89-118 Steiny & Co. Traffic Signal Modification at De Anza @ Mariani and Lazaneo, Project #5004 and 5004ACitAt of Cupertino
10300 Torre Avenue
Cupertino, California 95014
Telephone: (408) 252-4505
DEPARTMENT OF THE CITY CLERK
May 5, 1989
Steiny and Company, Inc,
P. 0. Box 8100
Baldwin Park, CA 91706-0993
P.O. Box 580
Cupertino, California 95015
TRAFFIC SIGNAL MODIFICATION, DE ANZA AT MAR_IANI AND AT LAZANBO DRIVE _ PRQTECT 5004 AND 5004A
We are enclosing to you one (1) copy of the Contract for Public Works
between the City of Cupertino and Steiny and Ccapan
fully executed by City officials. Y, Inc., which has been
Award of your contract was approved at the March 20, 1989. regular City Council meeting of
We are also enclosing your bid bond.
Sincerely,
i
DC/so
encl.
cc: Department of Public Works
C1t14 of cu ertilio
10300 Torre Avenue
Cupertino, California 95014
Telephone: (408) 252-4505
DEPARTMENT OF THE CITY CLERK
May 5, 1989
Steiny and Cmnpany, Inc.
P. O. Box 8100
Baldwin Park, CA 91706-0993
P.O. Box 580
Cupertino, California 95015
TRAFFIC SIGNAL MODIFICATION, DE ANZA AT MARIAN, AND AT UZU4EO DRIVE -
PROTECT 5004 AND 5004A
We are enclosing to you one (1) copy of the Contract for Public Works
between the City of Cupertino and Steiny and Company, Inc., which has been
fly executed by City Officials.
Award
March Of Y r contract was approved at the regular City Council meeting of
20,
We are also enclosing your bid bond.
Sincerely,
DO�ROIM CORNEUTUT�—S , v�
CITY CLERK
CITY OF CUPERTINO
DC/so
encl.
cc: Department of Public Works
CONTRACT FOR PUBLIC WORKS
This CONTRACT made one / j 1989 by the CITY OF CUPERTINO,
a municipal corporation of t e State of California, hereinafter called CITY,
and STEINY and COMPANY, INC., hereinafter called CONTRACTOR.
IT IS HEREBY AGREED by CITY and CONTRACTOR as follows:
1. THE CONTRACT DOCUMENTS. The complete contract consists of the following
contract documents:
a. Bid Documents (Notice to Contractors, Proposal, Time for Completion,
Estimated Quantities, Bidder Qualification Form, Sub -Contractors Form and
Signature Form), referred to as Exhibit A.
b. Standard Specifications, General Provisions and Special Provisions.
c. Plans and Specifications for TRAFFIC SIGNAL MODIFICATION on DEANZA
BOULEVARD at MARIANI AVENUE and at LAZANEO DRIVE, PROJECT No. 5004 and
5004(A).
d. Faithful Performance Bond and Materials Bond.
e. Insurance Certificates.
f. This Contract for Public Works.
Any and all obligations of CITY and CONTRACTOR are fully set forth and
described herein.
All of the above documents are intended to cooperate so that any work
called for in one and not mentioned in the other, or vice versa, is to be
executed the same as if mentioned in all of said documents. The documents
comprising the complete contract are sometimes hereinafter referred to as the
Contract Documents. In case of conflict between the Plans and the
Specifications on the one hand, and this Contract on the other, the Plans and
Specifications shall prevail.
2. THE WORK. CONTRACTOR agrees to furnish all of the tools, equipment,
apparatus, facilities, labor, transportation and materials necessary to
perform and complete in a good and working order, the work of TRAFFIC SIGNAL
MODIFICATION on DEANZA BOULEVARD at MARIANI AVENUE and at LAZANEO DRIVE,
PROJECT No. 5004 and 5004(A), as called for, and in the manner designated in,
and in strict conformity with, the Plans and Specifications prepared by the
Engineer and adopted by CITY, which Plans and Specifications are entitled,
respectively, TRAFFIC SIGNAL MODIFICATION on DEANZA BOULEVARD at MARIANI
AVENUE and at LAZANEO DRIVE, PROJECT No. 5004 and 5004(A), and which Plans and
Specifications are identified by the signatures of the parties to this
Contract. It is understood and agreed that said tools, equipment, apparatus,
facilities, labor, transportation and materials shall be furnished, and that
said work shall be performed and completed as required in said Plans and
Specifications under the sole direction of CONTRACTOR, but subject to the
inspection and approval of CITY, or its representative. CITY hereby designates
as its representative for the purpose of this Contract the Engineer, Mr. Bert
J. Viskovich.
Contract Page 1 of 6
CONTRACT FOR PUBLIC WORKS(Continued)
PROJECT No. 5004 and 5004(A)
3. CONTRACT PRICE. CITY agrees to pay, and CONTRACTOR agrees to accept, in
full payment for the work above agreed to be done, the sum of Sixty Eight
Thousand Five Hundred and Seventy Dollars and Eighty Cents ($68,570.80),
subject to additions and/or deductions as provided in the Contract Documents,
per Exhibit A attached hereto.
