CC 05-13-19 #5 Study Session FY 19-24 Proposed CIP_B - CIP Project NarrativesATTACHMENT B C I P FY 2020 Capital Improvement Program Proposed FY 2020 Planned FY 2021-2024 PROPOSED PROJECTS PUBLIC WORKS DEPARTMENT Roger Lee, Acting Director CITY HALL 10300 TORRE AVENUE ~ CUPERTINO, CA 95014-3266 (408) 777-3354 ~ FAX (408) 777-3333 CUPERTINO.ORG Table of Contents Category 1 – ............................................................................................................................................ 6 New Projects – Current Year ............................................................................................................... 6 Library Expansion – Surface Parking Lot ..................................................................................... 7 Library Expansion – “Perch” Option ............................................................................................. 8 Quinlan Preschool Shade Structure .............................................................................................. 9 Regnart Road Improvements Phase 1: Sta 28+40 to 29+80 (Retaining Wall) ........................ 10 Sports Center – Seismic Retrofit .................................................................................................. 11 Category 2 – .......................................................................................................................................... 12 Existing Projects – Multi-Year Funding .......................................................................................... 12 ADA Improvements ....................................................................................................................... 13 Capital Project Support .................................................................................................................. 15 CIP Preliminary Planning & Design ........................................................................................... 16 Street Light Installation – Annual Infill ..................................................................................... 17 Category 3 – .......................................................................................................................................... 18 Existing Projects - Completely Funded ........................................................................................... 18 2016 Bike Plan Implementation.................................................................................................... 19 Stevens Creek Boulevard Class IV Bikeway Installation Phase I (Dev. Funded) 20 Blackberry Farm Entrance Road Improvements - Feasibility ................................................. 21 Carmen Road Pedestrian/Bike Bridge Study ............................................................................. 22 City Bridge Maintenance Repairs ................................................................................................ 23 Citywide Parks and Recreation Master Plan and CEQA Analysis ........................................ 24 Lawrence-Mitty Park ...................................................................................................................... 25 Lawrence-Mitty Park Master Plan ............................................................................................... 26 McClellan Road Sidewalk Improvements – Phase 2................................................................ 27 McClellan Rd. Sidewalk Installation – Rose Blossom Dr. to Hwy 85 Overcrossing ......... 28 McClellan Ranch West Parking Lot Improvement ................................................................... 29 Memorial Park Master Plan & Parking Study ........................................................................... 30 Senior Center Repairs .................................................................................................................... 31 Sidewalk Improvements – Orange & Byrne .............................................................................. 32 Stevens Creek Blvd. and Bandley Dr. Signal Upgrades (Dev. Funded) ............................... 33 Stevens Creek Corridor Park Chain Master Plan – McClellan to Stevens Creek Blvd. .... 34 Street Light Installation – Randy Ln. & Larry Wy. ................................................................... 35 Street Light Replacement – Citywide (Labor Only) ................................................................. 36 Category 4 – .......................................................................................................................................... 37 Projects with External Funding ........................................................................................................ 37 All Inclusive Playground ............................................................................................................... 38 Bubb Road Improvements ............................................................................................................ 39 Junipera Serra Trail – Basic Design of All Segments ............................................................... 40 Linda Vista Trail (Land donation if we commit to construct) ................................................ 41 Mary Avenue Protected Bikeways ............................................................................................... 42 McClellan Rd. Bike Corridor Phase 3-Signal Intersection Improvements @ DeAnza/Pacifica .............................................................................................................................. 43 McClellan Rd. Bike Corridor Phase 4- Imperial to Byrne Separated Bike Lane ................. 44 School Walk Audit Implementation ........................................................................................... 45 Solar Electric Vehicle Chargers .................................................................................................... 46 Other Unfunded Projects ................................................................................................................... 47 Aquatics Facility .............................................................................................................................. 48 Bicycle Plan Implementation Phase 2: SCB – Wolfe Rd to Hwy 85 ....................................... 49 Bicycle Plan Implementation Phase 3: SCB – Hwy 85 to Foothill Expwy ............................ 50 Bicycle Plan Implementation Phase 4: Stevens Creek Blvd @ Stelling Rd .......................... 51 Bicycle Plan Implementation Phase 5: Grade Separated Crossing Study – Grand Ave to Mary Ave .......................................................................................................................................... 52 Blackberry Farm Entrance Road Improvements ....................................................................... 53 Blackberry Farm Golf Course Renovation ................................................................................. 54 Blackberry Farm – Play Area Improvements ............................................................................. 55 Blackberry Farm – Splash Pad ...................................................................................................... 56 Bicycle Boulevard Phase 1 & 2 Permanent Improvements ..................................................... 57 Carmen Road Pedestrian/Bike Bridge Design & Construction .............................................. 58 Citywide Building Condition Assessment Implementation Phase 2 ................................... 59 Citywide Building Condition Assessment Implementation Phase 3 ................................... 60 Citywide Building Condition Assessment Implementation Phase 4 ................................... 61 Citywide Building Condition Assessment Implementation Phase 5 ................................... 62 Creek Infall/Outfall Restoration .................................................................................................. 63 Creekside Park Improvements ..................................................................................................... 64 De Anza Median Island Landscaping Phase II - Construction .............................................. 65 Gymnasium Complex..................................................................................................................... 66 Healing Garden – Design and Construction .............................................................................. 67 Jollyman Park Improvements ....................................................................................................... 68 Jollyman Park Pathway Installation ............................................................................................ 69 Junipera Serra Trail Segment #3: Wolfe Rd. to Vallco Pkwy.................................................. 70 Junipera Serra Trail Segment #2: De Anza Blvd to Wolfe Rd. ............................................... 71 Junipera Serra Trail Segment #1: Don Burnett Bridge to De Anza Blvd. ............................. 72 Linda Vista Park Improvements .................................................................................................. 73 Mary Avenue Trail and Greenbelt .............................................................................................. 74 McClellan Ranch – Construct Trash Enclosure (Design Complete)...................................... 75 McClellan Ranch – Barn Renovation .......................................................................................... 76 McClellan Ranch Preserve Stevens Creek Access .................................................................... 77 McClellan Road Bridge Replacement @ Stevens Creek .......................................................... 78 Memorial Park – Tennis Court Restroom Replacement .......................................................... 79 Memorial Park Phase 1 – Pond Removal .................................................................................... 80 Memorial Park Phase 2 Improvements ....................................................................................... 81 Memorial Park Phase 3 Improvements ....................................................................................... 82 McClellan Ranch Preserve Community Garden Improvements – Construction ................ 83 McClellan Ranch Preserve EEC Aquatic Habitat ...................................................................... 84 New Neighborhood Parks ............................................................................................................. 85 Performing Arts Center .................................................................................................................. 86 Portal Park Improvements ............................................................................................................. 87 Quinlan Front Office Upgrades ................................................................................................... 88 Quinlan HVAC Upgrades ............................................................................................................. 89 Recreation Facilities Monument Signs ....................................................................................... 90 Regnart Road Improvements Phase 2: Sta 36+30 to 36+80 (Retaining Wall) ........................ 91 Regnart Road Improvements Phase 3: Sta 23+35 to 23+50 (Culvert/Outfall Replacement) ............................................................................................................................................................ 92 Regnart Road Improvements Phase 4: Sta 7+15 to 7+40 (Retaining Wall) ............................ 93 Regnart Road Improvements Phase 5: Sta 38+95 to 39+40 (Retaining Wall) ........................ 94 Regnart Road Improvements Phase 6: Various Locations (Uphill Side Retaining Wall) . 95 Retaining Wall Repair – Cordova Road ...................................................................................... 96 Senior Center Expansion ............................................................................................................... 97 Service Center – Replacement Administration Building with EOC ..................................... 98 Service Center Shed No. 3 Improvements .................................................................................. 99 Sports Center – Interior Upgrades ............................................................................................. 100 Sports Center HVAC Upgrades .................................................................................................. 101 Stevens Creek Bank Repair – South of SCB – Design & Construction .............................. 102 Stevens Creek Trail & Bridge over UPRR (De Anza Trail) ................................................... 103 Stocklmeir Legacy Farm – Phase 1 Improvements ................................................................. 104 Stocklmeir House – New Sewer Lateral ................................................................................... 105 Storm Drain Improvements Phase 1 (Pumpkin Dr & Cranberry Dr) ................................. 106 Storm Drain Improvements Phase 2 (Pumpkin Dr: Bubb to November) .......................... 107 Storm Drain Improvements Phase 3 (Bubb Rd: Columbus to Monrovia St) .................... 108 Storm Drain Improvements Phase 4 (McClellan Rd: Bubb Rd to September Dr) ..... 109 Storm Drain Improvements Phase 5 (Bubb Rd: Monrovia St to Results Way) ................. 110 Wilson Park Improvements ........................................................................................................ 111 (this page intentionally left blank) 6 FY 2019-2020 CIP Budget - Proposed Category 1 – New Projects – Current Year 7 FY 2019-2020 CIP Budget - Proposed Library Expansion – Surface Parking Lot DESCRIPTION Design and construct a single aisle, surface parking lot on the east side of Library Field with an estimated 68 parking stalls to meet additional parking needs of the Library Expansion and to satisfy parking deficiencies of the Civic Center. Estimated Project Cost $1,500,000 Location: Library Field Funding: Capital Improvement Fund Requesting Dept.: Public Works PROJECT JUSTIFICATION City Council approved the Civic Center Master Plan on July 7th, 2015, in the master plan the preferred option for an expansion to the Library was the “Perched” option. This expansion would be approximately 4,400 SF and accommodate 130 seats. Additional library parking is required to mitigate the impact of the proposed expansion. OPERATING BUDGET IMPACTS: A slight impact to the Operating Budget is anticipated in order to maintain this additional parking area. 8 FY 2019-2020 CIP Budget - Proposed Library Expansion – “Perch” Option DESCRIPTION Develop a design and construct an approx. 