Exhibit CC 09-06-2016 Item No. 27 Construction Update ReportCity of Cupertino
Construction Update Report
1September 1, 2016 Construction Update Report
Construction Update Report 2
Cupertino Sports Center
East Courts Resurfacing
Prior Month Activities
•Re-Mobilization for Phase 2
4 Week Look-Ahead
•Begin Resurfacing of
Courts 6-12
2Construction Update ReportSeptember 1, 2016
Project Schedule
•Phase 2 -August 15, 2016 to
November 2016
•Construction Completion –
November 2016
Construction Update Report 3
Pasadena Avenue Public Improvements
Construction Update ReportSeptember 1, 2016
Project Schedule
•Construction Start –
August 2016
•Construction completion –
November 2016
Prior Month Activities
•Notice to Proceed Issued
•Contractor Submittals and
Mobilization
•Resident Notification
•Work Started
4 Week Look-Ahead
•Project Demolition
•Improvement Construction
Construction Update Report 4
Sidewalk Construction-McClellan Road
(@ the corner of McClellan & Byrne)
Construction Update ReportSeptember 1, 2016
Project Schedule
•Construction Start –
July 2016
•Construction
completion –August
2016
Prior Month Activities
•Project Work
Completed
4 Week Look-Ahead
•Project Close-Out
Apple Campus 2
September 1, 2016 Construction Update Report 5
Mitigation work at Calvert and
Lawrence Expressway is
anticipated to be complete
December 2016.
Mitigation at Wolfe/Hwy 280
interchange is anticipated to be
complete December 2016.
Phase 3 –Tantau Frontage Work
has begun. Includes construction
of new sidewalks and new
median.
Mitigation work on Tantau and
Vallco Pkwy is complete.
66
2015 Concrete Improvements Projects
September 1, 2016
Project Schedule
•Construction Start -
January 2016
•Construction Completion -
August 2016
Streets Included
City-wide project to resolve drainage issues, uneven
sidewalks, and to prepare streets for future asphalt
improvements.
Construction Update Report
77
2016/17 Concrete Improvements Projects
September 1, 2016
Project Schedule
•Construction Start -
September 2016
•Construction Completion –
June 2017
Streets Included
City-wide project to resolve drainage issues, uneven
sidewalks, and to prepare streets for future asphalt
improvements.
Construction Update Report
88
2016 Pavement Maintenance –Phase 1
September 1, 2016
Project Schedule
Construction Start -June 2016
Construction Completion -
October 2016
Streets Included:
Asphalt overlay of various
streets throughout City with
emphasis on residential streets.
Construction Update Report
99
COMPLETED PROJECTS
September 1, 2016
PROJECT TITLE:
•Sidewalk Construction-McClellan & Byrne
•2015 Concrete Improvements Project
Construction Update Report