractor formed and
applied shotcrete
4 Week Look -Ahead
• Paint wall -
Installing shotcrete facing
January 20, 2015 Construction Update Report 6
1/20/2015
3
Quinlan Community Center
�'• Fiber Installation Project
Project Schedule
• Construction start - Oct. 20
• Construction completion -
December 2014
Prior Month Activities
• Fiber Optic cable splicing,
testing, and acceptance.
• Trench Repair
• Substantial Completion
Fiber Termination
January 20, 2015 Construction Update Report
Quinlan Community Center
• •• Interior Upgrade
Project Schedule
• On-site work start - Feb. 9, 2015
• Construction completion - May
2015
Prior Month Activities
• Issued Notice to Proceed
• Submittal review
• Material procurement
• Pre -construction conference
January 20, 2015 Construction Update Report 8
1/20/2015
GI
Apple Campus .2
Project Schedule
• Phase 1 of the Public
Improvements - Utility
Relocation and Wolfe Road
Widening work -
anticipated completion
in August 2015
Milestones
• All utility relocation work
necessary to vacate Pruneridge
Avenue is complete.
• Installation of new recycled water
line that will connect to future
reclaimed water extension to be
complete in March 2015
January 20, 2015 Construction Update Report 9
Apple Campus 2
Wolfe Road widening work is
being laid out for construction.
Fully striped traffic lanes and
construction of new median
island is scheduled for
completion in July of 2015.
All landscaping work along
Wolfe Road is scheduled for
completion in August 2015
January 20, 2015 Construction Update Report 10
1/20/2015
5
2014 Pavement Maintenance Project - Phase I
Project Scope & Schedule
• Scope: Asphalt overlay
-Work substantially complete: Oct 2014
• Project acceptance: Feb 2015
January 20, 2015 Construction Update Report 1
1/20/2015
no
�•• 2014 Pavement Maintenance :Project - .Phase .l.l
Project Scope & Schedule
• Scope: Rubberized asphalt overlay
• Work substantially complete: Nov 2014 = "
• Project acceptance: Feb 2015
De Anza @ Homestead
Intersection
Streets Included:
• Stevens Creek from De Anza to Wolfe
• De Anza from Stevens Creek to Homestead
January 20, 2015 Construction Update Report
�•• 2014 Pavement Maintenance Project - Phase III
Project Scope & Schedule
• Scope: Rubber cape seal,
chip seal & slurry
• Work substantially complete: Oct 2014
• Project acceptance: Feb 2015 KOM
Streets Included:
•.Stevens Creek from Hwy 85 to Foothill
• Bollinger from Blaney to De Anza
• Blaney for Rodriguez to Stevens Creek
• Miller from Bollinger to Calle De Barcelone
January 20, 2015 Construction Update Report
13
Stevens Creek @
Pasadena
14
1/20/2015
7
2014 Reconstruction of Curbs/Gutters & Sidewalks
Project Schedule
Work substantially complete: Jun 2015
Streets Included:
Throughout the City to resolve
drainage issues, trip/fall hazards
and to prepare streets for future
asphalt improvements.