4,400 SF addition to the Library building for a “program room” that will seat up to 130 to serve as a meeting space for library events. Using the “Perch” option from the Civic Center Master Plan. Estimated Project Cost $8,550,000 Location: Library Funding: Capital Improvement Fund Requesting Dept.: Public Works PROJECT JUSTIFICATION City Council approved the Civic Center Master Plan on July 7th, 2015, in the master plan the preferred option for an expansion to the Library was the “Perched” option. This expansion would be approximately 4,400 SF and accommodate 130 seats. This expansion would provide alternative meeting space and program space for the library operator. This project includes extensive community outreach. OPERATING BUDGET IMPACTS: Slight impacts to the Operating Budget are anticipated due to the increased size of the building. 9 FY 2019-2020 CIP Budget - Proposed Quinlan Preschool Shade Structure DESCRIPTION Design and construct a new shade structure over the existing play area and sand box at the preschool. Estimated Project Cost $125,000 Location: Quinlan Comm. Ctr. Funding: Capital Improvement Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION The current playground has a shade structure that is ineffective, leaving young preschool students in direct sunlight during use of the playground. The current shade structure is too small and sits squarely over the top of the playground, doing little to provide needed shade. OPERATING BUDGET IMPACTS: This project is not expected to impact Operating expenses. 10 FY 2019-2020 CIP Budget - Proposed Regnart Road Improvements Phase 1: Sta 28+40 to 29+80 (Retaining Wall) DESCRIPTION Phase 1 will construct a retaining wall to stabilize the road slope to the creek from Sta 28+40 to 29+80 (approx. 140 LF). Estimated Project Cost $1,150,000 Location: Regnart Road Funding: Capital Improvement Requesting Dept.: Public Works PROJECT JUSTIFICATION This project continues the stabilization efforts along Regnart Road and compliments the 2017 Outfall Repair and Slope Stabilization project and the Retaining wall project. The 2017 Regnart Road Slope Stability Study identified several areas along Regnart Road that exhibit poor drainage characteristics, slope stability concerns that require partial road reconstruction in order to avoid costly road or slope failures and lengthy road closures. Proposed improvements include additional drainage structures, regrading/repaving the road to drain towards the creek, slope stabilization and erosion control measures and retaining walls. OPERATING BUDGET IMPACTS: This project should minimize or prevent costly emergency responses by maintenance crews resulting in a savings to the operating budget. 11 FY 2019-2020 CIP Budget - Proposed Sports Center – Seismic Retrofit DESCRIPTION Design and construct structural upgrades to the Sports Center for increased resiliency in the event of an earthquake. Estimated Project Cost $1,275,000 Location: Sports Center Funding: Capital Improvement Requesting Dept.: Public Works. PROJECT JUSTIFICATION The Citywide Building Condition Assessment (BCA) identified several areas of concern with the Sports Center facility. Several structural deficiencies were identified that were deemed high priority. Based on the recommendations of the BCA this project will complete the following improvements: • Additional shear walls added to each side of the building • Concrete column reinforcement • Reinforce the balcony frame in the walkways • Reinforce the roofs structural capacity to reduce the vibration OPERATING BUDGET IMPACTS: This project is not anticipated to impact the Operating budget. 12 FY 2019-2020 CIP Budget - Proposed Category 2 – Existing Projects – Multi-Year Funding 13 FY 2019-2020 CIP Budget - Proposed ADA Improvements DESCRIPTION This is an ongoing program, funded annually, to improve accessibility at all public facilities throughout the City. Estimated Project Cost $450,000 (5-year) Location: Various Locations $80,000 FY19/20, $85,000 FY 20/21, $90,000 FY 21/22, $95,000 FY 22/23, $100,000 FY 23/24 Funding: Capital Improvement Requesting Dept.: Public Works PROJECT JUSTIFICATION An update of the City’s ADA Transition Plan was completed in April 2015. The plan identifies improvements needed and priorities to achieve compliance with ADA in public buildings, parks, and the public right of way. OPERATING BUDGET IMPACTS: There are no anticipated impacts to the Operating Budget. 14 FY 2019-2020 CIP Budget - Proposed Bicycle Wayfinding Implementation DESCRIPTION Implement to Bicycle Wayfinding Plan that recommends the location and messaging for the bicycle wayfinding signage. Estimated Project Cost: $65,000 Location: Various Locations Funding: Capital Improvement Requesting Dept.: Public Works PROJECT JUSTIFICATION The 2016 Bicycle Transportation Plan identifies bicycle wayfinding improvement needed and priorities to enhance and promote safer bicycle transportation in the City. The Bicycle Wayfinding Plan was completed in 2018. This project will implement the recommendations included in the plan. OPERATING BUDGET IMPACTS: There are no anticipated impacts to the Operating Budget. 15 FY 2019-2020 CIP Budget - Proposed Capital Project Support DESCRIPTION Funding for exceptional or unusual services that may occasionally be required in support of capital projects, so that such expenses may be accounted for and assigned to the project requiring the specific services. Estimated Project Cost: $250,000 (5-year) Location: Various $50,000 annually Funding: Capital Improvement Fund Requesting Dept.: Public Works PROJECT JUSTIFICATION Budgeted capital projects that are in progress occasionally face unexpected management responses that require additional effort by staff or with contract resources. Examples of this are unusual legal or permit/regulatory issues. An annual appropriation will support timely responses to such needs and allow the expenditures to be assigned to the specific projects. OPERATING BUDGET IMPACTS: There are no anticipated impacts to the Operating Budget. 16 FY 2019-2020 CIP Budget - Proposed CIP Preliminary Planning & Design DESCRIPTION Funding for preliminary planning, engineering and design services that are determined to be needed subsequent to the adoption of the CIP Budget. This action will provide the means for the acquisition of resources to respond to CIP initiatives in a timely way. Estimated Project Cost: $625,000 (5-year) Location: Various $125,000 annually Funding: Capital Improvement Requesting Dept.: Public Works PROJECT JUSTIFICATION Funding within the CIP operating budget for General Contract Services has been the source of funding for mid-year additions to the CIP project work program for planning. Such project-focused expenditures could not later be assigned to the specific capital project for tracking. Shifting funding from the operating budget to the CIP for preliminary planning and design will provide resources for mid-year CIP initiatives. OPERATING BUDGET IMPACTS: Shifting funding from the operating budget to the CIP for preliminary planning and design will result in a decrease to the operating budget. This has been accounted for in the FY 2019-20 Operating Budget. 17 FY 2019-2020 CIP Budget - Proposed Street Light Installation – Annual Infill DESCRIPTION Design and install streetlights on an as needed basis. Budget Unit: 420-99-056 Priority: 1 Budgeted Amount: $150,000 (5-year) Location: Various $30,000 annually Requesting Dept.: Public Works PROJECT JUSTIFICATION There are areas of the city where street light spacing is insufficient to meet current standards for illumination. Several locations are identified annually for infill with one or two lights. An annual appropriation will allow these deficiencies to be readily addressed. OPERATING BUDGET IMPACTS: This project will use staff time for the installation of these lights. Additional annual energy costs will be minor. Both of these costs are included in the department’s FY 2018-19 Operating Budget. 18 FY 2019-2020 CIP Budget - Proposed Category 3 – Existing Projects - Completely Funded 19 FY 2019-2020 CIP Budget - Proposed 2016 Bike Plan Implementation DESCRIPTION Design and construct high priority improvements of the 2016 Bicycle Transportation Plan. The following projects are proposed to continue or begin in FY 2017-18: • I-280 Channel Trail Feasibility Study ($250,000) • UPRR Trail Feasibility Study ($250,000) • Bicycle Wayfinding Program ($60,000) • Bicycle Blvds Implementation ($1,417,000) • McClellan Rd Bike Corridor ($5,289,000) o Stelling Rd to Imperial Ave Separated Bike Lane o Signal/intersection improvements at Bubb and at Stelling o Stelling to Torre Separated Bike Lane o Imperial to Byrne Separated Bike Lane o Signal/intersection improvements at DeAnza Blvd o Regnart Creek Trail, Feasibility Study Budget Unit: 420-99-036 Priority: 1 Budgeted Amount: $7,266,000 Location: Various Locations Requesting Dept.: Public Works PROJECT JUSTIFICATION The 2016 Bicycle Transportation Plan identifies improvement needed and priorities to enhance and promote safer bicycle transportation in the City. OPERATING BUDGET IMPACTS: Additional maintenance costs are anticipated to maintain the separated bike lanes free of debris and to repaint the green bike lanes as necessary. Any extra costs are anticipated to be minor and will be included in the FY 2019-20 Operating Budget. 20 FY 2019-2020 CIP Budget - Proposed Stevens Creek Boulevard Class IV Bikeway Installation Phase I (Dev. Funded) DESCRIPTION Design and construct a separated bikeway along Stevens Creek Blvd from the east end of the City to Wolfe Rd. Improvements include traffic signal modifications at Wolfe Rd, Finch Ave and Tantau Ave to provide separate bicycle phasing. Budget Unit: 420-99-036 Priority: 1 Budgeted Amount: $1,800,000 Location: Stevens Creek Blvd. – East City Limit to Wolfe Rd. Requesting Dept.: Public Works PROJECT JUSTIFICATION The 2016 Bicycle Transportation Plan identifies improvement needed and priorities to enhance and promote safer bicycle transportation in the City. The number one priority of the Plan was to provide a separated Class IV bicycle lane on Stevens Creek Blvd. This project is the first phase to address that priority. OPERATING BUDGET IMPACTS: It is anticipated that separated bike lanes will require additional maintenance to sweep bike lanes clean of debris. This cost will be in addition to normal street sweeping operations and will be included in FY 2019-20 Operating budget. 21 FY 2019-2020 CIP Budget - Proposed Blackberry Farm Entrance Road Improvements - Feasibility DESCRIPTION Prepare a feasibility study on ways to improve pedestrian and bicycle access to Blackberry Park Farm and Stevens Creek Corridor Trail. Budget Unit: 560-99-061 Priority: 1 Budgeted Amount: $75,000 Location: Blackberry Farm Requesting Dept.: Rec. and Comm. Services PROJECT JUSTIFICATION Current access to Blackberry Farm for bicycles, pedestrians and vehicles is a narrow access road shared by all three groups. This feasibility study will identify and evaluate various concepts to improve access for non-vehicular visitors to the park. OPERATING BUDGET IMPACTS: There will be no Operating Budget impact as a result of this project. This project will use staff time for project management. 22 FY 2019-2020 CIP Budget - Proposed Carmen Road Pedestrian/Bike Bridge Study DESCRIPTION Prepare a feasibility study on ways to improve pedestrian and bicycle access across Stevens Creek Boulevard at Carmen Road. Budget Unit: 420-99-036 Priority: 1 Budgeted Amount: $100,000 Location: Carmen Rd. at Stevens Creek Blvd Requesting Dept.: Public Works PROJECT JUSTIFICATION Currently there is no access across Stevens Creek Boulevard for bicycles and pedestrians at Carmen Road. This feasibility study will identify and evaluate various concepts to create safe access for non-vehicular traffic. OPERATING BUDGET IMPACTS: This project will require staff time to manage the work. Staff time for this project is included in the FY 2018-19 operating budget. 23 FY 2019-2020 CIP Budget - Proposed City Bridge Maintenance Repairs DESCRIPTION Design and construct bridge repairs recommended in the Caltrans Bridge Report along with additional improvements to prolong the useful life of the bridges. Locations: Stevens Creek Blvd., Homestead Rd and McClellan Rd. at Stevens Creek Stevens Creek Blvd., Miller Ave. and Tantau Ave. at Calabazas Creek Budget Unit: 270-90-960 Priority: 1 Budgeted Amount: $700,000 Locations: Various See Description Requesting Dept.: Public Works PROJECT JUSTIFICATION The City of Cupertino owns and maintains a total of seven vehicular bridges. Caltrans inspects these bridges and prepares a biennial report detailing the recommended repairs. Six of the seven bridges require rehabilitation. The required minor rehabilitation includes the repairs as recommended in the Caltrans Bridge Report as well as additional work to prolong the life and use of the bridges. Approximately 88% of the project costs are eligible for Federal reimbursement through Caltrans’ Bridge Preventive Maintenance Program (BPMP). OPERATING BUDGET IMPACTS: There are no anticipated impacts to the Operating Budget. 