19-071 Contract Change Order #06 10-28-2019CITY OF McClellan Road Separated Bikeways, Phase lb
Lm, Irm PROJECT NO.2017-01.06
CONTRACT CHANGE ORDER #6
CUPERTINO
DATE: 10/28/2019
Contractor:
Redgwick Construction Company
21 Hegenberger Court
Oakland, CA 94621
CCO# 6
P.O.# 2019-547
Acct. # 420-99-036-900-905-ST 029-03-01
The following changes are hereby approved, notwithstanding language in any attachment to the contrary, Contractor agrees
that the amount paid pursuant hereto is full and complete compensation for the work described herein for each and every
entity involved in the project who is being compensated hereunder and that each and every claim for any cost for schedule
impact such as a delay, impact, inefficiency, acceleration, extended overhead, increased supervision, compression and all
other factors affecting cost arising from the subject of this Change Order is hereby released and waived by all such
Subcontractors and suppliers at all tiers.
Change
No.
City Authorization
Type and No.
Description
Compensation Change
Furnish and install one pedestrian push
button post at the northeast corner of
Stelling and McClellan. Work includes
excavation, foundation construction,
6
mounting of post, conduit, pull box, wiring,
$2,663.74
and all associated hardware
Page 1 Change Order no. 6
CITY OF McClellan Road Separated Bikeways, Phase lb
PROJECT NO.2017-01.06
CONTRACT CHANGE ORDER #6
CUPERTINO
Total
Change Order No.6 $2,663.74
Total Proiect:
Original Contract
$1,365,420.00
Change Order No. 1
$1,557.66
Change Order No. 2
$4,950.60
Change Order No. 3
Based on field measured quantities
Change Order No. 4
$29,000.00
Change Order No. 5
$17,526.69
Change Order No. 6
$2,663.74
Revised Contract $1,421,118.69 Total Change Orders $55,698.69
Schedule Impact: 0 calendar days
Project Final Completion Date: 9/10/2019
REVIEWED BY:
Ci6 of Cupertino
John Raaymakers
City Project Manager
Date: 10-28-2019
CSG Consultants
Michael Ballard
Senior Project Manager
Date: (-t) 130 � ( 5'
APPROVED BY:
City of 6upertino,
Roger Lee
Director of Public Works
Date:
Redgwick Construction
Travis Miller
Project Manager
Date: /'/ 4// j
Page 2 Change Order no. 6