CC 05-31-2022 Item No. 1. The Rise (Vallco) - Supplemental Staff Report_Desk Item      SUPPLEMENTAL CITY COUNCIL STAFF REPORT  Meeting Date: May 31, 2022  Subject  City Manager Report regarding the Rise (Vallco) development ‐ request for modification  of approved SB 35 project pursuant to Government Code section 65913.4(g)  Recommended Action  Receive the report  This additional information is being provided to further clarify and provide additional  information regarding the proposed modifications to the former Vallco Town Center  pursuant to SB 35 project – now The Rise development.   Clarification regarding slope line: As determined in 2018, there are no height limits  applicable to the original or modified project. However, the Community Form Diagram  (Figure LU‐2) in the Land Use Element of the 2018 General Plan identifies building planes  that the project must meet. Figure LU‐2 states as a foot note: “Maintain the primary  building bulk below a 1:1 slope line drawn from the arterial/boulevard curb line or lines  except for the Crossroads Area” and “For the North and South Vallco Park areas (except  for the Vallco Shopping District Special Area): Maintain the primary building bulk below  a 1.5:1 (i.e., 1.5 feet of setback for every 1 foot of building height) slope line drawn from  the Stevens Creek Blvd. and Homestead Road curb lines and below 1:1 slope line drawn  from Wolfe Road and Tantau Avenue curb line.” In 2018, it was determined that the  original project met this standard. The 2022 modified project continues to meet this  standard by maintaining the 1:1 slope line for all proposed buildings, including the green  roof deck, from the arterial/boulevard curb line from Stevens Creek Boulevard. There are  portions of the green roof deck that continue to encroach into the 1:1 slope line from Wolfe  Road; however, the primary building bulk continues to remain outside of the 1:1 slope  line. Slope line sections are indicated on Sheets P‐0845 and P‐0845.01.  Independent Analysis of Floor Area within the development by type of use: As  mentioned in the prior staff report, an independent analysis of the square footages was  initiated by the City.   M‐2022‐001, ASA‐2022‐003, TR‐2022‐015    May 31, 2022  The Rise (Vallco) Development – Supplemental Staff Report Page 2    The following table shows the square footage of various uses provided by the applicant  and the square footage calculated by the City’s consultant, based on plans submitted by  the applicant. Any methodological differences between the applicant’s calculation and  the City’s review do not impact the project’s compliance with SB 35 criteria or applicable  objective standards.   Approved  (2018)  % of  Total  2022 Project  Plans (SF)  % of  Total  2022 Modification  (SF)  % of  Total  Residential 4,961,904 66.8 5,119,005 68.1 5,219,907 68.1  Retail  485,912 6.5 429,408 5.7 500,344 6.5  Office 1,981,447 26.7 1,973,494 26.2 1,949,797 25.4  Total 7,429,263 100 7,521,907 100.0 7,670,348 100.0  Next Steps  The City Manager will make a decision on the applicant’s modification request based on  the criteria for ministerial approval set forth in Government Code section 65913.4(g). The  60‐day review period under section 65913.4(g) expires on June 3, 2022.    Prepared by:        Piu Ghosh, Planning Manager   Reviewed by:  Benjamin Fu, Director of Community Development  Christopher Jensen, City Attorney  Approved for Submission: Jim Throop, City Manager