24 FY 2019-2020 CIP Budget - Proposed Citywide Parks and Recreation Master Plan and CEQA Analysis DESCRIPTION Prepare a long-range, citywide park and recreation system master plan. The planning process will include an evaluation of the recreation services, a needs assessment, and substantial outreach to the community. The master plan will provide guidance regarding recreation services needs as well as future renovations and capital needs for recreation facilities, including parks and open space. Budget Unit: 420-99-045 Priority: 1 Budgeted Amount: $600,000 Location: City Parks Requesting Dept.: Rec. and Comm. Services PROJECT JUSTIFICATION The master plan will provide guidance and recommendations on how to meet the future demand for recreation services and programming, operations, and establish priorities for facility improvements and acquisitions. A comprehensive needs assessment and plan for recreation services will inform future capital improvements and operations for those services. OPERATING BUDGET IMPACTS: This project will use staff time for the management and development of the master plan , this time is included in the department’s FY 2018-19 Operating Budget. Implementation of any specific recommendations will be a separate request and operating budget impacts will be assessed at that time. 25 FY 2019-2020 CIP Budget - Proposed Lawrence-Mitty Park DESCRIPTION Develop a neighborhood park on several acres of land adjacent to Saratoga Creek, near the intersection of Lawrence Expressway and Mitty, which is currently owned by the County and within the City of San Jose. Acquire the land, annex the land, design and construct the park. Budget Unit: 280-99-009 Priority: 1 Budgeted Amount: $8,170,994 Location: Lawrence Expwy. and Mitty Requesting Dept.: Rec. and Comm. Services PROJECT JUSTIFICATION The City is under-served for neighborhood parks to meet the level of service goal of the City’s General Plan. The east side of the City is particularly under-served. OPERATING BUDGET IMPACTS: A new park will require additional operation and maintenance and will require an increase in the Operating Budget. The additional cost will depend on the type and size of the improvements and will be identified at time of award. 26 FY 2019-2020 CIP Budget - Proposed Lawrence-Mitty Park Master Plan DESCRIPTION Develop a Master Plan for a proposed neighborhood park located on several acres of land adjacent to Saratoga Creek, near the intersection of Lawrence Expressway and Mitty Way. Budget Unit: 280-99-009 Priority 2 Budgeted Amount: $100,000 Location: Lawrence Expressway and Mitty Way Requesting Dept.: Rec. and Comm. Services PROJECT JUSTIFICATION The City is under-served for parks and open space to meet the level of service goal of the City’s General Plan. The east side of the City is particularly under-served. With the acquisition and annexation of the project, the next step is to master plan the site to determine the best use for the site. OPERATING BUDGET IMPACTS: This project is not expected to impact Operating expenses. 27 FY 2019-2020 CIP Budget - Proposed McClellan Road Sidewalk Improvements – Phase 2 DESCRIPTION Design and construct sidewalk improvements along McClellan Road between Orange Avenue and San Leandro Avenue Budget Unit: 270-90-976 Priority: 1 Budgeted Amount: $2,035,000 Location: McClellan Rd. between Orange and San Leandro Avenues. Requesting Dept.: Public Works PROJECT JUSTIFICATION In 2013, staff completed a feasibility study for the installation of sidewalks along McClellan Road between Orange Avenue and San Leandro Avenue. McClellan Road has a high volume of pedestrian traffic due to the close proximity of Lincoln Elementary School, Kennedy Middle School and Monta Vista High School, and there are large segments of McClellan Road, which currently lack sidewalks. Phase 1 of this project, which installs sidewalks along the less challenging segments, is currently being implemented. Phase 2 will install sidewalks along the remaining segments, which involve challenges such as acquiring right-of-way, relocation of utilities, etc., and will be implemented over a two-year period. OPERATING BUDGET IMPACTS: There are no anticipated impacts to the Operating Budget. 28 FY 2019-2020 CIP Budget - Proposed McClellan Rd. Sidewalk Installation – Rose Blossom Dr. to Hwy 85 Overcrossing DESCRIPTION Design and construct approximately 650 LF of sidewalk on the north side of McClellan between 85 and Rose Blossom. Budget Unit: 420-99-057 Priority: 1 Budgeted Amount: $430,000 Location: McClellan Rd. – Rose Blossom to Hwy 85 Overcrossing Requesting Dept.: Public Works PROJECT JUSTIFICATION There is a sidewalk gap on the north side of McClellan Rd. between Rose Blossom and the Hwy 85 overcrossing, an active pedestrian area that is well used by students and other residents. Installing a sidewalk in this location will provide continuous access to and from local schools including De Anza College. OPERATING BUDGET IMPACTS: There are no anticipated impacts to the Operating Budget. 29 FY 2019-2020 CIP Budget - Proposed McClellan Ranch West Parking Lot Improvement DESCRIPTION Design and construct a new “green” meadow-style parking lot that is compatible with the creek environment at McClellan Ranch West, which will be designed to have minimal impact to the site. Budget Unit: 420-99-030 Priority: 1 Budgeted Amount: $950,000 Location: McClellan Ranch West Requesting Dept.: Rec. and Comm. Services PROJECT JUSTIFICATION The McClellan Ranch West site has been used informally for staff and overflow parking without a suitable, stable surface, and which is not available for use during wet weather due to mud. The opening of the Environmental Education Center in 2015 has increased the parking demand at McClellan Ranch Preserve. The removal of the Simms house on the McClellan Ranch West site advances the option to provide the additional parking that is needed by providing a suitable parking surface. OPERATING BUDGET IMPACTS: This project will formalize the existing use of this area. Minor impacts to the Operating budget are anticipated and are included in the FY 2018-19 Operating Budget. 30 FY 2019-2020 CIP Budget - Proposed Memorial Park Master Plan & Parking Study DESCRIPTION Develop a master plan for the renovation Memorial Park and evaluate the parking needs for Memorial Park, Senior Center, Sports Center and the Quinlan Community Center. The project may result in a future renovation project. Budget Unit: 420-99-005 Priority: 2 Budgeted Amount: $150,000 Location: Memorial Park Requesting Dept.: Rec. and Comm. Services PROJECT JUSTIFICATION A process to obtain community input and consensus will assist in formulating plans to renovate portions of the park including parking requirements and upgrades for surrounding facilities. This schedule for this Master Planning effort is subject to the completion of the Citywide Parks and Recreation System Master Plan. OPERATING BUDGET IMPACTS: This project will use staff time for the management and development of the master plan , this time is included in the department’s FY 2018-19 Operating Budget. 31 FY 2019-2020 CIP Budget - Proposed Senior Center Repairs DESCRIPTION Design and construct a project to replace the ballroom acoustical panels. Budget Unit: 420-99-059 Priority: 2 Budgeted Amount: $200,000 Location: Senior Center Requesting Dept.: Public Works PROJECT JUSTIFICATION The acoustical panels in the ballroom are showing wear and tear and need to be replaced to keep the facility looking and functioning well. OPERATING BUDGET IMPACTS: There are no anticipated impacts to the Operating Budget. 32 FY 2019-2020 CIP Budget - Proposed Sidewalk Improvements – Orange & Byrne DESCRIPTION Acquire right-of-way as needed, design, and construct new sidewalks. Budget Unit: 270-90-958 Priority: 1 Budgeted Amount: $3,888,000 Location: Orange & Byrne Requesting Dept.: Public Works PROJECT JUSTIFICATION The Monta Vista neighborhood was annexed to the City without having standard right-of-way improvements, including sidewalks. Adding sidewalks to the neighborhood will improve pedestrian safety. OPERATING BUDGET IMPACTS: This project will use staff time for the management of this project. Staff time is included in the department’s FY 2018-19 Operating Budget. 33 FY 2019-2020 CIP Budget - Proposed Stevens Creek Blvd. and Bandley Dr. Signal Upgrades (Dev. Funded) DESCRIPTION Design and construct upgrades to the traffic signal at Bandley Dr. and Stevens Creek Blvd. Improvements include new conduit, wiring, traffic signal boxes, and two new signal heads. Budget Unit: 420-99-070 Priority: 2 Budgeted Amount: $150,000 Location: Stevens Creek Blvd. at Bandley Requesting Dept.: Public Works PROJECT JUSTIFICATION This project will significantly enhance pedestrian safety and pedestrian connectivity across Stevens Creek Blvd within the Crossroads district by reducing pedestrian-vehicle conflicts. Vehicle safety will also be increased for vehicles exiting the Crossroads driveway and Bandley Drive. OPERATING BUDGET IMPACTS: This traffic signal is currently maintained and operated by City staff; no net increase to the operating budget is envisioned as a result of this project. 34 FY 2019-2020 CIP Budget - Proposed Stevens Creek Corridor Park Chain Master Plan – McClellan to Stevens Creek Blvd. DESCRIPTION Study the various uses of public lands along Stevens Creek for optimal public use and operation. Properties to be included are McClellan Ranch Preserve, McClellan Ranch West, Blackberry Farm, Blackberry Farm Golf Course, Nathan Hall Tank House, and the Stocklmeir site. Reconcile the various plans for the different City properties into a comprehensive plan to inform future development and operations. Budget Unit: 420-90-898 Priority: 1 Budgeted Amount: $610,000 Location: Stevens Creek Corridor Requesting Dept.: Rec. and Comm. Services PROJECT JUSTIFICATION The Plan was previously funded and a preferred alternative presented to City Council in April of 2016. The preferred alternative was not adopted with council seeking sufficient progress on the Parks & Recreation Master Plan first. The Parks and Recreation Master Plan is expected to be completed in late 2018 at which time the Corridor master plan will be revisited. OPERATING BUDGET IMPACTS: This project uses staff tome for the management of this Master Plan. The staff time for this project is included in the department’s FY 2018-19 Operating Budget. 35 FY 2019-2020 CIP Budget - Proposed Street Light Installation – Randy Ln. & Larry Wy. DESCRIPTION Design and install street light installations to fill gaps in street light coverage. Budget Unit: 420-99-058 Priority: 1 Budgeted Amount: $367,000 Location: Randy Ln. & Larry Wy. Requesting Dept.: Public Works PROJECT JUSTIFICATION Larry Way and Randy Lane both have gaps in street light coverage that exceed the City’s street light spacing policy. Both streets have been designated semi-rural, which has resulted in a waiver of sidewalk installation, causing pedestrians to walk in the street. Additionally, Lawson Middle School is located immediately south of these streets with the associated student pedestrianism. Residents have requested additional lighting along these streets, and Public Works Staff finds that the additional lighting is warranted. This project will fill gaps in street light coverage along these streets in order to enhance safety. OPERATING BUDGET IMPACTS: This project will use staff time for the management of this project. Additional annual energy costs will be extremely minor. Both of these costs are included in the department’s FY 2018-19 Operating Budget. 36 FY 2019-2020 CIP Budget - Proposed Street Light Replacement – Citywide (Labor Only) DESCRIPTION Replace existing street lights in 55 locations throughout the City. This project will provide the labor to install and coordination with the utility companies to complete the replacement. The City will furnish the new poles. Budget Unit: 420-99-072 Priority: 1 Budgeted Amount: $200,000 Location: Various Requesting Dept.: Public Works PROJECT JUSTIFICATION The City has purchased new street light poles to replace the existing fluted poles that no longer meet the City standard. City staff have already replaced 20 streetlights these remaining 55 locations have conflicts with overhead utilities and require expertise beyond in-house capabilities. This project will provide a mechanism to install the remaining poles. OPERATING BUDGET IMPACTS: This project will require City maintenance staff time to coordinate with the contractor and inspect the work. Staff time for this project is included in the FY 2018-19 operating budget. 37 FY 2019-2020 CIP Budget - Proposed Category 4 – Projects with External Funding 38 FY 2019-2020 CIP Budget - Proposed All Inclusive Playground DESCRIPTION Design and construct an all-inclusive playground at Jollyman Park. Estimated Project Cost: $5,530,000 Location: Jollyman Park Funding: Grant $1,448,000 Capital Improvement $1,230,000 Donations $2,852,000 Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION Community input secured during the Parks & Recreation System Master Plan process favors having an All-Inclusive play area in Cupertino. In October 2018, the City Council unanimously endorsed applying for grant funding from Santa Clara County for an All- Inclusive Playground at Jollyman Park. In December the City was notified that they were awarded a $1.448M grant for construction. This playground will replace the existing playground. OPERATING BUDGET IMPACTS: Anticipated to be a slight impact to the Operating Budget due to the specialized nature of the play equipment. By accepting the grant, the City agrees to construct and maintain the playground for 20 years. 39 FY 2019-2020 CIP Budget - Proposed Bubb Road Improvements DESCRIPTION Installation of protected bike lanes, sidewalks, a new crosswalk with a pedestrian refuge median island and pedestrian activated flashing beacons and revised lane striping. Estimated Project Cost: $1,980,000 Location: Bubb Road Funding: Apple Donation $1,980,000 Requesting Dept.: Public Works PROJECT JUSTIFICATION Apple has offered the City funds to complete these pedestrian and bicycle improvements in order to enhance safety along the section of Bubb Road, between the UPRR Railroad Tracks and Stevens Creek Blvd. Improvements to this section of Bubb Road are included in the Bicycle Transportation Plan. OPERATING BUDGET IMPACTS: It is anticipated that separated bike lanes will require additional maintenance to sweep bike lanes clean of debris. This cost will be in addition to normal street sweeping operations and will be included in FY 2020-21 Operating budget. 40 FY 2019-2020 CIP Budget - Proposed Junipera Serra Trail – Basic Design of All Segments DESCRIPTION Basic design for all segments from the Don Burnett Bicycle-Pedestrian Bridge and Vallco Parkway. Estimated Project Cost: $1,800,000 Location: Junipera Serra Trail Funding: Apple Donation $1,800,000 Requesting Dept.: Public Works PROJECT JUSTIFICATION The 2016 Bicycle Transportation Plan identifies improvement needed and priorities to enhance and promote safer bicycle transportation in the City. The Junipero Serra Trail is one of the trail segments that would make up “The Loop” to provide an off-street bicycle and pedestrian facility that runs parallel to the existing Junipero Serra Channel and Calabazas Creek and would provide a connection between the Don Burnett Bicycle – Pedestrian Bridge and Vallco Parkway when all the sections are completed. This project would fund the basic design of all segments from the Don Burnett Bicycle-Pedestrian Bridge to Vallco Parkway for future construction projects. OPERATING BUDGET IMPACTS: Anticipated a slight impacts to the Operating Budget as staff will need to provide oversight of the consultant for the design. 