19-071 Contract Change Order #02 09-23-2019CITY OF McClellan Road Separated Bikeways, Phase lb
PROJECT NO.2017-01.06
CONTRACT CHANGE ORDER #2
CUPERTINO
DATE: 9/23/2019 CCO# 2
Contractor:
Redgwick Construction Company
21 Hegenberger Court
Oakland, CA 94621
P.O.# 2019-547
Acct. # 420-99-036-900-905-ST 029-03-01
The following changes are hereby approved, notwithstanding language in any attachment to the contrary, Contractor agrees
that the amount paid pursuant hereto is full and complete compensation for the work described herein for each and every
entity involved in the project who is being compensated hereunder and that each and every claim for any cost for schedule
impact such as a delay, impact, inefficiency, acceleration, extended overhead, increased supervision, compression and all
other factors affecting cost arising from the subject of this Change Order is hereby released and waived by all such
Subcontractors and suppliers at all tiers.
Change
No.
City Authorization
Type and No.
Description
Compensation Change
Relocate existing Electrolier at the Southwest
comer of McClellan Road and September
Drive.
2
ATP#3
$4,950.60
Page 1 Change Order no. 2
CITY OF McClellan Road Separated Bikeways, Phase lb
MPROJECT NO.2017-01.06
CONTRACT CHANGE ORDER #2
CUPERTINO
Total
Change Order No.2 $4,950.60
Total
Original Contract $1,365,420.00
Change Order No.1 $1,557.66
Chanee Order No. 2 $4.950.60
Revised Contract $1,371,928.26 Total Change Orders $6,508.26
Schedule Impact: 0 calendar days
Project Final Completion Date: 9/10/2019
REVIEWED BY: APPRO Y:
..� Y'
C' of Cupertino City of C ertino
John Raaymakers rVA Roger 49e
City Project Manager Director of Public Works
Date:-ZS / r/ Date: 9 Z5
CSG Consultants Redgwick Construction
Michael Ballard Travis Miller
Senior Project Manager Project Manager
Date: 91 z f I I q Date: /® / �/ /f
Page 2 Change Order no. 2