CC 04-16-19 #9 McClellan Rd Separated Bikeways-Phase 1B Project PresentationMcClellan Road Separated Bikeways- Phase 1B
1
SITE MAP OF IMPROVEMENTS
Phase 1A – Imperial to Rose Blossom – Some make ready work completed, kickoff ceremony on May 17th, project starts May 20, 2019, anticipated completed by August 9, 2019
Phase 1B – Intersection improvements at Bubb & Stelling
Phase 2 – Rose Blossom to Torre – land donations by property owners ongoing; status of design 35%; Summer 2020 construction.
Phase 3 – Imperial to Byrne – requires land donations by property owners. Construction anticipated Summer 2021 construction
Phase 4 – Intersection improvements at De Anza/Pacifica/McClellan. Construction anticipated Fall 2020 construction
In the 2016 Bike Plan this project was rated as a priority ?
2
McClellan Road &
Bubb Avenue
Due to long lead times, City purchased (ordered) required signal poles and arms in December, 2018; these items will be delivered to the City early May, 2019.
Bollards were ordered September, 2018 and received in October, 2018.
Scope of improvements include:
Curb ramp modifications to increase pedestrian refuge / calm traffic
Traffic signal modifications
Bike lane through intersection
Bike boxes
Improved curb ramps
3
McClellan Road &
South Stelling Road
Scope of improvements include:
Curb ramp modifications to increase pedestrian refuge / calm traffic
Traffic signal modifications
Bike lane through intersection
Bike boxes reconfigured
4
Construction Dollars
Phase 1A – $1,821,831
Phase 1B - $1.5M
Phase 2 - $1.5M
Phase 3 - $1.5M
Phase 4 - $1.5M
Total: $7.82M
External funding:
Developer in-lieu- $157,000
Vehicle Emissions Reduction Based at Schools (VERBS) Grant-$1M
Transportation Fund for Clean Air (TFCA) Grant- $85,900
Apple- $4.63M
2016 Measure B- $1M
5
Recommendation
Award construction contract for the Phase 1B
Project in the amount of $1,365,420 and authorize contingency amount of up to $136,000 for a total authorized amount of $1,501,420.
6