41 FY 2019-2020 CIP Budget - Proposed Linda Vista Trail (Land donation if we commit to construct) DESCRIPTION Design and construct a bicycle pedestrian trail between Linda Vista Park and McClellan Road. Estimated Project Cost: $2,200,000 Location: Linda Vista Park Funding: Capital Improvement McClellan Rd to Park Requesting Dept.: Public Works PROJECT JUSTIFICATION Creates connections envisioned within the General Plan, the Bicycle Transportation Plan, the Pedestrian Master Plan and the Stevens Creek Trail Feasibility Study. Additionally, the land is owned by a private individual who is willing to dedicate the land to the City free of charge if the project can be designed and funded by the end of 2019. OPERATING BUDGET IMPACTS: It is anticipated that trails will require additional maintenance however, it is anticipated that these impacts will be minimal. 42 FY 2019-2020 CIP Budget - Proposed Mary Avenue Protected Bikeways DESCRIPTION Design and construct a protected bikeway from Stevens Creek Blvd. to the Don Burnett Bicycle- Pedestrian Bridge . Estimated Project Cost: $165,000 Location: Mary Avenue Funding: Apple Donation $165,000 Requesting Dept.: Public Works PROJECT JUSTIFICATION The 2016 Bicycle Transportation Plan identifies improvement needed and priorities to enhance and promote safer bicycle transportation in the City. This project would fund the installation of a protected bikeway from Stevens Creek Blvd. to the Don Burnett Bicycle-Pedestrian Bridge to complete a project included in the 2016 Bicycle Transportation Plan. OPERATING BUDGET IMPACTS: It is anticipated that separated bike lanes will require additional maintenance to sweep bike lanes clean of debris. This cost will be in addition to normal street sweeping operations and will be included in FY 2020-21 Operating budget. 43 FY 2019-2020 CIP Budget - Proposed McClellan Rd. Bike Corridor Phase 3-Signal Intersection Improvements @ DeAnza/Pacifica DESCRIPTION Improves pedestrian and bicycle safety by realigning the intersection and reconfiguring the vehicle movements. Improvements include relocating two signal mast arms and poles, related electrical, concrete and striping work, and elimination of the free right turn lanes from eastbound McClellan Road and westbound Pacifica Drive Estimated Project Cost: $1,500,000 Location: DeAnza Funding: Apple Donation $3,130,000 at McClellan/Pacifica Requesting Dept.: Public Works PROJECT JUSTIFICATION Improve traffic flow, efficiency and bicycle safety at this complex intersection. OPERATING BUDGET IMPACTS: There are no known additional operating budget impacts associated with this project. 44 FY 2019-2020 CIP Budget - Proposed McClellan Rd. Bike Corridor Phase 4- Imperial to Byrne Separated Bike Lane DESCRIPTION Design and construct separated bike lanes on McClellan Rd. from Imperial Ave to Byrne Ave. Estimated Project Cost: $1,500,000 Location: McClellan Rd. – Imperial to Funding: Apple Donation $1,500,000 Byrne Requesting Dept.: Public Works PROJECT JUSTIFICATION The 2016 Bicycle Transportation Plan identifies improvement needed and priorities to enhance and promote safer bicycle transportation in the City. This project is the last phase of a four phase program that installed separated bikeway on McClellan Road. OPERATING BUDGET IMPACTS: It is anticipated that separated bike lanes will require additional maintenance to sweep bike lanes clean of debris. This cost will be in addition to normal street sweeping operations and will be included in FY 2021-22 Operating budget. 45 FY 2019-2020 CIP Budget - Proposed School Walk Audit Implementation DESCRIPTION This project will construct infrastructure related improvements around schools that were identified as part of the comprehensive School Walk Audit study. Estimated Project Cost: $1,500,000 Location: Various Funding: Apple Donation $1,200,000 Capital Improvement $300,000 Requesting Dept.: Public Works PROJECT JUSTIFICATION One of the goals of the Pedestrian Master Plan is to increase pedestrian safety around schools. The primary goal of the School Walk Audit report is to increase pedestrian and bicycle safety around schools. This project will attempt to address both goals; enhance bike and/or pedestrian safety around schools, as well as potentially facilitating student drop-off and pick-up operations to help alleviate vehicle congestion around schools. OPERATING BUDGET IMPACTS: There are no anticipated impacts to the Operating Budget. 46 FY 2019-2020 CIP Budget - Proposed Solar Electric Vehicle Chargers DESCRIPTION Installation of 30 solar powered electric vehicle chargers at four City facilities throughout the City: • Quinlan Community Center – 6 • Blackberry Farm – 12 • Sports Center – 6 • Monta Vista Recreation Center - 6 Estimated Project Cost: $827,400 Location: TBD Funding: BAAQMD Grant: $106,000 SVCE Grant: $100,000, Capital Improvement Fund Requesting Dept.: Public Works PROJECT JUSTIFICATION The number of electric vehicles, community adoption rates for electric vehicles are steadily increasing. Additionally, City Staff are also purchasing electric vehicles to get to work within the City, and many staff need to charge once they get here. The need for infrastructure that meets this need is that we need more electric vehicle charging stations at our public facilities. This project will also provide solar electricity to charge the EV chargers, so demand will not be diverted form the needs our buildings. In addition, when vehicles are not charging, the solar electricity will feed back to the building helping to reduce load and demand charges during the day. This project is grant eligible from two sources. The minimum eligible amount from Bay Area Air Quality Management District (BAAQMD) is $106,000 and from Silicon Valley Clean Energy (SVCE) Innovation grant is $100,000 (applied to the Monta Vista Recreation Center site. OPERATING BUDGET IMPACTS: There are no anticipated impacts to the Operating Budget 47 FY 2019-2020 CIP Budget - Proposed Other Unfunded Projects 48 FY 2019-2020 CIP Budget - Proposed Aquatics Facility DESCRIPTION Design and construct a facility that would provide year-round swimming, designed for recreation and instructional swimming, aquatic exercise, lap swimming and pool events. Estimated Project Cost: $ 50,000,000 Location: TBD Funding: Capital Improvement, General Obligation Bond Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION The City Council reviewed the Cupertino Parks and Recreation System Master Plan in April 2019. The master plan included recommendations for the adding of new major facilities to meet community needs at existing park, and a year-round aquatic facility was one of the major new facilities identified. One of the goals was to provide a year-round swimming facility, designed for recreation and instructional swimming, aquatic exercise, lap swimming and pool events. Potential sites identified were Memorial Park, Creekside Park, Jollyman Park, Wilson Park, new site or Public-private partnership. OPERATING BUDGET IMPACTS: The exact impacts to the Operating Budget cannot be determined at this time, the impacts will be dependent on the facility installed but are anticipated to be a significant annual cost 49 FY 2019-2020 CIP Budget - Proposed Bicycle Plan Implementation Phase 2: SCB – Wolfe Rd to Hwy 85 DESCRIPTION Design and construct a separated bikeway along Stevens Creek Blvd from Wolfe Rd. to HWY 85. . Estimated Project Cost: $1,900,000 Location: Various Locations Funding: Capital Improvement Fund Requesting Dept.: Public Works PROJECT JUSTIFICATION The 2016 Bicycle Transportation Plan identifies improvement needed and priorities to enhance and promote safer bicycle transportation in the City. The number one priority of the Plan was to provide a separated Class IV bicycle lane on Stevens Creek Blvd. This project is the second phase of a multi- phase program to address that priority. OPERATING BUDGET IMPACTS: It is anticipated that separated bike lanes will require additional maintenance to sweep bike lanes clean of debris. This cost will be in addition to normal street sweeping operations and will be included in FY 2021-22 Operating budget. . 50 FY 2019-2020 CIP Budget - Proposed Bicycle Plan Implementation Phase 3: SCB – Hwy 85 to Foothill Expwy DESCRIPTION Design and construct a separated bikeway along Stevens Creek Blvd from HWY 85 to Foothill Expwy. Estimated Project Cost: $2,000,000 Location: Various Locations Funding: Capital Improvement Fund Requesting Dept.: Public Works PROJECT JUSTIFICATION The 2016 Bicycle Transportation Plan identifies improvement needed and priorities to enhance and promote safer bicycle transportation in the City. The number one priority of the Plan was to provide a separated Class IV bicycle lane on Stevens Creek Blvd. This project is the third phase to address that priority. OPERATING BUDGET IMPACTS: It is anticipated that separated bike lanes will require additional maintenance to sweep bike lanes clean of debris. This cost will be in addition to normal street sweeping operations and will be included in FY 2022-23 Operating budget. 51 FY 2019-2020 CIP Budget - Proposed Bicycle Plan Implementation Phase 4: Stevens Creek Blvd @ Stelling Rd DESCRIPTION Design and construct enhanced bike routes (Class III shared bike lanes) that provide neighborhood friendly alternatives parallel to bike network options of major City streets. Estimated Project Cost: $825,000 Location: Various Locations Funding: Capital Improvement Fund Requesting Dept.: Public Works PROJECT JUSTIFICATION The 2016 Bicycle Transportation Plan identifies improvement needed and priorities to enhance and promote safer bicycle transportation in the City. This bike boulevard network supports families and young students wanting to reach schools, parks, and community amenities on quiet streets with low traffic volumes. OPERATING BUDGET IMPACTS: Minimal impacts (e.g. refresh striping every 3-5 years) are anticipated to the Operating Budget. 52 FY 2019-2020 CIP Budget - Proposed Bicycle Plan Implementation Phase 5: Grade Separated Crossing Study – Grand Ave to Mary Ave DESCRIPTION Design and construct enhanced bike routes (Class III shared bike lanes) that provide neighborhood friendly alternatives parallel to bike network options of major City streets. Estimated Project Cost: $450,000 Location: Various Locations Funding: Capital Improvement Requesting Dept.: Public Works PROJECT JUSTIFICATION The 2016 Bicycle Transportation Plan identifies improvement needed and priorities to enhance and promote safer bicycle transportation in the City. This bike boulevard network supports families and young students wanting to reach schools, parks, and community amenities on quiet streets with low traffic volumes. OPERATING BUDGET IMPACTS: Minimal impacts (e.g. refresh striping every 3-5 years) are anticipated to the Operating Budget. 53 FY 2019-2020 CIP Budget - Proposed Blackberry Farm Entrance Road Improvements DESCRIPTION Design and construct a pedestrian, bicycle and vehicle access to Blackberry Park Farm and Stevens Creek Corridor Trail. Estimated Project Cost: $5,500,000* *Program Level estimate only, actual cost will vary depending on option selected. Estimated Project Cost: $5,500,000 Location: Blackberry Farm Funding: Capital Improvement Requesting Dept.: Parks and Recreation PROJECT JUSTIFICATION Current access to Blackberry Farm for bicycles, pedestrians and vehicles is a narrow access road shared by all three groups. This project will fund the design and construction of the preferred alternative identified in the feasibility study. OPERATING BUDGET IMPACTS: Minimal impacts are anticipated to the Operating Budget. 54 FY 2019-2020 CIP Budget - Proposed Blackberry Farm Golf Course Renovation DESCRIPTION Initiate preliminary design effort to completely reconfigure and rebuild the existing golf course per the recommendations made by the National Golf Foundation, Inc. in their report dated December 2015. At a minimum, replace the existing irrigation system with a modern, water-efficient system and repair the two existing ponds. Pursue reactivating the existing well at Blackberry Farm. Estimated Project Cost: $ 1,450,000 Location: BB Farm Golf Course Funding: Capital Improvement Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION The current irrigation system, installed in the 1960s, is functionally outdated and failing due to age, which results in an excessive use of water and labor to maintain the system. The increasing retail cost of water exacerbates the operational inefficiency. Existing ponds no longer hold water. OPERATING BUDGET IMPACTS: As older equipment is replaced with energy efficient equipment and as building systems are upgraded significant, savings are expected in both maintenance and energy costs. 55 FY 2019-2020 CIP Budget - Proposed Blackberry Farm – Play Area Improvements DESCRIPTION Remove existing tan bark and replace with new resilient surfacing and install 3 par course type exercise stations. Estimated Project Cost: $250,000 Location: Blackberry Farm Funding: Capital Improvement Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION The Captain Stevens play area could be enhanced by adding a more reliable and stable resilient play surface beneath the play equipment and by adding exercise stations adjacent to the play area that would provide for a multi-generational activity. OPERATING BUDGET IMPACTS: This project is not expected to impact Operating expenses. 56 FY 2019-2020 CIP Budget - Proposed Blackberry Farm – Splash Pad DESCRIPTION Design and construct a splash pad of approximately 2000 square feet. Estimated Project Cost: $690,000 Location: Blackberry Farm Funding: Capital Improvement Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION Blackberry Farm currently provides aquatic amenities for children and adults, but doesn’t have an element to serve very young children and toddlers. Adding an element that will serve the youngest family members will enhance the attraction of the facility for families with children of various ages. OPERATING BUDGET IMPACTS: This project is expected to have a moderate impact Operating expenses. 