20-107 Contract Change Order #02 12-23-2020McClellan Road Separated Bikeways-Phase 2
Project No. 2017-01.07
CONTRACT CHANGE ORDER
DATE:23-Dec-20 CCO#2
P.O.#2021-142
Contractor:Acct. #420-99-036-900-905 ST-029
Granite Construction Company
715 Comstock Street
Santa Clara, CA 95040
Change
No.
2
The following changes are hereby approved, notwithstanding language in any attachment to the contrary, Contractor agrees
that the amount paid pursuant hereto is full and complete compensation for the work described herein for each and every
entity involved in the project who is being compensated hereunder and that each and every claim for any cost for schedule
impact such as a delay, impact, inefficiency, acceleration, extended overhead, increased supervision, compression and all
other factors affecting cost arising from the subject of this Change Order is hereby released and waived by all such
Subcontractors and suppliers at all tiers.
City Authorization
Type and No.Description
Grinding/reduce height of mountable islands
within project area to reduce impacts to
vehicles using driveways.
$33,487.51
Page 1 Change Order #2
McClellan Road Separated Bikeways-Phase 2
Project No. 2017-01.07
CONTRACT CHANGE ORDER
Total Project:
Original Contract
Change Order No.1
Change Order No.2
Revised Contract Total Change Orders
Schedule Impact: 10 Working Days
Project Final Completion Date
November 25, 2020
REVIEWED BY:APPROVED BY:
City of Cupertino City of Cupertino
John Raaymakers Roger Lee
Project Manager Director of Public Works
Date: Date:
CSG Consultants Granite Construction Company
Nourdin Khayata Steve Kaesler
Resident Engineer Construction Manager
Date: Date:
Total
Change Order No.2 $33,487.51
$33,487.51
$1,394.39
$34,881.90
Island Grinding
Temp Fence
$1,422,173.90
1,387,292.00
Page 2 Change Order #2
Steve Kasler
Jan 6, 2021
nourdinkhayata
Jan 6, 2021
Jan 6, 2021
Roger Lee
Jan 6, 2021
McClellan Road Separated Bikeways-Phase 2
Project No. 2017-01.07
CONTRACT CHANGE ORDER
DATE:23-Dec-20 CCO#3
P.O.#2021-142
Contractor:Acct. #420-99-036-900-905 ST-029
Granite Construction Company
715 Comstock Street
Santa Clara, CA 95040
Change
No.
3
The following changes are hereby approved, notwithstanding language in any attachment to the contrary, Contractor
agrees that the amount paid pursuant hereto is full and complete compensation for the work described herein for each
and every entity involved in the project who is being compensated hereunder and that each and every claim for any cost
for schedule impact such as a delay, impact, inefficiency, acceleration, extended overhead, increased supervision,
compression and all other factors affecting cost arising from the subject of this Change Order is hereby released and
waived by all such Subcontractors and suppliers at all tiers.
City Authorization
Type and No.Description
Work entails grinding and repaving
asphalt pavement, removing duct bank,
remove and rebuild island at Felton Way
$12,517.59
Perform various concrete and asphalt
operations to elevate grade and manage
drainage conflicts.
Page 1 Change Order #3
McClellan Road Separated Bikeways-Phase 2
Project No. 2017-01.07
CONTRACT CHANGE ORDER
Total Project:
Original Contract
Change Order No.1
Change Order No. 2
Change Order No. 3 Drainage @ Felton
Revised Contract Total Change Orders
Schedule Impact: 5 Working Days
Project Final Completion Date
REVIEWED BY:APPROVED BY:
City of Cupertino City of Cupertino
John Raaymakers Roger Lee
Project Manager Director of Public Works
Date: Date:
CSG Consultants Granite Construction Company
Nourdin Khayata Steve Kaesler
Resident Engineer Construction Manager
Date: Date:
Total
Change Order No.3 $12,517.59
December 4, 2020
$1,394.39
$33,487.51
$47,399.49
Temp Fence
Island Grinding
$1,434,691.49
$12,517.59
1,387,292.00
Page 2 Change Order #3
Steve Kasler
Jan 6, 2021
nourdinkhayata
Jan 6, 2021
Jan 6, 2021
Roger Lee
Jan 6, 2021
McClellan Road Separated Bikeways-Phase 2
Project No. 2017-01.07
CONTRACT CHANGE ORDER
DATE:23-Dec-20 CCO#4
P.O.#2021-142
Contractor:Acct. #420-99-036-900-905 ST-029
Granite Construction Company
715 Comstock Street
Santa Clara, CA 95040
Change
No.
