14110006-Spec InspAdlikk FILE TESTING ENGINEERS, INC. 17 V V 1� 2811 Teagarden St. 510-835-3142 aX San Leandro, CA 94577 800-660-3142 San Leandro • San Jose • Martinez INSPECTION REPORT Week Ending: 1/16/15 PROJECT # 60422 PROJECT: Apple Bubb 12 Tenant Improvement 10460 Bubb Road Cupertino, CA DATE HOURS Permit # 14110006 1/15/15 INSPECTOR C. Wilson Reported to Devcon Construction at the jobsite as requested. TYPE OF INSPECTION: Epoxied Anchors PLACE OF INSPECTION: Jobsite Witnessed the drilling of holes of proper diameter and depth and inspected predrilled holes for proper diameter and depth. Observed the cleaning of holes and the injection of Hilti HY 200 epoxy (exp. 9/15). Witnessed the proper insertion of three hundred seventy-two (372) 1/8" diameter Allthread anchors, 8" in length, embedded 4-1/2" for seismic retrofit at roof between lines A and D at 1 (126), between lines A and D at 10 (144) and between lines 1 and 10 at A (102). The preceding work was, to the best of my knowledge, in compliance with approved plans and specifications, including revisions by engineer and Drawing SR3, Details 1 and 5, dated 11/3/14. Reviewed by: David Chippero Special Inspection Division Manager 1cc: Apple Computer Inc. / J. Dunbar Devcon Construction / A. Michelmore City of Cupertino / Bldg. Inspection Dept. This report can be reproduced only in its entirety unless written permission from TEI is obtained. Page 1 of 1 FILE Ask TESTING ENGINEERS, INC. 2811 Teagarden St. 510-835-3142 510-834-3777 fax San Leandro, CA 94577 800-660-3142 San Leandro • San Jose • Martinez INSPECTION REPORT Week Ending: 1/2/15 PROJECT # 60422 PROJECT: Apple Bubb 12 Tenant Improvement 10460 Bubb Road Cupertino, CA DATE HOURS Permit # 14110006 12/29/14 INSPECTOR R. Peterson Reported to Eric of Concord Iron Works at the shop as requested. TYPE OF INSPECTION: Visual Welding PLACE OF INSPECTION: Concord Iron Works (shop) Checked welder qualification papers (Norman Cruz, ID # 4523, Armando Cardona, ID # 5523). Checked WPSs and verified welding parameters. Verified proper electrode storage. Verified proper preheat. Visually inspected joint preparation and fit - up. Performed continuous visual inspection of the in -progress welding performed by two qualified welders using the FCAW process with E71T-11 wire electrode. Weldments consist of 1/4" fillet welds joining /4" plate to 5/8' plate for assemblies shop marked A7 (112) and B7 (12); HSS 4" x 4" x 5/16" to 3/4' plate for cap and base plates for columns on units Al, A2 and A3; and 1/4" partial joint penetration groove welds joining HSS 4" x 4" x 5/16" to 3/4" plate for cap and base plates for columns on units Al, A2 and A3. The preceding work was, to the best of my knowledge, in compliance with engineer approved plans and specifications, including revisions by engineer and shop drawings 7,1, 2 and 3, dated 12/16/14. Reviewed by: David Chippero Special Inspection Division Manager lcc: Apple Computer Inc. / J. Dunbar Devcon Construction / A. Michelmore City of Cupertino / Bldg. Inspection Dept. This report can be reproduced only in its entirety unless written permission from TEI is obtained. Page 1 of 1 TESTING ENGINEERS, INC. RECEIVED MAR 0 2 095 2811 Teagarden St. 510-835-3142 510-834-3777 fax San Leandro, CA 94577 800-660-3142 BY San Leandro • SanJose • Martinez INSPECTION REPORT Week Ending. 2/13/15 PROJECT # 60422 PROJECT: Apple Bubb 12 Tenant Improvement 10460 Bubb Road Cupertino, CA Permit # 14110006 DATE 2/13/15 HOURS 4 INSPECTOR J. Souza TYPE OF INSPECTION: Visual Welding PLACE OF INSPECTION: Jobsite Reported to Alfredo of Devcon Construction at the jobsite as requested. Performed visual inspection of previously completed welding. Weldments consist of single pass fillet welds joining 5" x 5" x 1/4' tube steel brace to 5/8" x T' gusset plate; and 5/8' x T' gusset plate to 3/4' flat plate between lines A and D at 2 on roofline. The preceding work was, to the best of my knowledge, in compliance with approved plans and specifications, including revisions by engineer. Reviewed by: avid Chippero Special Inspection Division Manager 1cc: Apple Computer Inc. / J. Dunbar Devcon Construction / A. Michelmore City of Cupertino / Bldg. Inspection Dept. This report can be reproduced only in its entirety unless written permission from TEI is obtained. Page 1 of 1 VTESTING ENGINEERS, INC. 2811 Teagarden St. 510-835-3142 510-834-3777 fax San Leandro, CA 94577 800-660-3142 San Leandro • San Jose • Martinez INSPECTION REPORT 6 /5 PROJECT # 60422 PROJECT: Apple Bubb 12 Tenant Improvement 10460 Bubb Road Cupertino, CA Permit # 14110006 DATE 2/3/15 HOURS 8 +1 of INSPECTOR A. Gundersen Reported to Eric of Concord Iron at the shop as requested. TYPE OF INSPECTION: FEB 18 zo15 Visual Welding RY PLACE OF INSPECTION: Concord Iron (shop) Checked welder qualification papers (Armando Cordona, ID # 5623, Tidenci Vasquez, ID # 6709, Norman Cruz, ID # 4523). Checked WPSs and verified welding parameters. Verified proper electrode storage. Verified proper preheat. Visually inspected joint preparation and fit -up. Performed continuous visual inspection of the in -progress welding performed by three qualified welders using the FCAW process with E71T-8 wire electrode. Weldments consist of 1/4" single pass fillet welds joining 3/4" base plate to C10 x 15.3 x 5'-4" assemblies shop marked All, Bll, Al2, B12, A13, B13, A14, B14, A15, B15, A16 and B16; and partial joint penetration groove welds joining 3/4" x 8" base plate to 5/8' x 7" bracket for HSS 5" x 5" x 1/4" x 18'-00" braces shop marked A5, A6, A8, A9, A10 and B10. The preceding work was, to the best of my knowledge, in compliance with engineer approved plans and specifications, including revisions by engineer and shop drawings 5 through 16, dated 1/29/15. Reviewed by: �.�► David ppero Special Inspection Division Manager lcc: Apple Computer Inc. / J. Dunbar Devcon Construction / A. Michelmore City of Cupertino / Bldg. Inspection Dept. This report can be reproduced only in its entirety unless written permission from TEI is obtained. Page 1 of 1