57 FY 2019-2020 CIP Budget - Proposed Bicycle Boulevard Phase 1 & 2 Permanent Improvements DESCRIPTION Remove the existing low-cost Bike Boulevard Improvements installed under Phase 1 & 2 with permanent, lower maintenance improvements. enhanced bike routes (Class III shared bike lanes) that provide neighborhood friendly alternatives parallel to bike network options of major City streets. Estimated Project Cost: $3,154,000 Location: Various Locations Funding: Capital Improvement Fund Requesting Dept.: Public Works PROJECT JUSTIFICATION The 2016 Bicycle Transportation Plan identifies improvement needed and priorities to enhance and promote safer bicycle transportation in the City. This bike boulevard network supports families and young students wanting to reach schools, parks, and community amenities on quiet streets with low traffic volumes. This project with replace the existing low-cost, pilot program improvements with a more permanent, more aesthetically pleasing improvements. OPERATING BUDGET IMPACTS: Minimal impacts (e.g. refresh striping every 3-5 years, refresh bark and decomposed granite, replace bollards as necessary) are anticipated to the Operating Budget 58 FY 2019-2020 CIP Budget - Proposed Carmen Road Pedestrian/Bike Bridge Design & Construction DESCRIPTION Design and Construct a pedestrian bridge across Stevens Creek Blvd. for bicycles and pedestrians at Carmen Rd. as identified in the feasibility study. Budgeted Amount: $3,100,000 Location: Carmen Rd. at Stevens Creek Blvd Requesting Dept.: Public Works PROJECT JUSTIFICATION Currently there is no access across Stevens Creek Boulevard for bicycles and pedestrians at Carmen Road. Staff is working on the feasibility study which will identify and evaluate various concepts to create safe access for non-vehicular traffic. Once the feasibility study is completed and City Council has accepted it this project will complete the final design and construction. OPERATING BUDGET IMPACTS: Impacts to the Operating Budget cannot be determined at this time; the impacts will be dependent on the facility installed. 59 FY 2019-2020 CIP Budget - Proposed Citywide Building Condition Assessment Implementation Phase 2 DESCRIPTION Implement recommendations at the Senior Center, Monta Vista Recreation Center and Service Center (Administration and Mechanics shops) identified as a priority in the Comprehensive Facility Condition and Use Assessment. Estimated Project Cost: $2,169,000 Location: Various Locations Funding: Capital Improvement Fund Requesting Dept.: Public Works PROJECT JUSTIFICATION The 2017/18 Comprehensive Facility Condition and Use Assessments project assessed the condition of nearly every City owned facility Senior Center, Monta Vista Recreation Center and Service Center (Administration and Mechanics shops) were identified as high priority facilities with significant deficiencies that need to be addressed to avoid costly repairs and extended service interruptions. OPERATING BUDGET IMPACTS: As older equipment is replaced with energy efficient equipment and as building systems are upgraded significant, savings are expected in both maintenance and energy costs. 60 FY 2019-2020 CIP Budget - Proposed Citywide Building Condition Assessment Implementation Phase 3 DESCRIPTION Implement recommendations at the Quinlan Community Center, Sports Center, Senior Center, Monta Vista Recreation Center, Blackberry Farm McClellan Ranch and Service Center (Welding shops) identified as a priority in the Comprehensive Facility Condition and Use Assessment. . Estimated Project Cost: $1,637,209 Location: Various Funding: Capital Improvement Requesting Dept.: Public Works PROJECT JUSTIFICATION The 2017/18 Comprehensive Facility Condition and Use Assessments project includes a scope of work that will assess the condition of nearly every City owned facility. These assessments, depending on the selected buildings, may include but are not limited to:  Health and life safety systems  Seismic evaluation  Mechanical, electric and plumbing evaluation  ADA compliance  Building envelope evaluation  Energy use efficiency  Space use efficiency Based on results of the assessment facility specific project recommendations will be identified, estimated and prioritized. This project provides a mechanism to initiate those recommendations. OPERATING BUDGET IMPACTS: As older equipment is replaced with energy efficient equipment and as building systems are upgraded significant savings are expected in both maintenance and energy costs. 61 FY 2019-2020 CIP Budget - Proposed Citywide Building Condition Assessment Implementation Phase 4 DESCRIPTION The fourth Phase of a multiphase program to implement recommendations identified in the 2017/18 Comprehensive Facility Condition and Use Assessment. Facilities included in this phase include Quinlan Community Center, Sports Center, Senior Center, Monta Vista Recreation Center, Blackberry Farm McClellan Ranch and Service Center (Welding & Mechanics shops), Memorial Park, Traffic Center and Kennedy Sports Field. Estimated Project Cost: $11,706,626 Location: Various Funding: Capital Improvement Requesting Dept.: Public Works PROJECT JUSTIFICATION The 2017/18 Comprehensive Facility Condition and Use Assessments project includes a scope of work that will assess the condition of nearly every City owned facility. These assessments, depending on the selected buildings, may include but are not limited to:  Health and life safety systems  Seismic evaluation  Mechanical, electric and plumbing evaluation  ADA compliance  Building envelope evaluation  Energy use efficiency  Space use efficiency Based on results of the assessment facility specific project recommendations will be identified, estimated and prioritized. This project provides a mechanism to initiate those recommendations. OPERATING BUDGET IMPACTS: As older equipment is replaced with energy efficient equipment and as building systems are upgraded significant, savings are expected in both maintenance and energy costs. 62 FY 2019-2020 CIP Budget - Proposed Citywide Building Condition Assessment Implementation Phase 5 DESCRIPTION The third Phase of a multiphase program to implement recommendations identified in the 2017/18 Comprehensive Facility Condition and Use Assessment. This project would fund improvements to correct building deficiencies and improvements necessary to keep City owned building functioning properly. Estimated Project Cost: $17,836,491 Location: Various Funding: Capital Improvement Fund Requesting Dept.: Public Works PROJECT JUSTIFICATION The 2017/18 Comprehensive Facility Condition and Use Assessments project includes a scope of work that will assess the condition of nearly every City owned facility. These assessments, depending on the selected buildings, may include but are not limited to:  Health and life safety systems  Seismic evaluation  Mechanical, electric and plumbing evaluation  ADA compliance  Building envelope evaluation  Energy use efficiency  Space use efficiency Based on results of the assessment facility specific project recommendations will be identified, estimated and prioritized. This project provides a mechanism to initiate those recommendations. OPERATING BUDGET IMPACTS: As older equipment is replaced with energy efficient equipment and as building systems are upgraded significant, savings are expected in both maintenance and energy costs. 63 FY 2019-2020 CIP Budget - Proposed Creek Infall/Outfall Restoration DESCRIPTION Reconstruct existing drainage structures adjacent to 22001 Lindy Lane, 10545 Cordova Road and 21710 Regnart Road to prevent debris build-up, flooding and creek erosion during the rainy season. Budgeted Amount: $480,000 (total) Location: Various $160,000 annually for 3 years Requesting Dept.: Public Works PROJECT JUSTIFICATION The existing drainage structures at these three locations are antiquated, poorly protected from floating debris making them susceptible to debris build-up, blockages and potential flooding. This project proposes to rebuild these structures with more effective debris capture devices and improve the outfall structures to reduce erosion and improve hydraulic conditions. OPERATING BUDGET IMPACTS: Unanticipated blockages during storm events require immediate attention to avoid potential flooding and costly repairs. The frequency of these occurrences increases with each storm event requiring a costly response by City Staff. This project proposes to reduce the likelihood of occurrence with improved facilities. 64 FY 2019-2020 CIP Budget - Proposed Creekside Park Improvements DESCRIPTION Identify improvements for the existing Creekside Park, design and construct those improvements Estimated Project Cost: Design = $100,000 Location: Creekside Park Construction: $750,000 Funding: Capital Improvement Fund Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION The City Council reviewed the Cupertino Parks and Recreation System Master Plan in April 2019. The master plan recommended renovating the site as a neighborhood recreation and sports hub. The short-term goals were to sustain existing park uses and evaluate long-term opportunities to expand the recreation building and reactivate or repurpose the concession area. The long term goals were as follows: coordinate with Public Works to implement recreation building recommendations; develop site master plan and evaluate options to increase sports playing capacity; consider artificial turf sport fields; add full basketball court if space allows; add nature play elements to existing play area; provide trailhead amenities; connect via trails and bike lane network to Cupertino High, Wilson Park and Civic Center/Library. OPERATING BUDGET IMPACTS: Impacts to the Operating Budget cannot be determined at this time; the impacts will be dependent on the facility installed. 65 FY 2019-2020 CIP Budget - Proposed De Anza Median Island Landscaping Phase II - Construction DESCRIPTION Design and construct replacement arbor, irrigation and plantings of street medians. This is the second phase of the program and covers the length of De Anza Boulevard between I-280 & Mariani Avenue. Estimated Project Cost: $1,546,500 Location: De Anza Blvd. between Funding: Capital Improvement HWY 280 to Mariani Ave. Requesting Dept.: Public Works PROJECT JUSTIFICATION Cupertino has many mounded median islands, which are difficult to irrigate efficiently. Since the installation of many of the City’s planted median islands, the approach to grading, planting, and maintaining them has changed as the desire to conserve resources has increased. Over that same time, irrigation products and systems have also improved efficiency. In addition, landscape plantings need to be replaced as they age out over time. Projects to renovate the median islands will refresh the plantings and improve the efficiency in the use of water and labor to maintain the systems. OPERATING BUDGET IMPACTS: This project will result in reduced water usage due to drought tolerant planting and more efficient irrigation system. New planting will reduce the need to refresh plantings in the near future, which will result in a maintenance savings for the next 2-3 years. 66 FY 2019-2020 CIP Budget - Proposed Gymnasium Complex DESCRIPTION Design and construct Gymnasium Complex that would provide a multi-generational gymnasium complex and recreation center to provide sports courts spaces and support other activities. Estimated Project Cost: $35,000,000 Location: TBD Funding: Capital Improvement Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION The City Council reviewed the Cupertino Parks and Recreation System Master Plan in April 2019. The master plan included recommendations for the adding of new major facilities to meet community needs at existing park, and a Gymnasium Complex and Multi-Use Recreation Center was identified as one of these facilities. The Gymnasium Complex would provide a multi-generational gymnasium complex and recreation center to provide sports courts spaces and support other activities. Potential locations identified were as follows: Memorial Park, Creekside Park, Jollyman Park, Wilson Park, New site or Public-private partnership or Joint use facility. OPERATING BUDGET IMPACTS: Impacts to the Operating Budget cannot be determined at this time; the impacts will be dependent on the facility installed. 67 FY 2019-2020 CIP Budget - Proposed Healing Garden – Design and Construction DESCRIPTION Design and construct a tranquil, relaxing garden to promote positive outcomes, including stress reduction, are derived through both passive and active nature connection. A “therapeutic garden,” is a garden where physical, occupational, horticultural, and other therapies take place. A “restorative landscape” is any landscape— wild or designed, large or small—that facilitates human health and well-being. Estimated Project Cost: $1,000,000 Location: TBD Funding: Capital Improvement Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION This project promotes the therapeutic benefits of the garden. Access to nature promotes health through reduction in stress, depression, myopia, pain, fatigue, aggression, impulsivity, and symptoms of Attention Deficit Hyperactivity Disorder (ADHD); and improvement in immune function, bone strength, wound healing, cognition, concentration, emotional resilience, empathy, vitality, relaxation, mood, and satisfaction. OPERATING BUDGET IMPACTS: Impacts to the Operating Budget cannot be determined at this time; the impacts will be dependent on the facility installed. 68 FY 2019-2020 CIP Budget - Proposed Jollyman Park Improvements DESCRIPTION Identify improvements for the existing Jollyman Park, design and construct those improvements Estimated Project Cost: Design - $100,000 Location: Jollyman Park Construction - $750,000 Funding: Capital Improvement Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION The City Council reviewed the Cupertino Parks and Recreation System Master Plan in April 2019. The master plan included recommendations for Jollyman Park. The master plan recommended renovating the site as a neighborhood and community hub for recreation programs, activities and sports. The short term goals were as follows: sustain existing park uses; consider adding an all-inclusive, destination play area; add a picnic shelter and group seating; provide all-weather loop path; add neighborhood-serving event infrastructure and utilities. The long-term goals were as follows: consider adding diverse amenities, such as outdoor fitness equipment/par course or full size basketball court; consider development of other new facilities; provide inviting connection to bikeway This project would construct improvements as specified in the Jollyman Park Development Plan. OPERATING BUDGET IMPACTS: Impacts to the Operating Budget cannot be determined at this time; the impacts will be dependent on the facility installed. 