CC Exhibit 03-17-15 Item #14 Construction Update 3/17/2015
• City of Cupertino
Construction Update Report
` .
March 17,2015 Construction Update Report 1
McClellan Ranch Environmental Education Center
& Blacksmith Shop Relocation Project
Project Schedule
• Construction start-June 2014
• Construction substantial completion -Apr 2015
• Occupancy preparation - May-July 2015
Prior Month Activities
r
• Continued utility work
• Installed siding and painted
• Install interior finishes
• Complete Milk Barn restroom work
View looking southeast
March 17,2015 Construction Update Report 2
1
3/17/2015
` McClellan Ranch Environmental Education Center
& Blacksmith Shop Relocation Project
4 Week Look-Ahead
• Complete installation of BSS siding
• Complete site work
Inside small classroom,
view looking south thru
new windows
Framing of outdoor covered area
March 17,2015 3
FE] Public Building Solar Installation -
<••• �• Service Center
Project Schedule
• Construction start- Dec 2014
• Construction completion - Feb 2015
Prior Month Activities i% s aj
• Interconnect to the PG&E grid and
system activated - Feb 28 %
• System commissioning
• Staff training
Of
4 Week Look-Ahead
• "Flip the Switch" event on Carport style PV system-panels installed
March 18 4:00 p.m.
March 17,2015 Construction Update Report 4"
2
3/17/2015
Quinlan Community Center
<�..ma• Interior Upgrade
Project Schedule j
• . On-site work start- Feb. 9, 2015
• .Construction completion - May 2015
Prior Month Activities
• Phase 1 &2 substantially completed �� s
(Cupertino Room, main hallways and
main lobby)
• Phase 3 underway(North hallway and
lobby)
4 Week Look-Ahead * u
• Complete Phase 3 ,a
March 17,2015 Construction Update Report 5
Apple Campus 2
Proiect Schedule
• Phase 1 of the Public
Improvements - Utility
Relocation and Wolfe Road
Widening work-
anticipated completion
in August 2015
Milestones
• Installation of new recycled water
line that will connect to future
reclaimed water extension to
begin in March 2015 y
• Wolfe Road widening work
underway. Concrete paving work
being installed. F1 Fa
March 17,2015 Construction Update Report 6
r
3
3/17/2015
0 Apple Campus 2
ca.vmxa -
�.r
Wolfe Road Median work
anticipated to begin in April.
Fully striped traffic lanes•and
construction of new median-
island is scheduled for
completion in July of 2015.
All landscaping work along
Wolfe Road is scheduled for
completion in August 2015
March 17,2015 Construction Update Report 7
2014 Reconstruction of Curbs/Gutters & Sidewalks
Proiect Schedule
Work substantially complete: Jun 2015
n �a ry
�i ✓ i iii �
Streets Included: � �l�"r�1 ✓�� ���i�-�� � �. '
Throughout the City to resolve
drainage issues, trip/fall hazards � .
and to prepare streets for future
asphalt improvements.
March 17,2015 Construction Update Report 8