Exhibit CC 02-02-2016 Item No. 16 Construction Projects UpdateCity of Cupertino Construction Update Report 1February 1, 2016 Construction Update Report McClellen Ranch West-Simm’s House Removal •Demolition is complete and the debris hauled off of the site •No trees were removed •Hydroseeding is complete February 1, 2016 Construction Update Report 2 Before Demolition After Demolition and Hydroseeding Construction Update Report 3 Cupertino Senior CenterMary Avenue Landscaping Prior Month Activities •Contract close-out activities 4 Week Look-Ahead •90 day Maintenance Period ends March 15, 2016 3Construction Update Report Senior Center landscaping Project Schedule •Notice to Proceed–Nov 2015 •Construction completion –Dec. 2015 February 1, 2016 Apple Campus 2 Project Schedule •Phase 1 –Utility Relocations and Wolfe Widening -Completed Milestones •Phase 3 –Tantau Frontage Work has begun. Phase 3 anticipated completion December •Mitigation work at Calvert and Lawrence has begun; completion by December •Mitigation work at Wolfe/280 off-ramps has begun; completion by December February 1, 2016 Construction Update Report 4 Apple Campus 2 February 1, 2016 Construction Update Report 5 Mitigation work on Tantau and Vallco Pkwy is nearly complete Phase 3 –Tantau work has begun, including construction of new detached sidewalks and median. 66 2015 Reconstruction of Curbs Gutters and Sidewalks & 2015 Concrete Improvements Projects February 1, 2016 2015 Reconstruction of Curbs Gutters and SidewalksConstruction Complete: Jan. 2016 2015 Concrete Improvements Construction Start:Jan. 2016Construction Complete June 2016 Streets Included:City-wide project to resolve drainage issues, trip/fall hazards and to prepare streets for future asphalt improvements. Construction Update Report 77 2015 Pavement Maintenance –Phase 1 February 1, 2016 Project ScheduleAnticipated Completion March 2016 Streets Included:Asphalt overlay of various streets throughout the City with emphasis on residential streets. Construction Update Report De Anza Blvd at Bollinger Road 88 2016 Pavement Maintenance –Phase 1 February 1, 2016 Project ScheduleConstruction Start:April 2016Construction Complete:Oct. 2016 Streets Included: Asphalt overlay of various streets throughout the City with emphasis on residential streets. Construction Update Report Scenic Circle