69 FY 2019-2020 CIP Budget - Proposed Jollyman Park Pathway Installation DESCRIPTION Design and construct a pathway around the southeastern field at Jollyman Park. Estimated Project Cost $750,000 Location: Jollyman Park Funding: Capital Improvement Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION Currently many visitors to this park walk a circuit around the edges of the southeastern ballfield. Installing a paved path will provide a more stable surface for this activity, greatly increasing the paved walking circuit within the park. OPERATING BUDGET IMPACTS: This project is not expected to impact Operating expenses. 70 FY 2019-2020 CIP Budget - Proposed Junipera Serra Trail Segment #3: Wolfe Rd. to Vallco Pkwy DESCRIPTION Final design and construction of Segment #3 from Wolfe Rd. to Vallco Pkwy. Estimated Project Cost: $1,800,000 Location: Junipera Serra Trail – Wolfe Funding: Capital Improvement Rd.to Vallco Pkwy Requesting Dept.: Public Works PROJECT JUSTIFICATION The 2016 Bicycle Transportation Plan identifies improvement needed and priorities to enhance and promote safer bicycle transportation in the City. The Junipero Serra Trail is one of the trail segments that would make up “The Loop” to provide an off-street bicycle and pedestrian facility that runs parallel to the existing Junipero Serra Channel and Calabazas Creek and would provide a connection between the Don Burnett Bicycle – Pedestrian Bridge and Vallco Parkway when all the sections are completed. Segment #3 - Wolfe Rd. to Vallco Parkway is the first phase of a multi-phase program and is considered to be the lowest cost segment to construct. OPERATING BUDGET IMPACTS: It is anticipated that trails will require additional maintenance however, it is anticipated that these impacts will be minimal. 71 FY 2019-2020 CIP Budget - Proposed Junipera Serra Trail Segment #2: De Anza Blvd to Wolfe Rd. DESCRIPTION Final design and construction of Segment #2 from De Anza Blvd to Wolfe Rd. including a tunnel at De Anza) Estimated Project Cost: Design - $2,600,000 Location: Junipera Serra Trail – Wolfe Construction - $22,200,000 Rd.to Vallco Pkwy Funding: Capital Improvement Fund Requesting Dept.: Public Works PROJECT JUSTIFICATION The 2016 Bicycle Transportation Plan identifies improvement needed and priorities to enhance and promote safer bicycle transportation in the City. The Junipero Serra Trail is one of the trail segments that would make up “The Loop” to provide an off-street bicycle and pedestrian facility that runs parallel to the existing Junipero Serra Channel and Calabazas Creek and would provide a connection between the Don Burnett Bicycle – Pedestrian Bridge and Vallco Parkway when all the sections are completed. Segment #2 – De Anza Blvd to Wolfe Rd. is the second phase of a multi- phase program and is considered to be the highest cost segment to construct if a tunnel under De Anza Blvd is included. OPERATING BUDGET IMPACTS: It is anticipated that trails will require additional maintenance however, it is anticipated that these impacts will be minimal. 72 FY 2019-2020 CIP Budget - Proposed Junipera Serra Trail Segment #1: Don Burnett Bridge to De Anza Blvd. DESCRIPTION Construction of Segment #1 from Don Burnett Bridge to De Anza Blvd. Estimated Project Cost: $3,500,000 Location: Junipera Serra Trail – Don Funding: Capital Improvement Burnett Bridge to De Anza Bl. Requesting Dept.: Public Works PROJECT JUSTIFICATION The 2016 Bicycle Transportation Plan identifies improvement needed and priorities to enhance and promote safer bicycle transportation in the City. The Junipero Serra Trail is one of the trail segments that would make up “The Loop” to provide an off-street bicycle and pedestrian facility that runs parallel to the existing Junipero Serra Channel and Calabazas Creek and would provide a connection between the Don Burnett Bicycle – Pedestrian Bridge and Vallco Parkway when all the sections are completed. This project will construct Segment #1 from Don Burnett Bicycle-Pedestrian Bridge to De Anza Blvd. OPERATING BUDGET IMPACTS: Slight impacts to the Operating Budget are anticipated. Exact impacts depend on the improvements installed. 73 FY 2019-2020 CIP Budget - Proposed Linda Vista Park Improvements DESCRIPTION Identify improvements for the existing Linda Vista Park, design and construct those improvements Estimated Project Cost: Design - $100,000 Location: Linda Vista Park Construction - $750,000 Funding: Capital Improvement Fund Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION The City Council reviewed the Cupertino Parks and Recreation System Master Plan in April 2019. The master plan included recommendations for Linda Vista Park. The master plan recommended renovating the site as a neighborhood and community hub for recreation programs, activities and sports. The short-term goals were as follows: sustain existing park uses; consider adding; add a picnic shelter and group seating; provide all-weather loop path; add neighborhood-serving event infrastructure and utilities. The long-term goals were as follows: consider adding diverse amenities, such as outdoor fitness equipment/par course or full size basketball court; consider development of other new facilities; provide inviting connection to bikeway and reconstructing the fountains. This project would construct improvements as specified in the Linda Vista Park Development Plan. OPERATING BUDGET IMPACTS: Impacts to the Operating Budget cannot be determined at this time; the impacts will be dependent on the facility installed. 74 FY 2019-2020 CIP Budget - Proposed Mary Avenue Trail and Greenbelt DESCRIPTION Create a linear park-like greenbelt with separated bikeway and pedestrian path. Improvements include use of pervious pavement, PCB reduction by use of bio swale, infiltration Estimated Project Cost: $6,170,000 Location: Mary Avenue Requesting Dept.: Public Works PROJECT JUSTIFICATION This project is considered a top tier, Tier One priority in the Pedestrian Transportation Plan adopted in February 2018. This would be the City’s first complete or green street and would show progress toward meeting Municipal Regional Stormwater NPDES permit requirements. OPERATING BUDGET IMPACTS: Impacts to the Operating Budget cannot be determined at this time; the impacts will be dependent on the facility installed 75 FY 2019-2020 CIP Budget - Proposed McClellan Ranch – Construct Trash Enclosure (Design Complete) DESCRIPTION Screen the existing trash/debris boxes from McClellan Road. This would include a concrete pad for the boxes. Estimated Project Cost: $100,000 Location: McClellan Ranch Preserve Funding: Capital Improvement Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION Currently the trash containers are in the open, visible from McClellan Road, and attract illegal dumping. Screening the trash containers will help discourage illegal dumping at McClellan Ranch Preserve. OPERATING BUDGET IMPACTS: There are no anticipated impacts to the Operating Budget. 76 FY 2019-2020 CIP Budget - Proposed McClellan Ranch – Barn Renovation DESCRIPTION Design and construct improvements to renovate the barn into an educational and public space. Estimated Project Cost: $3,250,000 Location: McClellan Ranch Preserve Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION In 2012, an update to the 1993 master plan for the McClellan Ranch was completed, which lays out priorities for implementing programs and the related improvements at the park. In the FY 2013 budget, Council approved funding for the barn to be evaluated historically and structurally and for a conceptual renovation plan to be developed to meet the goals for the barn as listed in the master plan. The outcome of this project produced a conceptual renovation plan for the barn to be used for education and as an agricultural exhibit space open to the public. OPERATING BUDGET IMPACTS: Impacts to the Operating Budget cannot be determined at this time; the impacts will be dependent on the facility installed. 77 FY 2019-2020 CIP Budget - Proposed McClellan Ranch Preserve Stevens Creek Access DESCRIPTION Design and construct an accessible access to the creek. Estimated Project Cost: $750,000 Location: McClellan Ranch Funding: Capital Improvement Preserve Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION Design and construct an accessible access to the creek along Stevens Creek in McClellan Ranch Preserve to be able to offer as a learning experience. OPERATING BUDGET IMPACTS: There are no anticipated impacts to the Operating Budget. 78 FY 2019-2020 CIP Budget - Proposed McClellan Road Bridge Replacement @ Stevens Creek DESCRIPTION Design and construct a replacement bridge on McClellan Rd. over Stevens Creek. Estimated Project Cost: $6,000,000 Location: McClellan Road at Funding: SB 1 Eligible $4,800,000 Stevens Creek Capital Improvement $1,200,000 Requesting Dept.: Public Works PROJECT JUSTIFICATION This bridge provides a critical east-west transportation link for Cupertino residents. Constructed in 1920 and widened in 1976, the structural capacity and seismic resiliency of this bridge is unknown. As a precautionary measure, weight restrictions have been applied to this bridge. Replacement of this bridge would provide numerous benefits including increased structural strength, seismic resiliency, potential widening and realignment and the opportunity to provide a pedestrian / bicycle crossing under McClellan Road thereby increasing overall safety at this location. This project is eligible for SB 1 funding. OPERATING BUDGET IMPACTS: There are no anticipated impacts to the Operating Budget. 79 FY 2019-2020 CIP Budget - Proposed Memorial Park – Tennis Court Restroom Replacement DESCRIPTION Design and construct a new restroom. Estimated Project Cost: $625,000 Location: Memorial Park Funding: Capital Improvement Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION The public restroom near the Memorial Park Tennis Courts needs upgrading for improved performance and to improve accessibility. OPERATING BUDGET IMPACTS: There are no anticipated impacts to the Operating Budget. 80 FY 2019-2020 CIP Budget - Proposed Memorial Park Phase 1 – Pond Removal DESCRIPTION This project will remove of the existing concrete pond and return the site to a naturalized state. Estimated Project Cost: $1,500,000 Location: Memorial Park Funding: Capital Improvement Requesting Dept.: Public Works PROJECT JUSTIFICATION The existing concrete liner is in poor condition with numerous cracks that resulted in significant water loss. Due to this condition and drought restrictions the City drained the ponds in 2013 and has not refilled them. Reconstruction of the ponds is not cost effective and empty ponds pose a potential safety hazard. This project would remove the ponds and prepare the site for future development as identified through the Memorial Park Master Plan. OPERATING BUDGET IMPACTS: A slight impact to the Operating Budget is anticipated. The exact extent of the impact will depend on the nature and extent of the naturalization improvements installed. 81 FY 2019-2020 CIP Budget - Proposed Memorial Park Phase 2 Improvements DESCRIPTION Design and construct Memorial Park Phase 2 improvement as shown in the Memorial Park Master Plan & Parking Study. Estimated Project Cost: Design - $350,000 Location: Memorial Park Construction - $2,500,000 Funding: Capital Improvement Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION The City Council reviewed the Cupertino Parks and Recreation System Master Plan in April 2019. The master plan included recommendations for Memorial Park. The master plan recommended enhancing the site as a community hub and multi-use civic-focused event space. In FY2018 CIP, the Memorial Park Master Plan & Parking Study was funded. OPERATING BUDGET IMPACTS: Impacts to the Operating Budget cannot be determined at this time; the impacts will be dependent on the facility installed. 82 FY 2019-2020 CIP Budget - Proposed Memorial Park Phase 3 Improvements DESCRIPTION Construct Memorial Park Phase 3 improvement as shown in the Memorial Park Master Plan & Parking Study. Estimated Project Cost: Design - $350,000 Location: Memorial Park Construction - $2,425,000 Funding: Capital Improvement Fund Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION The City Council reviewed the Cupertino Parks and Recreation System Master Plan in April 2019. The master plan included recommendations for Memorial Park. The master plan recommended enhancing the site as a community hub and multi-use civic-focused event space. In FY2018 CIP, the Memorial Park Master Plan & Parking Study was funded. OPERATING BUDGET IMPACTS: Impacts to the Operating Budget cannot be determined at this time; the impacts will be dependent on the facility installed. 83 FY 2019-2020 CIP Budget - Proposed McClellan Ranch Preserve Community Garden Improvements – Construction DESCRIPTION Reconstruct the existing community garden based on the design developed in FY 2017-18. The project includes reconfiguration of the garden plots, improved ADA accessibility to and within the garden, installation of new perimeter fencing, irrigation distribution system and informal meeting area. Estimated Project Cost: $1,500,000 Location: McClellan Funding: Capital Improvement $575,000 Ranch Preserve Parkland Dedication $925,000 Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION This project will implement the approved conceptual design for the McClellan Ranch Community Garden Improvements project. The goals of this project are to increase the number of garden plots thereby reducing the number of residents on the waiting list, improve ADA accessibility, improve the water distribution system throughout the garden, increase the aesthetics and sense of community and provide increased protection from non-beneficial wildlife. OPERATING BUDGET IMPACTS: An improved water distribution system should result in an overall water usage reduction. Improved fencing and more efficient garden configuration should reduce the need for additional pest control. Additional plots and a renewed emphasis on proactive management will require additional staff commitment. The staff time is included in the operating budget. 