B-2018-0463InspectionRecordINSPECTION RECORD
CITY HALL
10300 Torre Avenue • Cupertino, CA 95014-3255
PHONE 408-777-3228
WWW.CUPERTINO.ORG
BUILDING ADDRESS: 19751 BIXBY DR CUPERTINO, CA 95014-3324
CUPERTINO APN: 369 09 049 PERMIT NO: B-2018-0463
OWNER'S NAME: Huang Chris Chen And Wu Xian Feng Sharon Tr OWNER'S PHONE: 408-666-3382
CONTRACTOR: NO LICENSE INFO,CONTRACTOR PHONE:
DATE ISSUED 7/13/2020 11:09:29 AM ISSUED BY:VALUATION: $300000
JOB DESCRIPTION
FIRST FLOOR ADDITION (888 SF); REMODEL OTHER (1350 SF); ELEC PANEL UPGRADE (200 AMP); (N) TANK-LESS WATER HEATER. REV # 1 - REMOVE FIREPLACE FROM LIVING ROOM,
EXTEND (N) FOOTING AND REPLACE FLOOR FRAMING IN FAMILY RM AND MASTER BATHROOM; RELOCATE AND INSTALL (N) FURNACE; REMOVE TANK-LESS WATER HEATER FROM
SCOPE (EXISTING TO REMAIN) - ISSUED 06/14/2019
INSPECTION TYPE DATE STATUS INSPECTOR
FOUNDATION 2019-05-28 Partial
UNDERFLOOR FRAMING 2019-06-19 Partial
ROOF NAIL 2019-08-09 Failed LARRY SQUARCIA
EXTERIOR SHEAR 2019-08-09 Passed LARRY SQUARCIA
ROOF NAIL 2019-08-15 Passed James Lee
INTERIOR LATH 2019-10-03 Cancelled Jeff Greef
EXTERIOR LATH 2019-10-03 Passed Jeff Greef
FIRE DEPT - SPRINKLERS - ROUGH 2019-10-25 Passed Santa Clara County Fire
ROUGH FRAME 2019-10-29 Failed Jeff Greef
ROUGH ELECTRICAL 2019-10-29 Failed Jeff Greef
ROUGH MECHANICAL 2019-10-29 Failed Jeff Greef
ROUGH PLUMBING 2019-10-29 Passed Jeff Greef
ROUGH FRAME 2019-11-07 Passed Jeff Greef
INSULATION 2019-11-07 Passed Jeff Greef
ROUGH MECHANICAL 2019-11-07 Passed Jeff Greef
UNDERFLOOR INSULATION 2019-11-07 Passed Jeff Greef
ROUGH ELECTRICAL 2019-11-07 Failed Jeff Greef
UNDERGROUND SEWER 2019-11-13 Passed James Lee
INTERIOR LATH 2019-11-19 Passed James Lee
SHEETROCK 2019-11-19 Passed James Lee
SANITARY - VISUAL 2019-11-13 Passed cupsanitary
PROPERTY LINE CLEANOUT 2019-11-13 Passed James Lee
ROUGH ELECTRICAL 2019-11-19 Passed James Lee
GAS TEST 2019-11-19 Passed James Lee
SCRATCH COAT 2019-12-03 Passed Jeff Greef
FIRE DEPT - FINAL 2020-03-04 Passed Santa Clara County Fire
PW - DEPARTMENT FINAL 2020-07-08 Passed Kevin Rieden
FINAL BUILDING 2020-07-13 Passed James Lee
EVERY PERMIT ISSUED SHALL BECOME INVALID UNLESS THE WORK ON THE SITE AUTHORIZED BY SUCH PERMIT IS COMMENCED WITHIN 12 MONTHS AFTER ITS ISSUANCE, OR IF THE WORK
AUTHORIZED ON THE SITE BY SUCH PERMIT IS SUSPENDED OR ABANDONED FOR A PERIOD OF 12 MONTHS AFTER THE TIME THE WORK IS COMMENCED.