19-071 Contract Change Order #05 09-23-2019CITY OF McClellan Road Separated Bikeways, Phase lb
PROJECT NO.2017-01.06
CONTRACT CHANGE ORDER #5
CUPERTINO
DATE: 9/23/2019 CCO#
Contractor:
Redgwick Construction Company
21 Hegenberger Court
Oakland, CA 94621
P.O.# 2019-547
Acet. # 420-99-036-900-905-ST 029-03-01
The following changes are hereby approved, notwithstanding language in any attachment to the contrary, Contractor agrees
that the amount paid pursuant hereto is full and complete compensation for the work described herein for each and every
entity involved in the project who is being compensated hereunder and that each and every claim for any cost for schedule
impact such as a delay, impact, inefficiency, acceleration, extended overhead, increased supervision, compression and all
other factors affecting cost arising from the subject of this Change Order is hereby released and waived by all such
Subcontractors and suppliers at all tiers.
Change
No.
City Authorization
Type and No.
Description
Compensation Change
Furnish two (2) Trafftcware (Engineered by
Naztec) NEMA P-44 traffic control cabinets
in -lie of two (2) Econolite TS2-1 P44 traffic
control cabinets
5
$17,526.69
Page 1 Change Order no. 5
CITY OF McClellan Road Separated Bikeways, Phase lb
PROJECT NO.2017-01.06
CONTRACT CHANGE ORDER #5
CUPERTINO
Total
Change Order No.5 $17,526.69
fatal Project:
Original Contract
$1,365,420.00
Change Order No.1
$1,557.66
Change Order No. 2
$4,950.60
Change Order No. 3
Based on field measured quantities
Change Order No. 4
$29,000.00
Change Order No. 5
$17,526.69
Revised Contract $1,418,454.95 Total Change Orders $53,034.95
Schedule Impact: 0 calendar days
Project Final Completion Date: 9/10/2019
REVIEWED BY:
--- Zz.
Ci of Cupertino
John Raaymakers
City Project Manager
Date:
h .1, ajo
CSG Consultants
Michael Ballard
Senior Project Manager
Date: I as /11
City of ertino
�t Rogerj&e
Dire or of Public Works
Date: 1
451-19
Redgwick Construction
Travis Miller
Project Manager
Date: /% yI9
Page 2 Change Order no. 5