4. DISPUTES PERTAINING TO PAYMENT FOR WORK. Should any dispute arise
respecting the true value of the work done, or any work omitted, or of any
extra work which CONTRACTOR may be required to do, or respecting the size of
any payment to CONTRACTOR during the performance of this Contract, said
dispute shall be determined either by reference to the Unit Prices bid, if
applicable, or in accordance with agreement of prices, if applicable, of in
accordance with the agreement of the parties, or in accordance with the rules
of the American Arbitration Association if the parties are unable to agree.
5. PERMITS, COMPLIANCE WITH LAW. CONTRACTOR shall obtain and bear all
expense for all necessary permits, licenses and easements for the construction
of the project, give all necessary notices, pay all fees required by law, and
comply with the laws, ordinances and regulations relating to the work and to
the preservation of the public health and safety.
6. INSPECTION BY THE CITY. CONTRACTOR shall at all times maintain proper
facilities and provide safe access for inspection by CITY to all parts of the
work, and to the shops wherein the work is in preparation. Where the
Specifications require work to be specially tested or approved, it shall not
be tested or covered up without timely notice to CITY of its readiness for
inspection and without the approval thereof or consent thereto by CITY. Should
any such work be covered up without such notice, approval, or consent, it
must, if required by CITY, be uncovered for examination at CONTRACTOR'S
expense.
7. EXTRA OR ADDITIONAL WORK AND CHANGES. Should CITY at any time during the
progress of the work require any alterations, deviations, additions or
omissions from the Plans or Specifications or the Contract Documents, CITY
shall have the right to do so, and the same shall in no way affect or make
void the Contract, but the cost or value thereof will be added to, or deducted
from, the amount of the Contract price, as the case may be, by a fair and
reasonable valuation, which shall be determined either by reference to the
Unit Prices bid, if applicable, the Standrad Specifications, or in accordance
with the agreement of the parties, or in accordance with the rules of the
American Arbitration Association if the parties are unable to agree. No extra
work shall be performed or change be made except by a written order from CITY,
duly authorized by resolution of the City Council, and by all agencies whose
approval is required by law, stating that the extra work or change is
authorized, and no claim for an addition to the Contract sum shall be valid
unless so ordered.
8. CHANGES TO MEET ENVIRONMEMTAL REQUIREMENTS. CITY shall have the right to
make changes in this Contract during the course of construction to bring the
completed improvements into compliance with environmental requirements or
standards established by State and Federal statutes and regulations after the
Contract has been awarded or entered into. CONTRACTOR shall be paid for such
changes either by reference to the Unit Prices bid, if applicable, or in
accordance with the agreement of the parties, or in accordance with the rules
of the American Arbitration Association if the parties are unable to agree.
Contract Page 2 of 6
CONTRACT FOR PUBLIC WORKS(Continued)
PROJECT No. 5004 and 5004(A)
9. TERMINATION, AMENDMENTS OR MODIFICATIONS. This Contract may be
terminated, amended or modified, with the mutual consent of the parties. The
compensation payable, if any, for such termination, amendment or modification,
shall be determined either by reference to the Unit Price bid, if applicable,
the Standard Specifications, or in accordance with the agreement of the
partie, or in accordance with the rules of the American Arbitration
Association if the parties are unable to agree.
10. TIME FOR COMPLETION. All work under this Contract shall be completed in
accordance with the Time for Completion section in the proposal and the
Specifications of this project. If CONTRACTOR shall be delayed in the work by
the acts or neglect of CITY, or its employees, or those under it by contract
or otherwise, or by changes ordered in the work, or by strikes, lockouts by
others, fire, unusual delay in transportation, unavoidable casualties or any
causes beyond CONTRACTOR'S control, or by delay authorized by CITY, or by any
cause which CITY shall determine justifies the delay, then the time of
completion shall be extended accordingly. This paragraph does not exclude the
recovery of damages for delay by either party under other provisions in the
Contract Documents.
11. INSPECTION AND TESTING OF MATERIALS. CONTRACTOR shall notify CITY a
sufficient time in advance of the manufacture, production or testing of
materials to be supplied under this Contract, in order that CITY may arrange
for mill, factory or laboratory inspection and testing of same.