4
The following changes are hereby approved, notwithstanding language in any attachment to the contrary, Contractor agrees
that the amount paid pursuant hereto is full and complete compensation for the work described herein for each and every
entity involved in the project who is being compensated hereunder and that each and every claim for any cost for schedule
impact such as a delay, impact, inefficiency, acceleration, extended overhead, increased supervision, compression and all
other factors affecting cost arising from the subject of this Change Order is hereby released and waived by all such
Subcontractors and suppliers at all tiers.
City Authorization
Type and No.$3,801.50Description
Perform drainage modifications at
McClellan Road and John Way. Work
entails modifying 12" RCP to avoid conflict
with existing gas line.
Page 1 Change Order #4
McClellan Road Separated Bikeways-Phase 2
Project No. 2017-01.07
CONTRACT CHANGE ORDER
Total Project:
Original Contract
Change Order No.1
Change Order No.2
Change Order No.3 Drainage @ Felton
Change Order No.4 Gas Conflict @ John
Revised Contract Total Change Orders
Schedule Impact: 5 Working Days
Project Final Completion Date
REVIEWED BY:APPROVED BY:
City of Cupertino City of Cupertino
John Raaymakers Roger Lee
Project Manager Director of Public Works
Date: Date:
CSG Consultants Granite Construction Company
Nourdin Khayata Steve Kaesler
Resident Engineer Construction Manager
Date: Date:
$3,801.50
$1,394.39
$33,487.51
$47,399.49
Temp. Fence
Island Grinding
$1,438,492.99
$12,517.59
Total
Change Order No.4 $3,801.50
1,387,292.00
12/10/2020
Page 2 Change Order #4
Steve Kasler
Jan 6, 2021
nourdinkhayata
Jan 6, 2021
Jan 6, 2021
Roger Lee
Jan 6, 2021
Granite Construction CCO #s 2, 3, & 4
Final Audit Report 2021-01-06
Created:2020-12-30
By:Julia Kinst (juliak@cupertino.org)
Status:Signed
Transaction ID:CBJCHBCAABAAljhxthZFQaPB1agshPshcPmDOvQkb_hV
"Granite Construction CCO #s 2, 3, & 4" History
Document created by Julia Kinst (juliak@cupertino.org)
2020-12-30 - 10:58:38 PM GMT- IP address: 64.178.242.15
Document emailed to Steve Kasler (steve.kaesler@gcinc.com) for signature
2020-12-30 - 11:06:07 PM GMT
Email viewed by Steve Kasler (steve.kaesler@gcinc.com)
2020-12-30 - 11:26:13 PM GMT- IP address: 67.170.209.125
Email viewed by Steve Kasler (steve.kaesler@gcinc.com)
2021-01-06 - 5:18:19 PM GMT- IP address: 67.170.209.125
Document e-signed by Steve Kasler (steve.kaesler@gcinc.com)
Signature Date: 2021-01-06 - 5:21:31 PM GMT - Time Source: server- IP address: 67.170.209.125
Document emailed to nourdinkhayata (nourdin@csgengr.com) for signature
2021-01-06 - 5:21:33 PM GMT
Email viewed by nourdinkhayata (nourdin@csgengr.com)
2021-01-06 - 7:08:46 PM GMT- IP address: 98.248.42.52
Document e-signed by nourdinkhayata (nourdin@csgengr.com)
Signature Date: 2021-01-06 - 7:09:28 PM GMT - Time Source: server- IP address: 98.248.42.52
Document emailed to John Raaymakers (johnr@cupertino.org) for signature
2021-01-06 - 7:09:29 PM GMT
Email viewed by John Raaymakers (johnr@cupertino.org)
2021-01-06 - 7:26:08 PM GMT- IP address: 104.47.73.126
Document e-signed by John Raaymakers (johnr@cupertino.org)
Signature Date: 2021-01-06 - 7:29:00 PM GMT - Time Source: server- IP address: 108.201.190.161
Document emailed to Roger Lee (rogerl@cupertino.org) for signature
2021-01-06 - 7:29:02 PM GMT
Email viewed by Roger Lee (rogerl@cupertino.org)
2021-01-06 - 7:33:59 PM GMT- IP address: 104.47.46.254
Document e-signed by Roger Lee (rogerl@cupertino.org)
Signature Date: 2021-01-06 - 7:35:24 PM GMT - Time Source: server- IP address: 24.4.161.237
Agreement completed.
2021-01-06 - 7:35:24 PM GMT