CC 04-30-19 #2 City Hall and Library Expansion Funding Strategy Presentation4/30/2019
1
City Council April 30, 2019
City Hall & Library Expansion
Design, Delivery & Funding
Strategies
Presentation Outline
●Background
●Conditions of Existing City Hall
●Design Delivery Strategy
●Library Expansion
●Schedule
●Cost / Funding
4/30/2019
2
December 2012 – CCMP Study
Civic Network
4/30/2019
3
Civic Youth
Civic Life
4/30/2019
4
April 2014 Master Plan+Parking
Project
Council / Community Input
●July – December 2015
●February – November 2018
4/30/2019
5
New City Hall –Specifications
●Essential facility of 40,000 square feet
●118 stall underground parking garage
●Larger meeting and program space for activities
and City business
●LEED Silver design equivalent
New City Hall –2014 Cross Section
4/30/2019
6
New City Hall –2014 Below Parking
New City Hall –2014 1st Floor
4/30/2019
7
New City Hall –2014 2nd Floor
New City Hall –
2014 Representation
4/30/2019
8
What will public want in a
New City Hall?
Conditions of Existing City Hall
●Insufficient space
●Health & safety
●Seismic retrofit
●HVAC
●Electrical
4/30/2019
9
Construction Delivery
●Design, Bid, Build
●Design Build
●Construction Manager at Risk
●Lease-Leaseback
●Public-Private Partnership
●Developer Agreement
Design Delivery Strategy
RFQ
Interviews
Design
Competition
Five
Member
Panel
City
Council
Decision
4/30/2019
10
Library Expansion
West Wing Expansion
4/30/2019
11
East Wing Expansion
Court Yard Infill
4/30/2019
12
Perched Expansion – 1
st Floor
Perched Expansion – 2
nd Floor
4/30/2019
13
Perched Expansion – 2014
Perched Expansion – 2014
4/30/2019
14
Perched Expansion – 2014
New City Hall Schedule
Activity Date
Issue Design RFQ July 10, 2019
Complete Conceptual Design September 25, 2019
Start Design December 2, 2019
Construction Documents Complete February 3, 2021
Start of Construction August 9, 2021
City Hall Complete October 30, 2023
4/30/2019
15
Interim City Hall Schedule
Activity Date
Start Design August 5, 2019
Start Construction September 28, 2020
Complete Construction April 9, 2021
Transition Staff April 12 – 30, 2021
Move out and restore site
Complete restoration
Foothill Blvd.
Voss Ave.
Woodridge Ct.
McKlintock Ln.
4/30/2019
16
Monta Vista Community
Center Programs
●Home to Tiny Tots/Super Tots
●Gymnastic Program
●Kung Fu & Judo Clubs
●Art & Education Classes
Library Expansion Schedule
Activity Date
Issue RFP for Architect July 6, 2021
Start Design December 13, 2021
Construction Documents Complete February 3, 2023
Start Construction August 7, 2023
Construction Complete November 29, 2024
4/30/2019
17
Cost Projections of New City
Hall/Library Expansion ‘14 – ‘19
2014 Feb. 2018 April 2019
City Hall $61.6M - -
Library Exp. $8.1M - -
City Hall - $69.15M -
Library Exp. - $9.95M -
City Hall - - $70.51M
Library Exp. - - $10.05M
●New City Hall
●$30M capital reserves
●$40M certificate of
participation
Funding – New City Hall
4/30/2019
18
●Library Expansion
●$11M general obligation
bond
Funding – Library Expansion
Funding Schedule
Activity Date
Ballot Initiative to Increase:
•Transactional Use Tax .25%
•Transient Occupancy Tax 2%
November 2020
Ballot Initiative for General Obligation
Bond November 2020
Initiate Certificate of Participation April 5, 2021
Receive Voter Approved Revenue April 2021
4/30/2019
19
Survey
●Open from April 12th to April 26th
●259 responses
●Available via City’s Open City
Hall, Earth Day festival, social
media and e-notifications on
April 23rd
Question #1
4/30/2019
20
Question #2
Question #3
4/30/2019
21
CIP Study Session to Follow
●End of City Hall / Library
presentation
●CIP study session to follow
●Format of presentation
City Hall
●New - $70.5M
●Renovated - $23M
●Minimum - $6.6M
4/30/2019
22
Recent Architectural Design
Fees for Public Buildings
City of Los Altos Community Center (proposed)
●$23.4 million
●20,000 SF
●Design Fee $3.35 million (14.3%)
City of Pleasant Hill New Library
●$24 million
●25,000 SF
●Design Fee $3.1 million (13%)