12. TERMINATION FOR BREACH OR INSOLVENCY. If CONTRACTOR should be adjudged a
bankrupt, or should make a general assignment for the benefit of creditors, or
if a receiver should be appointed on account of insolvency, or if CONTRACTOR
or any sub -contractor should violate any of the provisions of the Contract,
CITY may serve written notice upon CONTRACTOR and CONTRACTOR'S surety of its
intention to terminate the Contract. Such notice shall contain the reasons for
CITY'S intention to terminate the Contract, and unless within ten(10) days
after serving of such notice, such violation shall cease and satisfactory
arrangements for corrections thereof be made, the Contract shall, upon the
expiration of said ten(10) days, cease and terminate. In the event of any such
termination, CITY shall immediately serve notice thereof upon CONTRACTOR'S
surety and CONTRACTOR, and the surety shall have the right to take over and
perform the Contract; provided, however, that, if the surety within
fifteen(15) days after the serving upon it of notice of termination does not
give CITY written notice of its intention to take over and perform the
Contract, or does not commence performance thereof within thirty(30) days from
the date of the serving of such notice, CITY may take over the work and
prosecute the same to completion by contract, or by any other method it may
deem advisable, for the account and at the expense of CONTRACTOR, and
CONTRACTOR and CONTRACTOR'S surety shall be liable to CITY for any excess cost
occasioned by CITY thereby, and in such event CITY may, without liability for
so doing, take possession of, and utilize in completing the work, such
materials, appliances, plant and other property belonging to CONTRACTOR as may
be on the site of the work and necessary therefor.
Contract Page 3 of 6
CONTRACT FOR PUBLIC WORKS(Continued)
PROJECT No. 5004 and 5004(A)
13. THE CITY'S RIGHT TO WITHHOLD CERTAIN AMOUNTS AND MAKE APPLICATION
THEREOF. In addition to amounts which CITY may retain under other provisions
of the Specifications until final completion and acceptance of all work
covered by the Contract, CITY may withhold from payment to CONTRACTOR such an
amount or amounts as in its judgement may be necessary to pay just claims
against CONTRACTOR or sub -contractors for labor and services rendered and
materials furnished in and about the work. CITY may apply such withheld amount
or amounts to the payment of such claims in its discretion. In doing so, CITY
shall be deemed the agent of CONTRACTOR, and any payment so made by CITY shall
be considered as a payment made under the Contract by CITY to CONTRACTOR, and
CITY shall not be liable to CONTRACTOR for any payment made in good faith.
Such payment may be made without prior judicial determination of the claim or
claims. With respect to any retention of payment by CITY to ensure performance
of the Contract, CONTRACTOR will be entitled to substitute securities as
provided in Section 4590 of the California Government Code as more fully
described in CITY'S Notice to Contractors.
14. NOTICE AND SERVICE THEREOF. Any notice from one party to the other under
this Contract shall be in writing, and shall be dated and signed either by the
party giving such notice, or by a duly authorized representative of such
party. Any such notice shall not be effective for any purpose whatsoever
unless served in the following manner: (a) if the notice is given to CITY
either by personal delivery thereof to the Engineer of CITY, or by depositing
same in the United States mails, enclosed in a sealed envelope, addressed to
CITY, postage prepaid and certified; (b) if the notice is given to CONTRACTOR,
either by personal delivery thereof to CONTRACTOR, or to CONTRACTOR'S duly
authorized representative at the site of the project, or by depositing same in
the United States mails, enclosed in a sealed envelope, addressed to
CONTRACTOR at STEINY and COMPANY, INC., 27 SHERIDAN STREET, VALLEJO, CA 94590
postage prepaid and certified; and (c) if notice is given to CONTRACTOR'S
surety or any other person, either by personal delivery thereof to
CONTRACTOR'S surety or other person, or by depositing same in the United
States mails, enclosed in a sealed envelope, addressed to CONTRACTOR'S surety
or person, as the case may be, at the address of CONTRACTOR'S surety or the
address of the person last communicated by such person to the party giving the
notice, postage prepaid and certified.
15. ASSIGNMENT OF CONTRACT. Neither the Contract, nor any part thereof, nor
moneys due or to become due thereunder, shall be assigned by CONTRACTOR
without the prior written approval of CITY.
16. COMPLIANCE WITH SPECIFICATIONS OF MATERIALS. Whenever in the
Specifications, any material or process is indicated or specified by patent or
proprietary name, or by name of manufacturer, such Specifications must be met
by CONTRACTOR, unless CITY agrees in writing to some other material, process
or article offered by CONTRACTOR which is equal in all respects to the one
specified. It shall be CONTRACTOR'S responsibility to prove equality of any
such material, process or article offered as a substitution to the one(s)
specified.
