Exhibit CC 02-02-2016 Item No. 16 Construction Projects UpdateCity of Cupertino
Construction Update Report
1February 1, 2016 Construction Update Report
McClellen Ranch West-Simm’s House Removal
•Demolition is complete and the debris hauled off of the site
•No trees were removed
•Hydroseeding is complete
February 1, 2016 Construction Update Report 2
Before Demolition
After Demolition and
Hydroseeding
Construction Update Report 3
Cupertino Senior CenterMary Avenue Landscaping
Prior Month Activities
•Contract close-out activities
4 Week Look-Ahead
•90 day Maintenance Period ends March 15, 2016
3Construction Update Report
Senior Center landscaping
Project Schedule
•Notice to Proceed–Nov 2015
•Construction completion –Dec. 2015
February 1, 2016
Apple Campus 2
Project Schedule
•Phase 1 –Utility Relocations and Wolfe Widening -Completed
Milestones
•Phase 3 –Tantau Frontage Work
has begun. Phase 3
anticipated completion
December
•Mitigation work at Calvert and
Lawrence has begun; completion
by December
•Mitigation work at Wolfe/280
off-ramps has begun; completion
by December
February 1, 2016 Construction Update Report 4
Apple Campus 2
February 1, 2016 Construction Update Report 5
Mitigation work on Tantau and Vallco
Pkwy is nearly complete
Phase 3 –Tantau work
has begun, including construction of
new detached sidewalks and median.
66
2015 Reconstruction of Curbs Gutters and Sidewalks & 2015 Concrete Improvements Projects
February 1, 2016
2015 Reconstruction of Curbs Gutters and SidewalksConstruction Complete: Jan. 2016
2015 Concrete Improvements Construction Start:Jan. 2016Construction Complete June 2016
Streets Included:City-wide project to resolve drainage issues, trip/fall hazards and to prepare streets for future asphalt improvements.
Construction Update Report
77
2015 Pavement Maintenance –Phase 1
February 1, 2016
Project ScheduleAnticipated Completion March 2016
Streets Included:Asphalt overlay of various streets throughout the City with emphasis on residential streets.
Construction Update Report
De Anza Blvd at Bollinger Road
88
2016 Pavement Maintenance –Phase 1
February 1, 2016
Project ScheduleConstruction Start:April 2016Construction Complete:Oct. 2016
Streets Included:
Asphalt overlay of various streets throughout the City with emphasis
on residential streets.
Construction Update Report
Scenic Circle