Exhibit CC 11-03-15 Item #16 Construction UpdateCity of Cupertino
Construction Update Report
1 November 1, 2015 Construction Update Report
CC 11-3-15 Item #16
School-Area Green Bike Lane Enhancements
Bike Plan Progress Update
•Green bike lane enhancements
on Stelling (Hwy 85 to Stevens
Creek Blvd), Blaney (Calle de
Barcelona to Stevens Creek
Blvd) and Stelling south of
Homestead to be completed
soon.
2 November 1, 2015 Construction Update Report
•Green bike lanes on
Homestead, Finch,
Bollinger, McClellan Rd
and Bubb Rd are
complete.
Cupertino Sport Center-West Court Renovations
and Improvements
Prior Month Activities
•Installed tennis court slip sheet
resurfacing & color coat
•Paved sports court & color coat
•Installed fencing, ball wall &
wiring for lights, and completed
property-line façade
4 Week Look-Ahead
•Install lights
November 1, 2015 3 Construction Update Report
Sports court paving & color coat
Project Schedule
• Construction start – Aug 2015
• Construction completion – Nov 2015
Apple Campus 2
Project Schedule
•Phase 1 – Utility Relocations and Wolfe Widening - Completed
•Apple Mitigation - Tantau & Vallco: anticipated completion – Mid Nov.
Milestones
•Minor pavement work (sidewalk,
curb and gutter replacement)
around the campus underway.
•Phase 3 – Tantau Frontage Work
to begin in November. Phase 3 is
anticipated to be complete by
December 2016.
November 1, 2015 Construction Update Report 4
Apple Campus 2
November 1, 2015 Construction Update Report 5
The mitigation work on Tantau Ave
and Vallco Pkwy is scheduled to be
complete in November.
Minor pavement work (including
the sidewalk shown on right) will
be complete by end of November.
The two new traffic signals on
Vallco Parkway are operational.
6 6
Bubb, Elm & McClellan Drive
Storm Drain/Sanitary Sewer Improvements
November 1, 2015
Project Schedule
Construction Start: Jun 2015
Complete project work: Nov 2015 (early)
Contractor is finalizing work this week.
Description
Increase of storm drain capacity in Bubb to alleviate periodic
flooding of Elm Court
Construction Update Report
7 7
2014 Sidewalk Accessibility Project & 2015
Reconstruction of Curbs Gutters and Sidewalks
November 1, 2015
2014 Sidewalk Accessibility Project Schedule
Construction Start: Apr 2015
Construction Complete: Sep 2015
2015 Reconstruction of Curbs Gutters and Sidewalks
Construction Start: June 2015
Construction Complete: Dec 2015
Streets Included:
City-wide project to resolve drainage issues, trip/fall hazards
and to prepare streets for future asphalt improvements.
Construction Update Report
8 8
2015 Pavement Maintenance – Phase 1
November 1, 2015
Project Schedule
Construction Start: Jun 2015
Construction Complete: Dec 2015
Streets Included:
Asphalt overlay of various streets throughout the City with
emphasis on residential streets.
Construction Update Report
De Anza Blvd at Bollinger Road
9 9
2015 Pavement Maintenance – Phase 2
November 1, 2015
Project Schedule
Construction Start: Sept 2015
Construction Complete: Nov 2015
Streets Included:
Rubber cape seal and slurry of various streets throughout the
City.
Construction Update Report
Lazaneo Drive
10 10
COMPLETED PROJECTS
November 1, 2015
PROJECT TITLE:
1.McClellan Ranch Pedestrian, Parking & Landscape
Improvements
Construction Update Report