Contract Page 4 of 6
CONTRACT FOR PUBLIC WORKS(Continued)
PROJECT No. 5004 and 5004(A)
17. WORKER'S COMPENSATION INSURANCE AND EMPLOYER'S LIABILITY INSURANCE.
CONTRACTOR shall take out and maintain during the life of this Contract
Worker's Compensation Insurance and Employer's Liability Insurance for all of
CONTRACTOR'S employees employed at the site of the project. In case any work
is sublet, CONTRACTOR shall require any and all sub -contractors similarly to
provide Worker's Compensation and Employer's Liability Insurance for all of
the latter's employees unless such employees are covered by the protection
afforded by CONTRACTOR. In signing this Contract CONTRACTOR makes the
following certification, required by Section 1861 of the Labor Code: "I am
aware of the provisions of Section 3700 of the Labor Code which requires every
employer to be insured against liability for worker's compensation or to
undertake self insurance in accordance with the provisions of the Labor Code,
and I will comply with such provisions before commencing the performance of
the work of this Contract."
18. ACCIDENT PREVENTION. Precaution shall be exercised at all times for the
protection of persons (including employees) and property. The safety
provisions of applicable laws, building codes and construction codes shall be
observed. Machinery, equipment and other hazards shall be guarded or
eliminated in accordance with the safety provisions of the Construction and
Safety Orders issued by the Industrial Accident Commission of the State of
California.
19. CONTRACTOR'S RESPONSIBILITY FOR THE WORK. CONTRACTOR shall not be
responsible for the cost of repairing or restoring damage to the work caused
by Acts of God. NEVERTHELESS, CONTRACTOR shall, if the insurance premium is a
seperate bid item, obtain the insurance to indemnify CITY for any damage to
the work caused by Acts of God. "Acts of God" shall include only the following
occurances or conditions and effects: earthquakes and tidal waves, when such
occurances or conditions and effects have been proclaimed a disaster or state
of emergency by the President of the United States or by the Governor of the
State of California, or were of a magnitude at the site of the work sufficient
to have caused a proclamation of disaster or state of emergency having occured
in a populated area. Subject to the foregoing, CITY shall not, in any way or
manner, be answerable or suffer loss, damage, expense or liability for any
loss or damage that may happen to said building, work, or equipment or any
part thereof, or in, on, or about the same during its construction and before
acceptance.
20. CONTRACTOR'S GUARANTEE. CONTRACTOR unqualifiedly guarantees the first-
class quality of all work and of all materials, apparatus and equipment used
or installed by CONTRACTOR or by any sub -contractor or supplier in the project
which is the subject of this Contract, unless a lesser quality is expressly
authorized in the Plans and Specifications, in which event CONTRACTOR
unqualifiedly guarantees such lesser quality; and that the work as performed
by CONTRACTOR will conform with the Plans and SPecifications or any written
authorized deviations therefrom. In case of any defect in the work, materials,
apparatus or equipment, whether latent or patent, revealed to CITY within
one(1) year of the date of acceptance of completion of this Contract by CITY,
CONTRACTOR will forthwith remedy such defects without cost to CITY.
Contract Page 5 of 6
CONTRACT FOR PUBLIC WORKS(Continued)
PROJECT No. 5004 and 5004(A)
21. ADDITIONAL PROVISIONS.
IN WITNESS WHEREOF, the parties have executed this Contract, in
duplicate, the day and year first hereinabove written.
CITY OF CUPERTINO
By: Q�
M y r
r
Attest:
City Cle
Dater ! ,1989
'ty Clerk
APPROVED AS TO FORM AND
PROCEDURE:
71
City Attorney
STEINY and COMPANY, INC.
Notary acknowledgement is required.
If a corporation, corporate seal and
corporate notary acknowledgement are
required.
Contract Amount:Sixty Eight Thousand Five Hundred and Seventy Dollars and
Eighty Cents($68,570.80)
Account Number:120-5007-953
Purchase Order Number:
STATE OF CALIFORNIA ss.
COUNTY OF Los Angeles
OFFICIAL SEAL d
MARY McCLUNG `
NOTARY PUBLIC -CA
oLIFORIVIA
PRINCIPAL OFFICE IN
r L.OS ANGELES COUNTY
My Commission Expires Niar. 19, 1991
4h .
On this
10th dayof April, 1989 , in the year 19_,
before me, the undersigned, a Notary Public in and for said State, personally appeared
Jay E. Perry — Secretary
STEINY AND COMPANY , INC . personally known to me
(or proved to me on the basis of satisfactory evidence) to be the person who executed the
within instrument on behalf of the Corporation therein named, and acknowledged to me that
the Corporation executed it.
---WMfiNESS my hand and official seal.
Notary Public in and for said State.
ACKNOWLEDGMENT —Corporation —Wolcotts Form 222CA-X—Rev. 5-82