84 FY 2019-2020 CIP Budget - Proposed McClellan Ranch Preserve EEC Aquatic Habitat DESCRIPTION Construction of an outdoor aquatic habitat for turtles, fish and other species adjacent to the Environmental Education Center (EEC). This habitat will be used as an outdoor education center for schools visiting the EEC. Estimated Project Cost: 175,000 Location: McClellan Ranch Preserve Funding: Capital Improvement Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION This project would create an outdoor habitat and classroom providing for a more natural environment for the turtles, fish, etc. and more space to conduct classroom-sized presentations. The facility would be ADA accessible, consistent with the McClellan Ranch environment and from other animals. OPERATING BUDGET IMPACTS: Care and operation of the aquatic habitat will be the responsibility of existing McClellan Ranch staff and supported by part-time staff. No additional staff is required. Maintenance of the pond pumps and filters would need to cleaned and replaced periodically. Estimated annual expense is less than $1,000 annually. 85 FY 2019-2020 CIP Budget - Proposed New Neighborhood Parks DESCRIPTION Identify sites and develop a procurement plan to meet the recommendations in the master plan. Acquire and develop new neighborhood parks in accordance with the Master Plan Estimated Project Cost: Design - $150,000 Location: City Wide Land Acquisition & Construction - $20,000,000 ($4,000,000 annually) Funding: Capital Improvement Fund Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION The City Council reviewed the Cupertino Parks and Recreation System Master Plan in April 2019. The master plan included recommendations for the adding of new major facilities to meet community needs at existing park, and new acquisitions. The Master plan recommended the City look for opportunities should they arise, acquire and develop new neighborhood parks in targeted underserved areas was recommended. Potential area locations include new acquisition in north and east Cupertino, joint-use sites at schools and public-private partnerships. This project will provide a funding mechanism to identify and acquire new park/open space. OPERATING BUDGET IMPACTS: Impacts to the Operating Budget cannot be determined at this time, Operating impacts are anticipated to increase as additional parkland is acquired and developed. 86 FY 2019-2020 CIP Budget - Proposed Performing Arts Center DESCRIPTION Design and construct a Performing Arts Center to include a community auditorium or fine and performing arts center to house community-sale performances and support daytime art and recreation programs as well as evening programs. Estimated Project Cost: $77,000,000 Location: TBD Funding: Capital Improvement Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION The City Council reviewed the Cupertino Parks and Recreation System Master Plan in April 2019. The master plan included recommendations for the adding of new major facilities to meet community needs at existing park, and a Performing & Fine Arts Center was identified as one of these facilities. The Preforming Arts Center would provide for a community auditorium or fine and performing arts center to house community-scale performances and support daytime arts and recreation programs as well as evening programs. The Master Plan identified the following potential locations: Memorial Park, Civic Center/Library Field, New Site, Public-private partnership or other/repurpose building or a joint use facility. OPERATING BUDGET IMPACTS: Impacts to the Operating Budget cannot be determined at this time, the impacts will be dependent on the facility installed and the operating model selected (i.e. City operated or 3rd party vendor) 87 FY 2019-2020 CIP Budget - Proposed Portal Park Improvements DESCRIPTION Design and construct improvements identified in the Portal Park Development Plan. Estimated Project Cost: Design - $75,000 Location: Portal Park Construction - $750,000 Funding: Capital Improvement Fund Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION Portal Park has some facilities from the original construction in the 1960s that can no longer be used as intended. Areas of the park are underutilized for this reason. A process to obtain community input and consensus will inform future plans to renovate portions of the park. Once identified the improvements will be designed and constructed through an additional appropriation. OPERATING BUDGET IMPACTS: Impacts to the Operating Budget cannot be determined at this time, the impacts will be dependent on the facility installed. 88 FY 2019-2020 CIP Budget - Proposed Quinlan Front Office Upgrades DESCRIPTION Design and construct improvement to the front office to accommodate operational changes and provide better customer service. Estimated Project Cost: $700,000 Location: City Wide Funding: Capital Improvement Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION The new registration system comes with improvements that create a need for staff to be sitting at the customer counter. PCI compliance has created a need for more storage in the office. Project would include a complete reconfiguration of the front office to allow for better customer service and new program needs. OPERATING BUDGET IMPACTS: There are no anticipated impacts to the Operating Budget. 89 FY 2019-2020 CIP Budget - Proposed Quinlan HVAC Upgrades DESCRIPTION Design and construct a multi-zone HVAC system upgrade. Estimated Project Cost: $1,000,000 Location: City Wide Funding: Capital Improvement Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION The HVAC system at Quinlan is original with the building in 1990. Temperature does not stay regulated throughout the building. The temperature does not stay regulated day to day. Public Works has looked at the unit and the temperature issues over and over to no avail. Building temperatures are either too cool or too warm, are not consistent within a single conditioned area, and are not efficient. OPERATING BUDGET IMPACTS: As older equipment is replaced with energy efficient equipment and as building systems are upgraded significant, savings are expected in both maintenance and energy costs. 90 FY 2019-2020 CIP Budget - Proposed Recreation Facilities Monument Signs DESCRIPTION Design and construct new monument signs with lighting at the following locations: McClellan Ranch Preserve McClellan Ranch West Estimated Project Cost: $200,000 Location: Various Funding: Capital Improvement Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION Council approved the McClellan Ranch Preserve and Stevens Creek Corridor Signage Program in December 2014. The Signage Program prescribes a standardized and consistent look and feel for all signage along Stevens Creek. The Signage Program provides a signage convention that can be applied to other recreation facilities in the city. The existing monument signs at several city facilities are outdated, worn, and in need of repair. This project will install new monument signs at McClellan Ranch Preserve and McClellan Ranch West. OPERATING BUDGET IMPACTS: There are no anticipated impacts to the Operating Budget. 91 FY 2019-2020 CIP Budget - Proposed Regnart Road Improvements Phase 2: Sta 36+30 to 36+80 (Retaining Wall) DESCRIPTION Phase 2 will construct a retaining wall to stabilize the road slope to the creek from Sta 36+30 to 36+80 (approx. 50 LF). Estimated Project Cost: $800,000 Location: Regnart Road Funding: Capital Improvement Requesting Dept.: Public Works PROJECT JUSTIFICATION This project continues the stabilization efforts along Regnart Road and compliments the 2017 Outfall Repair and Slope Stabilization project and the Retaining wall project. The 2017 Regnart Road Slope Stability Study identified several areas along Regnart Road that exhibit poor drainage characteristics, slope stability concerns that require partial road reconstruction in order to avoid costly road or slope failures and lengthy road closures. Proposed improvements include additional drainage structures, regrading/repaving the road to drain towards the creek, slope stabilization and erosion control measures and retaining walls. This is Phase 2 of 6. OPERATING BUDGET IMPACTS: This project should minimize or prevent costly emergency responses by maintenance crews resulting in a savings to the operating budget. 92 FY 2019-2020 CIP Budget - Proposed Regnart Road Improvements Phase 3: Sta 23+35 to 23+50 (Culvert/Outfall Replacement) DESCRIPTION Phase 3 will replace a culvert/outfall to stabilize the road slope to the creek from Sta 23+35 to 23+50. Estimated Project Cost: $925,000 Location: Regnart Road Funding: Capital Improvement Requesting Dept.: Public Works PROJECT JUSTIFICATION This project continues the stabilization efforts along Regnart Road and compliments the 2017 Outfall Repair and Slope Stabilization project and the Retaining wall project. The 2017 Regnart Road Slope Stability Study identified several areas along Regnart Road that exhibit poor drainage characteristics, slope stability concerns that require partial road reconstruction in order to avoid costly road or slope failures and lengthy road closures. Proposed improvements include additional drainage structures, regrading/repaving the road to drain towards the creek, slope stabilization and erosion control measures and retaining walls. This is Phase 3 of a 6-phase program. OPERATING BUDGET IMPACTS: This project should minimize or prevent costly emergency responses by maintenance crews resulting in a savings to the operating budget. 93 FY 2019-2020 CIP Budget - Proposed Regnart Road Improvements Phase 4: Sta 7+15 to 7+40 (Retaining Wall) DESCRIPTION Phase 4 will construct a retaining wall to stabilize the road slope to the creek from Sta 7+15 to 7+40 (approx. 25LF). Estimated Project Cost: $700,000 Location: Regnart Road Funding: Capital Improvement Requesting Dept.: Public Works PROJECT JUSTIFICATION This project continues the stabilization efforts along Regnart Road and compliments the 2017 Outfall Repair and Slope Stabilization project and the Retaining wall project. The 2017 Regnart Road Slope Stability Study identified several areas along Regnart Road that exhibit poor drainage characteristics, slope stability concerns that require partial road reconstruction in order to avoid costly road or slope failures and lengthy road closures. Proposed improvements include additional drainage structures, regrading/repaving the road to drain towards the creek, slope stabilization and erosion control measures and retaining walls. This is Phase 4 of a 6-phase program. OPERATING BUDGET IMPACTS: This project should minimize or prevent costly emergency responses by maintenance crews resulting in a savings to the operating budget. 94 FY 2019-2020 CIP Budget - Proposed Regnart Road Improvements Phase 5: Sta 38+95 to 39+40 (Retaining Wall) DESCRIPTION Phase 5 will construct a retaining wall to stabilize the road slope to the creek from Sta 38+95 to 39+40 (approx. 45LF). Estimated Project Cost: $825,000 Location: Regnart Road Funding: Capital Improvement Requesting Dept.: Public Works PROJECT JUSTIFICATION This project continues the stabilization efforts along Regnart Road and compliments the 2017 Outfall Repair and Slope Stabilization project and the Retaining wall project. The 2017 Regnart Road Slope Stability Study identified several areas along Regnart Road that exhibit poor drainage characteristics, slope stability concerns that require partial road reconstruction in order to avoid costly road or slope failures and lengthy road closures. Proposed improvements include additional drainage structures, regrading/repaving the road to drain towards the creek, slope stabilization and erosion control measures and retaining walls. This is Phase 5 of a 6-phase program. OPERATING BUDGET IMPACTS: This project should minimize or prevent costly emergency responses by maintenance crews resulting in a savings to the operating budget. 95 FY 2019-2020 CIP Budget - Proposed Regnart Road Improvements Phase 6: Various Locations (Uphill Side Retaining Wall) DESCRIPTION Phase 6 will construct a retaining wall to stabilize the road on the uphill side of the road. Estimated Project Cost: $250,000 Location: Regnart Road Funding: Capital Improvement Requesting Dept.: Public Works PROJECT JUSTIFICATION This project continues the stabilization efforts along Regnart Road and compliments the 2017 Outfall Repair and Slope Stabilization project and the Retaining wall project. The 2017 Regnart Road Slope Stability Study identified several areas along Regnart Road that exhibit poor drainage characteristics, slope stability concerns that require partial road reconstruction in order to avoid costly road or slope failures and lengthy road closures. Proposed improvements include additional drainage structures, regrading/repaving the road to drain towards the creek, slope stabilization and erosion control measures and retaining walls. This is anticipated to be the final phase of the improvement program for Regnart Road. OPERATING BUDGET IMPACTS: This project should minimize or prevent costly emergency responses by maintenance crews resulting in a savings to the operating budget. 96 FY 2019-2020 CIP Budget - Proposed Retaining Wall Repair – Cordova Road DESCRIPTION Design and construct a project to replace the existing wood planks in the existing wall. Estimated Project Cost: $350,000 Location: West side of Cordova Road, Funding: Capital Improvement north of San Juan Road Requesting Dept.: Public Works PROJECT JUSTIFICATION There is an existing wall along Cordova Rd. that retains soil adjacent to private property. The existing retaining wall is showing signs of deferred maintenance and potential premature failure. This project will replace the wood planks (ie lagging) in the wall and extend the useful life of the wall. OPERATING BUDGET IMPACTS: This project should minimize or prevent costly emergency responses by maintenance crews resulting in a savings to the operating budget. 97 FY 2019-2020 CIP Budget - Proposed Senior Center Expansion DESCRIPTION Design and construct an expansion to the existing Senior Center to provide additional recreation space for older adults, and both fit and frail seniors. Estimated Project Cost: $25,000,000 Location: Senior Center Funding: Capital Improvement Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION The City Council reviewed the Cupertino Parks and Recreation System Master Plan in April 2019. The master plan included recommendations for expanding and/or adding of new major facilities to meet community needs at existing park, expanding services to provide space for seniors and teens was identified as one of these facilities. The master plan included space for seniors and teens, this project would provide additional recreation space for older adults, and both fit and frail seniors. The master plan considered expanding the Senior Center for increased senior population. OPERATING BUDGET IMPACTS: Impacts to the Operating Budget cannot be determined at this time; the impacts will be dependent on the facility installed. 98 FY 2019-2020 CIP Budget - Proposed Service Center – Replacement Administration Building with EOC DESCRIPTION Design and construction of a new administration building at the Service Center Improvements include an EOC, modest future growth of Service Center staffing and up to ten staff from City Hall. Estimated Project Cost: $16,000,000 Location: Service Center Funding: Capital Improvement Requesting Dept.: Public Works PROJECT JUSTIFICATION The current Service Center Administration building, built in the late 1970’s, is inadequate for meeting current staffing levels. A new administration building will provide adequate, efficient office, meeting, and training space for city staff and an EOC, in a structurally compliant building. A feasibility study completed in spring 2017 provides design options and cost estimates for building a new administration/EOC building at the Service Center. The estimated all-inclusive project cost for the proposed conceptual plan is approximately $16 million. OPERATING BUDGET IMPACTS: It is anticipated that Operating expenses would increase slightly. Operational expenses would increase with the increased square footage of the building but will be offset by the energy efficiency’s of the new equipment. Maintenance costs are expected to be reduced as emergency repairs are replaced by preventative maintenance efforts. 99 FY 2019-2020 CIP Budget - Proposed Service Center Shed No. 3 Improvements DESCRIPTION Design and construct a replacement for the existing Shed 3 to accommodate the landscape material and organic waste storage requirements, including durable walls and canopy and comply with current stormwater pollution prevention requirements. Estimated Project Cost: $1,700,000 Location: Service Center Funding: Capital Improvement Requesting Dept.: Public Works PROJECT JUSTIFICATION Currently, loose landscape materials and waste are stored at the Service Center in outdoor, covered, material storage bays at Shed No. 3. As part of the City’s increasing waste diversion efforts, it now collects different types of organics from its sites to recycle, including food scraps. The existing material bays need to be reconfigured to accommodate the increasing demand for separate storage bays. This project was bid in January 2018 and proposals exceeded the available budget. This proposal will augment the existing budget and allow for a redesign of the project to a more cost effective solution. OPERATING BUDGET IMPACTS: This project will increase waste diversion opportunities and create efficiencies in the collection process. It is anticipated that these efficiencies will result in a net zero increase in the FY 2018-19 Operating Budget. 100 FY 2019-2020 CIP Budget - Proposed Sports Center – Interior Upgrades DESCRIPTION Design and implement the following, as available funding permits: 1) renovate the second floor restrooms; 2) renovate the women’s locker room and shower; 3) renovate the men’s locker room and shower; 4) renovate the front lobby counter. Estimated Project Cost: $1,548,700 Location: Sports Center Funding: Capital Improvement Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION The last major upgrades to the building were in 2004 and the facility is in need of some minor upgrades, due to wear-&-tear and weathering. These improvements will improve user experience and attract new users. This project will continue the modernization program and increase the attractiveness of the facility. OPERATING BUDGET IMPACTS: The Sports Center is requiring increased maintenance as the facility ages and improvements wear out. The renovation of these four areas will result in fewer maintenance calls and no net increase to the Operating Budget. 101 FY 2019-2020 CIP Budget - Proposed Sports Center HVAC Upgrades DESCRIPTION Replace the existing HVAC units with new, energy efficient units with increased cooling capacity. Estimated Project Cost $500,000 Location: Sports Center Funding: Capital Improvement Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION The current HVAC units were installed for a customer base of 600; the current customer base is 2000. The amount of classes and fitness equipment in the building have quadrupled since the remodel in 2004. Staff have received multiple complaints from patrons due to facility temperatures that are either too cold or too hot. The current units are under capacity to meet the current demand. In addition, the existing units have reached the end of their useful life and need constant maintenance and repairs, which include calling in outside contractors to trouble shoot. OPERATING BUDGET IMPACTS: As older equipment is replaced with energy efficient equipment and as building systems are upgraded significant savings are expected in both maintenance and energy costs. 102 FY 2019-2020 CIP Budget - Proposed Stevens Creek Bank Repair – South of SCB – Design & Construction DESCRIPTION Prepare a conceptual design for repairs to creek banks that will protect property from further erosion and stabilize the bank, and is compatible with existing goals and requirements for the creek corridor. Budgeted Amount: $1,600,000 Location: Stevens Creek South of Funding: Capital Improvement Stevens Creek Boulevard Requesting Dept.: Rec. and Comm. Services PROJECT JUSTIFICATION In 2014, the City purchased a residential parcel (Blesch) on Stevens Creek Boulevard that lies between the Stocklmeir site and the Blackberry Farm Golf Course. The creek channel upstream of this parcel has been widened and restored. However, this parcel, which is in the active floodway and subject to bank erosion, remains to be stabilized and restored. This parcel is targeted for improvements relating to the park and recreation purposes of the Stevens Creek Corridor. Its bank should be stabilized before such improvements move forward in order to protect the City’s investment. A conceptual plan for improvement of the bank and channel will make the implementation of the project more eligible and attractive for potential grant funding. OPERATING BUDGET IMPACTS: There are no anticipated impacts to the Operating Budget. 103 FY 2019-2020 CIP Budget - Proposed Stevens Creek Trail & Bridge over UPRR (De Anza Trail) DESCRIPTION Acquire necessary easement, permits, and agreements, and, design and construct a vehicle/pedestrian/bicycle bridge span over the UPRR right of way, adjacent to Stevens Creek Blvd. and near the Lehigh Cement Plant. Budgeted Amount: $18,000,000 Location: Stevens Creek Blvd. Requesting Dept.: Public Works at UPRR PROJECT JUSTIFICATION Provide a connection with the Stevens Creek Trail system and vehicle access to the Snyder- Hammond House. This project is included in the City’s adopted Bicycle Transportation Plan. OPERATING BUDGET IMPACTS: There are no anticipated impacts to the Operating Budget. 104 FY 2019-2020 CIP Budget - Proposed Stocklmeir Legacy Farm – Phase 1 Improvements DESCRIPTION Develop a service program and master plan for a legacy farm park, and implement an initial improvement project. Estimated Project Cost: $400,000 Location: Stocklmeir Funding: Capital Improvement Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION Transition the former Stocklmeir property to a public park as a “legacy farm”. OPERATING BUDGET IMPACTS: Impacts to the Operating Budget cannot be determined at this time; the impacts will be dependent on the facility installed. 105 FY 2019-2020 CIP Budget - Proposed Stocklmeir House – New Sewer Lateral DESCRIPTION Install a new sewer lateral to connect the Stocklmeir House to the City’s sanitary sewer main. Estimated Project Cost: $100,000 Location: Stocklmeir Funding: Capital Improvement Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION This is the first step towards renovating this house and making it suitable for future non-residential use and occupancy. OPERATING BUDGET IMPACTS: There are no anticipated impacts to the Operating Budget. 106 FY 2019-2020 CIP Budget - Proposed Storm Drain Improvements Phase 1 (Pumpkin Dr & Cranberry Dr) DESCRIPTION Design and construct storm drain improvements at high priority locations identified in the updated Storm Drain Master Plan. The goal of the improvements is to minimize the potential for localized flooding of streets and private property. Estimated Project Cost: $714,375 Location: Various locations Funding: Storm Drain Improvement Requesting Dept.: Public Works PROJECT JUSTIFICATION City Council accepted the Storm Drain Master Plan on Jan. 15, 2019. The Storm Drain Master Plan identified and prioritized storm drain improvement projects. This project will fund implementation of the initial priorities (Pumpkin Fiesta – Phase 1). Phase 1 will increase the size of the pipes downstream of the railroad crossing. OPERATING BUDGET IMPACTS: This project has no increase in operating budget expenses. A net savings may result over time if the potential for localized flooding is reduced requiring reduced storm related responses by maintenance staff. 107 FY 2019-2020 CIP Budget - Proposed Storm Drain Improvements Phase 2 (Pumpkin Dr: Bubb to November) DESCRIPTION Design and construct storm drain improvements at high priority locations identified in the updated Storm Drain Master Plan. The goal of the improvements is to minimize the potential for localized flooding of streets and private property. Estimated Project Cost: $2,103,000 Location: Various locations Funding: Storm Drain Improvement Requesting Dept.: Public Works PROJECT JUSTIFICATION City Council accepted the Storm Drain Master Plan on Jan. 15, 2019. The Storm Drain Master Plan identified and prioritized storm drain improvement projects. This project will fund implementation of the initial priorities (Pumpkin Fiesta – Phase 2). Phase 2 will install new piping that would connect Bubb to Pumpkin and upsize piping under Pumpkin to the railroad. New 3-ft piping would be installed under the railroad tracks. OPERATING BUDGET IMPACTS: This project has no increase in operating budget expenses. A net savings may result over time if the potential for localized flooding is reduced requiring reduced storm related responses by maintenance staff. 108 FY 2019-2020 CIP Budget - Proposed Storm Drain Improvements Phase 3 (Bubb Rd: Columbus to Monrovia St) DESCRIPTION Design and construct storm drain improvements at high priority locations identified in the updated Storm Drain Master Plan. The goal of the improvements is to minimize the potential for localized flooding of streets and private property. Estimated Project Cost: $273,000 Location: Various locations Funding: Storm Drain Improvement Requesting Dept.: Public Works PROJECT JUSTIFICATION City Council accepted the Storm Drain Master Plan on Jan. 15, 2019. The Storm Drain Master Plan identified and prioritized storm drain improvement projects. This project will fund implementation of the initial priorities (Bubb – Phase 1). Phase 1 will add a 42” pipe to connect the storm drain system under Bubb to the system under Columbus. This will eliminate flooding at the southern- most manhole on Bubb. OPERATING BUDGET IMPACTS: This project has no increase in operating budget expenses. A net savings may result over time if the potential for localized flooding is reduced requiring reduced storm related responses by maintenance staff. 109 FY 2019-2020 CIP Budget - Proposed Storm Drain Improvements Phase 4 (McClellan Rd: Bubb Rd to September Dr) DESCRIPTION Design and construct storm drain improvements at high priority locations identified in the updated Storm Drain Master Plan. The goal of the improvements is to minimize the potential for localized flooding of streets and private property. Estimated Project Cost $711,500 Location: Various locations Funding: Storm Drain Improvement Requesting Dept.: Public Works PROJECT JUSTIFICATION City Council accepted the Storm Drain Master Plan on Jan. 15, 2019. The Storm Drain Master Plan identified and prioritized storm drain improvement projects. This project will fund implementation of the initial priorities (Bubb – Phase 2). Phase 2 will upsize the northern parallel pipe under McClellan after Phase 1 is complete. It will also upsize the pipe along McClellan from Bubb to September. OPERATING BUDGET IMPACTS: This project has no increase in operating budget expenses. A net savings may result over time if the potential for localized flooding is reduced requiring reduced storm related responses by maintenance staff. 110 FY 2019-2020 CIP Budget - Proposed Storm Drain Improvements Phase 5 (Bubb Rd: Monrovia St to Results Way) DESCRIPTION Design and construct storm drain improvements at high priority locations identified in the updated Storm Drain Master Plan. The goal of the improvements is to minimize the potential for localized flooding of streets and private property. Estimated Project Cost: $2,477,000 Location: Various locations Funding: Storm Drain Improvement Requesting Dept.: Public Works PROJECT JUSTIFICATION City Council accepted the Storm Drain Master Plan on Jan. 15, 2019. The Storm Drain Master Plan identified and prioritized storm drain improvement projects. This project will fund implementation of the initial priorities (Bubb – Phase 3). Phase 3 will upsize the pipes under Bubb from between 12- inch and 27-inch to 18-inch and 48-inch. OPERATING BUDGET IMPACTS: This project has no increase in operating budget expenses. A net savings may result over time if the potential for localized flooding is reduced requiring reduced storm related responses by maintenance staff. 111 FY 2019-2020 CIP Budget - Proposed Wilson Park Improvements DESCRIPTION Identify improvements for the renovation of the east side of Wilson Park. Prepare final design and construction documents and construct improvements. Estimated Project Cost: Design - $75,000 Location: Wilson Park Construction - $750,000 Funding: Capital Improvement Fund Requesting Dept.: Parks & Rec. PROJECT JUSTIFICATION Wilson Park has sport fields on the west side of the park and the east side of the park is potentially underutilized. A process to obtain community input and consensus will assist in formulating a plan to renovate portions of the park. OPERATING BUDGET IMPACTS: This project is not expected to impact Operating expenses. 112 FY 2019-2020 CIP Budget - Proposed